Skip to main content
Additional Financing for George Price Highway Rehabilitation Project
The general objective is to contribute to the productivity and economic integration of Belize. The specific objective of the supplementary additional financing is to provide additional resources to complete the George Price Highway (GPH) Rehabilitation Project (3344/OC-BL), which aims to substantially improve the road connectivity within Belize's main districts and with Central America. This will be achieved through the rehabilitation of the GPH road infrastructure between miles 47.9 in Belmopan and 67.3 in Santa Elena to national standards, thereby decreasing travel time and costs, reducing road fatalities and injuries, and ensuring road accessibility by improving the Climate Change (CC) resilience of the corridor.

Project Detail

Country

Belize

Project Number

BL-L1029

Approval Date

September 26, 2018

Project Status

Closed

Project Type

Loan Operation

Sector

TRANSPORT

Subsector

MAJOR HIGHWAYS

Lending Instrument

Préstamo de Inversión

Lending Instrument Code

INV

Modality

ESP (Specific Investment Operation)

Facility Type

-

Environmental Classification

Likely to cause mostly local and short-term negative environmental and associated social impacts and for which effective mitigation measures are readily available

Total Cost

USD 7,000,000.00

Country Counterpart Financing

USD 0.00

Original Amount Approved

USD 7,000,000.00

Financial Information
Operation Number Lending Type Reporting Currency Reporting Date Signed Date Fund Financial Instrument
4616/OC-BL Sovereign Guaranteed USD - United States Dollar Ordinary Capital Flexible Financing Facility
Operation Number 4616/OC-BL
  • Lending Type: Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: Ordinary Capital
  • Financial Instrument: Flexible Financing Facility

