VE-L1003 : Tocoma Hydroelectric Power Plant
Project Status: Closed
The project is aimed at satisfying the increasing demand of electricity in the country utilizing the hydraulic resources of the Caroní river and substituting the thermo electric generation to decrease the use of non renewable resources.
Project Detail
Project Number
VE-L1003
Project Country
Venezuela
Project Sector
ENERGY
Project Subsector
NEW HYDROPOWER PROJECTS
Project Type
Loan Operation
Project Lending Type
SG
Project Modality
ESP (Specific Investment Operation)
Project Facility Type
Environmental and social impact category
A(R)
Project Status
Closed
Operation Number
1686/OC-VE
Financial Information
Project Number
VE-L1003
Project Status
Closed
IDB Financing
Financing type
SCF
Fund
Ordinary Capital
Reporting currency
USD - United States Dollar
Reporting date
Sep/21/2023
Roles & Responsibilities
Contract signature date
Nov/14/2006
Project Information
Total Cost
USD 3,061,000,000
Country counterpart financing
USD 2,011,000,000
Amount
USD 750,000,000
Preparation
Title
Type
Project Number
Date Published
Project Concept Document
VE-L1003
March 04, 2005
Project Concept Document
VE-L1003
March 04, 2005
Project Concept Document
VE-L1003;VE-L1006
June 01, 2004
Project Concept Document
VE-L1003;VE-L1006
June 01, 2004
Approved
Title
Type
Project Number
Date Published
Loan Proposal
1686/OC-VE;VE-L1003
November 16, 2005
Loan Proposal
VE-L1003
September 26, 2005
Implementation
Title
Type
Project Number
Date Published
Project Monitoring Report ( Public version)
1686/OC-VE;VE-L1003
May 14, 2012
Project Monitoring Report ( Public version)
1686/OC-VE;VE-L1003
May 14, 2012
Project Monitoring Report ( Public version)
1686/OC-VE;VE-L1003
May 14, 2012
Project Monitoring Report ( Public version)
1686/OC-VE;VE-L1003
May 14, 2012
Project Monitoring Report ( Public version)
1686/OC-VE;VE-L1003
November 18, 2011
Project Monitoring Report ( Public version)
1686/OC-VE;VE-L1003
November 18, 2011
Project Monitoring Report ( Public version)
1686/OC-VE;VE-L1003
November 18, 2011
Project Monitoring Report ( Public version)
1686/OC-VE;VE-L1003
November 18, 2011
Project Monitoring Report ( Public version)
1686/OC-VE;VE-L1003
June 22, 2011
Project Monitoring Report ( Public version)
1686/OC-VE;VE-L1003
June 22, 2011
Project Monitoring Report ( Public version)
1686/OC-VE;VE-L1003
June 22, 2011
Project Monitoring Report ( Public version)
1686/OC-VE;VE-L1003
June 22, 2011
Specific Procurement Notices
1686/OC-VE;VE-L1003
December 20, 2010