Punta del Tigre Combined Cycle Power Generation Project
The objective of this operation is to support the strengthening of the electricity sector to secure the long term supply of energy. The specific objective is to support the development of a combined cycle power generation plant. The plant will be modern and efficient and will help to reduce the vulnerability of the electricity generation to dry years, when hydro power is limited.

Project Detail

Country

Uruguay

Project Number

UR-L1070

Approval Date

December 17, 2012

Project Status

Closed

Project Type

Loan Operation

Sector

ENERGY

Subsector

NEW THERMAL POWER PLANTS

Lending Instrument

Investment Loan

Lending Instrument Code

INV

Modality

ESP (Specific Investment Operation)

Facility Type

-

Environmental Classification

Likely to cause significant negative impacts, or have profound implications affecting natural resources

Total Cost

USD 200,000,000.00

Country Counterpart Financing

USD 0.00

Original Amount Approved

USD 200,000,000.00

Financial Information
Operation Number Lending Type Reporting Currency Reporting Date Signed Date Fund Financial Instrument
2894/OC-UR Sovereign Guaranteed USD - United States Dollar Ordinary Capital Flexible Financing Facility
Operation Number 2894/OC-UR
  • Lending Type: Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: Ordinary Capital
  • Financial Instrument: Flexible Financing Facility

Can’t find a document? Request information

Closed Phase
https://www.iadb.org/document.cfm?id=EZSHARE-494289285-793
Project Completion Report
UR-L1070-PCR- versión aprobada.pdf
Oct. 21, 2020
Spanish
Implementation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-899178216-6
Annual Project Audited Financial Statement
Informe Proyecto Ciclo Combinado Punta del Tigre b al 15 de mayo 2019.pdf
Dec. 10, 2020
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-494289285-7
Project Monitoring Report ( Public version)
UR-L1070 First period Jan-Jun 2016-Public Report [40800004].PDF
Dec. 28, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-494289285-6
Project Monitoring Report ( Public version)
UR-L1070 Second period Jan-Dec 2015-Public Report [40360617].PDF
Jun. 23, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-313220703-2
Annual Project Audited Financial Statement
Informe de Auditoría de los Estados Financieros al 31 de diciembre de 2015 [40277456].PDF
Aug. 10, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-494289285-5
Project Monitoring Report ( Public version)
UR-L1070 First period Jan-Jun 2015-Public Report [40209874].PDF
Mar. 28, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-494289285-4
Project Monitoring Report ( Public version)
UR-L1070 Second period Jan-Dec 2014-Public Report [40177018].PDF
Mar. 11, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-494289285-3
Project Monitoring Report ( Public version)
UR-L1070 First period Jan-Jun 2014-Public Report [40174705].PDF
Mar. 10, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-494289285-2
Project Monitoring Report ( Public version)
UR-L1070 Second period Jan-Dec 2013-Public Report [40169814].PDF
Mar. 08, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-667599345-3
Annual Project Audited Financial Statement
FS-Proyecto de Generación Eléctrica Ciclo Combinado Punta del Tigre [39654394].MSG
Jul. 02, 2015
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-19
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_UR-L1070-2013-1º-Período [38265728].PDF
Mar. 06, 2014
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-20
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_UR-L1070-2013-1º-Período [38266388].PDF
Mar. 06, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-21
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_UR-L1070-2013-1º-Periodo [38267052].PDF
Mar. 06, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-22
Project Monitoring Report ( Public version)
Report for Publication_PMR-_UR-L1070-2013-1º-Period [38267725].PDF
Mar. 06, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-15
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_UR-L1070-2012-2º-Período [37873508].PDF
Jul. 27, 2013
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-16
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_UR-L1070-2012-2º-Período [37874170].PDF
Jul. 27, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-17
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_UR-L1070-2012-2º-Periodo [37874884].PDF
Jul. 27, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-18
Project Monitoring Report ( Public version)
Report for Publication_PMR-_UR-L1070-2012-2º-Period [37875683].PDF
Jul. 27, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-13
Loan Proposal
UR-L1070 - PROYECTO CICLO COMBINADO PUNTA DEL TIGRE B [37331211].PDF
Dec. 12, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-14
Loan Proposal
UR-L1070 - PUNTA DEL TIGRE B COMBINED-CYCLE PROJECT [37331231].PDF
Dec. 12, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-8103
Loan Contract
Contrato - Proyecto Ciclo Combinado Punta del Tigre “B”.pdf
Apr. 29, 2020
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-8104
Loan Contract
Contrato de Garantía - Proyecto Ciclo Combinado Punta del Tigre “B”.pdf
Apr. 29, 2020
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-2275
Project Monitoring Report ( Public version)
UR-L1070 Second period Jan-Dec 2017-Public Report.pdf
Aug. 02, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-238
Project Monitoring Report ( Public version)
UR-L1070 Second period Jan-Dec 2016-Public Report.pdf
Feb. 15, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-31899
Project Monitoring Report ( Public version)
UR-L1070 First period Jan-Jun 2018-Public Report.pdf
Dec. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-32582
Project Monitoring Report ( Public version)
UR-L1070 Second period Jan-Dec 2018-Public Report.pdf
Oct. 16, 2019
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-892
Project Monitoring Report ( Public version)
UR-L1070 First period Jan-Jun 2017-Public Report.pdf
Feb. 15, 2018
English
Other Documents
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-23
Procurement
UR-L1070 [40347639].PDF
Jun. 16, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-667599345-2
Financial Statements
Estados Financieros Auditados al 31_12_2013 [38897625].MSG
Aug. 04, 2014
Spanish
Preparation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-39278
Project Profile
Proyecto Ciclo Combinado Punta del Tigre B [36819575].PDF
Apr. 26, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1621785331-2
Environmental Impact Assessments
EIA - Ciclo Combinado Punta del Tigre B Completo (UR-L1070) [36677536].PDF
Feb. 10, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-12
Environmental Impact Assessments
Ciclo Combinado Punta del Tigre B Parte II [36677725].PDF
Feb. 10, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-209255000-11
Environmental Impact Assessments
Ciclo Combinado Punta del Tigre B Parte I [36677716].PDF
Feb. 10, 2012
Spanish