Can’t find a document? Request information

Implementation Phase
https://www.iadb.org/document.cfm?id=EZIDB0000102-1584871705-86
Annual Project Audited Financial Statement
Final Audited Financial Statements.pdf
Apr. 18, 2024
English
https://www.iadb.org/document.cfm?id=EZIDB0000578-522669563-44065
Project Monitoring Report ( Public version)
BL-L1029 First period Jan-Jun 2023 - Public Report.PDF
Jan. 26, 2024
English
https://www.iadb.org/document.cfm?id=EZIDB0000102-1424282337-866
Procurement Plan
BL-L1029 Additional Financing for George Price Highway Rehabilitation Project - Procurement Plan as of August 22, 2023.pdf
Aug. 24, 2023
English
https://www.iadb.org/document.cfm?id=EZIDB0000102-1584871705-56
Annual Project Audited Financial Statement
AF GPHRP contract Audited Financial Statement- Supporting Document.pdf
Sep. 01, 2023
English
https://www.iadb.org/document.cfm?id=EZIDB0000171-1375635338-35759
Specific Procurement Notices
BL-L1029_P2043255_SP.pdf
Jul. 24, 2023
English
https://www.iadb.org/document.cfm?id=EZIDB0000578-522669563-43873
Project Monitoring Report ( Public version)
BL-L1029 Second period Jan-Dec 2022 - Public Report.PDF
Jul. 19, 2023
English
https://www.iadb.org/document.cfm?id=EZIDB0000102-1424282337-833
Procurement Plan
BL-L1029 Additional Financing for George Price Highway Rehabilitation Project - Procurement Plan as of June 14, 2023.pdf
Jun. 19, 2023
English
https://www.iadb.org/document.cfm?id=EZIDB0000102-1424282337-769
Procurement Plan
BL-L1029 Additional Financing for George Price Highway Rehabilitation Project - Procurement Plan as of April 17 2023.pdf
Apr. 19, 2023
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-42156
Project Monitoring Report ( Public version)
BL-L1029 First period Jan-Jun 2022 - Public Report.PDF
Feb. 07, 2023
English
https://www.iadb.org/document.cfm?id=EZSHARE-1424282337-670
Procurement Plan
BL-L1029 Additional Financing for George Price Highway Rehabilitation Project - Procurement Plan as of November 29, 2022.pdf
Dec. 11, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-1375635338-34509
Specific Procurement Notices
BL-L1029_P1108177_SP.pdf
Nov. 28, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-1584871705-44
Annual Project Audited Financial Statement
Annual Project Audited Financial Statement.pdf
Aug. 23, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-40876
Project Monitoring Report ( Public version)
BL-L1029 Second period Jan-Dec 2021 - Public Report.PDF
Aug. 11, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-1424282337-492
Procurement Plan
BL-L1029 Additional Financing for George Price Highway Rehabilitation Project - Procurement Plan as of July 18, 2022.pdf
Jul. 21, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-1424282337-391
Procurement Plan
BL-L1029 Additional Financing for George Price Highway Rehabilitation Project - Procurement Plan as of May 31, 2022.pdf
Jun. 01, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-1424282337-375
Procurement Plan
BL-L1029 Additional Financing for George Price Highway Rehabilitation Project - Procurement Plan as of May 18, 2022.pdf
May. 19, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-1424282337-278
Procurement Plan
BL-L1029 Additional Financing for George Price Highway Rehabilitation Project - Procurement Plan as of March 8, 2022.pdf
Mar. 08, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-35296
Project Monitoring Report ( Public version)
BL-L1029 First period Jan-Jun 2021 - Public Report.pdf
Feb. 16, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-1424282337-179
Procurement Plan
BL-L1029 Additional Financing for George Price Highway Rehabilitation Project - Revised Procurement Plan 12Jan2022.pdf
Jan. 14, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-1424282337-144
Procurement Plan
BL-L1029 Additional Financing for George Price Highway Rehabilitation Project - Procurement Plan 28Nov2021.pdf
Dec. 02, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-1424282337-126
Procurement Plan
BL-L1019_BL-L1029 George Price Highway Rehabilitation Project - Revised Procurement Plan as of October 6, 2021.pdf
Oct. 08, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-1375635338-31671
Specific Procurement Notices
BL-L1029_P794629_SP.pdf
Aug. 06, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-34665
Project Monitoring Report ( Public version)
BL-L1029 Second period Jan-Dec 2020 - Public Report.pdf
Jul. 21, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-34093
Project Monitoring Report ( Public version)
BL-L1029 First period Jan-Jun 2020 - Public Report.pdf
Mar. 09, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-33344
Project Monitoring Report ( Public version)
BL-L1029 Second period Jan-Dec 2019-Public Report.pdf
Aug. 24, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-1375635338-25712
General Procurement Notices
BL-L1029_5992_GN.pdf
Jun. 29, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-1470197173-48132
Loan Contract
Additional Financing for George Price Highway Rehabilitation Project.pdf
Dec. 10, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-6217
Loan Contract
Contract - Additional Financing for George Price Highway Rehabilitation Project.pdf
Apr. 17, 2019
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-74
Loan Proposal
Belize. Proposal for a loan for Additional Financing for George Price Highway Rehabilitation Project.pdf
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-38
Loan Proposal
EER2 Monitoring and evaluation plan BL-L1029.docx
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-32022
Project Monitoring Report ( Public version)
BL-L1029 Second period Jan-Dec 2018-Public Report.pdf
Oct. 15, 2019
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-75
Loan Proposal
Belize. Propuesta de prestamo para un Financiamiento Adicional rehabilitacion de la Carretera George Pr.pdf
Sep. 13, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1470197173-48131
Loan Contract
Financiamiento Adicional para el Proyecto de Rehabilitación de la Carretera George Price.pdf
Oct. 03, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-39
Loan Proposal
EER4 Procurement Plan.xlsx
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-32708
Project Monitoring Report ( Public version)
BL-L1029 First period Jan-Jun 2019-Public Report.pdf
Feb. 12, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-20
Loan Proposal
EEO1 technical options and design.pdf
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-42
Loan Proposal
EEO3 Progress Report.pdf
Sep. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-23
Loan Proposal
EEO4 Design Review.pdf
Sep. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-43
Loan Proposal
EER1 PEP.xlsx
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-24
Loan Proposal
EEO5 Integration annex - BL-L1029.docx
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-44
Loan Proposal
EER1 AOP.xlsx
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-25
Loan Proposal
EEO6 Institutional Capacity Assessment System ICAS.doc
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-46
Loan Proposal
EEO2 Analysis of Project Cost and Economic Viability.pdf
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-26
Loan Proposal
EEO7 ESIA and ESMP.pdf
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-47
Loan Proposal
EEO10 Project Operations Manual (POM).doc
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-27
Loan Proposal
EEO8 BL-L1029_2018_Addendum to the ESIA.pdf
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-50
Loan Proposal
EER3 ESMR BL L1029.docx
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-28
Loan Proposal
EEO9 BL-L1029 2018 Resettlement and Livelihoods Restoration Plan.pdf
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-51
Loan Proposal
EEO11 Compliance with IDB Policy on Additional Financing of Cost Overruns.docx
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-35
Loan Proposal
EEO13 Saveguards.pdf
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-62
Loan Proposal
EEO12 Climate Finance.docx
Sep. 13, 2018
English
Other Documents
https://www.iadb.org/document.cfm?id=EZSHARE-1424282337-729
Access to Information
BL-L1029 Additional Financing for George Price Highway Rehabilitation Project Updated Procurement Plan Submitted Jan 17, 2023.pdf
Jan. 23, 2023
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-36
Results Matrix
1. DEM BL-L1029.xlsx
Jan. 29, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-114430752-8
Results Matrix
BL-L1029. Appendix I DEM.xlsx
May. 08, 2019
English
Preparation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-1793277437-14
Environmental Impact Assessments
ESIA 2014 Environmental and Social Impact Assessment for the Rehabilitation of the George Price Highway.pdf
May. 22, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-1793277437-15
Environmental Impact Assessments
BL-L1029 2018 Addendum to the ESIA and ESMP.pdf
May. 23, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-1793277437-17
Environmental and Social Analyses
2018 BL-L1029 Resettlement and Livelihoods Restoration Plan.pdf
May. 25, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1793277437-31
Environmental and Social Analyses
BL-L1029 ESIA Addendum and Updated ESMP 2018 -Final Version.pdf
Aug. 10, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-1793277437-32
Public Consultation Report
BL-L1029 GPH Consultation and Stakeholder Engagement Plan and Report-Final Version.pdf
Aug. 10, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-1793277437-34
Resettlement Plans
BL-L1029 Resettlement and Livelihoods Restoration Plan -Final Version.pdf
Aug. 10, 2018
English

Have an Environmental or Social issue related to IDB projects? File a Complaint

Jump back to top