VE-L1033 : Rehabilitation of Units 1 to 6 of Powerhouse I Simón Bolivar Hydroelectric Plant
Project Status: Implementation
Increase energy efficiency and extend the life of the Guri Hydroelectric Central, through the rehabilitation of the turbine generators 1-6, of a powerhouse.
Project Detail
Project Number
VE-L1033
Approval date
October 27, 2010
Project Country
Venezuela
Project Sector
ENERGY
Project Subsector
NEW HYDROPOWER PROJECTS
Project Type
Loan Operation
Project Lending Type
SG
Project Modality
ESP (Specific Investment Operation)
Project Facility Type
Environmental and social impact category
B
Project Status
Implementation
Operation Number
2429/OC-VE
Financial Information
Project Number
VE-L1033
Project Status
Implementation
IDB Financing
Financing type
SCF
Fund
Ordinary Capital
Reporting currency
USD - United States Dollar
Reporting date
Jul/18/2023
Roles & Responsibilities
Contract signature date
Dec/30/2010
Project Information
Total Cost
USD 1,309,771,000
Country counterpart financing
USD 609,771,000
Amount
USD 700,000,000
Preparation
Title
Type
Project Number
Date Published
Project Profile
VE-L1033
August 26, 2010
Approved
Title
Type
Project Number
Date Published
Loan Contract
2429/OC-VE;VE-L1033
December 17, 2012
Loan Contract
2429/OC-VE;VE-L1033
December 30, 2010
Loan Proposal
VE-L1033
October 29, 2010
Loan Proposal
VE-L1033
October 29, 2010
Implementation
Title
Type
Project Number
Date Published
Project Monitoring Report ( Public version)
VE-L1033
February 08, 2023
Project Monitoring Report ( Public version)
VE-L1033
August 16, 2022
Project Monitoring Report ( Public version)
VE-L1033
February 28, 2022
Project Monitoring Report ( Public version)
VE-L1033
July 20, 2021
Project Monitoring Report ( Public version)
VE-L1033
March 09, 2021
Project Monitoring Report ( Public version)
VE-L1033
August 25, 2020
Project Monitoring Report ( Public version)
VE-L1033
February 12, 2020
Project Monitoring Report ( Public version)
VE-L1033
October 16, 2019
Project Monitoring Report ( Public version)
VE-L1033
December 14, 2018
Project Monitoring Report ( Public version)
VE-L1033
August 03, 2018
Procurement Plan
VE-L1033
July 13, 2018
Project Monitoring Report ( Public version)
VE-L1033
February 15, 2018
Project Monitoring Report ( Public version)
VE-L1033
February 14, 2018
Project Monitoring Report ( Public version)
VE-L1033
December 23, 2016
Procurement Plan
2429/OC-VE;VE-L1033
September 06, 2016
Project Monitoring Report ( Public version)
VE-L1033
June 24, 2016
Project Monitoring Report ( Public version)
VE-L1033
March 15, 2016
Project Monitoring Report ( Public version)
VE-L1033
March 14, 2016
Project Monitoring Report ( Public version)
VE-L1033
March 11, 2016
Project Monitoring Report ( Public version)
VE-L1033
March 10, 2016
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
October 31, 2013
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
October 31, 2013
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
October 31, 2013
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
October 31, 2013
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
May 07, 2013
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
May 07, 2013
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
May 07, 2013
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
May 07, 2013
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
December 11, 2012
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
December 11, 2012
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
December 11, 2012
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
December 11, 2012
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
May 14, 2012
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
May 14, 2012
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
May 14, 2012
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
May 14, 2012
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
November 18, 2011
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
November 18, 2011
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
November 18, 2011
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
November 18, 2011
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
June 22, 2011
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
June 22, 2011
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
June 22, 2011
Project Monitoring Report ( Public version)
2429/OC-VE;VE-L1033
June 22, 2011