AR-L1288 : Social and Urban Integration Program in Greater Buenos Aires
Project Status: Implementation
The general objective of the CCLIP and its first operation is to improve living conditions in shantytowns, informal neighborhoods, and housing complexes in the Province of Buenos Aires through social and urban integration interventions. The specific objectives of the first operation are to: (i) strengthen and support local and provincial governments in the planning, management, and execution of comprehensive informal neighborhood intervention and regularization projects; (ii) improve access to and facilitate the use of basic utilities, resilient urban infrastructure, public spaces, community facilities, and government services for the residents of these neighborhoods, thereby integrating them into the municipal urban fabric; and (iii) strengthen social capital, increase opportunities for social, labor, and productive community development, and improve habitability and tenure conditions
Project Detail
Approval date
July 02, 2019
Project Country
Argentina
Project Sector
URBAN DEVELOPMENT AND HOUSING
Project Subsector
NEIGHBORHOOD UPGRADING
Project Type
Loan Operation
Project Modality
GOM (Global of Multiple Works Operation)
Environmental and social impact category
B
Project Status
Implementation
Operation Number
4823/OC-AR
Financial Information
Project Status
Implementation
IDB Financing
Reporting currency
USD - United States Dollar
Reporting date
Mar/28/2023
Roles & Responsibilities
Contract signature date
Dec/23/2020
Preparation
Title
Type
Project Number
Date Published
Resettlement Plans
AR-L1288
May 21, 2019
Resettlement Plans
AR-L1288
May 21, 2019
Environmental and Social Management Plan
AR-L1288
May 21, 2019
Environmental Impact Assessments
AR-L1288
May 21, 2019
Project Profile
AR-L1288
April 04, 2019
Environmental Impact Assessments
AR-L1288
September 28, 2018
Resettlement Plans
AR-L1288
September 28, 2018
Environmental Impact Assessments
AR-L1288
September 28, 2018
Environmental Impact Assessments
AR-L1288
September 28, 2018
Environmental Impact Assessments
AR-L1288
September 28, 2018
Approved
Title
Type
Project Number
Date Published
Loan Contract
AR-L1288
April 05, 2022
Loan Contract
AR-L1288
February 03, 2021
Loan Contract
AR-L1288;AR-O0012
July 26, 2019
Loan Contract
AR-L1288
July 26, 2019
Loan Contract
AR-L1288
July 26, 2019
Loan Contract
AR-L1288;AR-O0012
July 26, 2019
Loan Proposal
AR-L1288
June 20, 2019
Loan Proposal
AR-L1288
June 19, 2019
Implementation
Title
Type
Project Number
Date Published
Project Monitoring Report ( Public version)
AR-L1288
February 07, 2023
Project Monitoring Report ( Public version)
AR-L1288
August 11, 2022
Project Monitoring Report ( Public version)
AR-L1288
February 16, 2022
Specific Procurement Notices
AR-L1288
December 01, 2021
Project Monitoring Report ( Public version)
AR-L1288
July 20, 2021
Project Monitoring Report ( Public version)
AR-L1288
March 08, 2021
Project Monitoring Report ( Public version)
AR-L1288
August 24, 2020