SU-L1009 : Support to Improve Sustainability of the Electricity Service

Project Status: Closed

The specific objectives are to support the implementation of information technologies in business support tools for EBS, to provide financial support for upgrading critical infrastructure, and to contribute to expand electricity coverage by grid extension and renewable energy systems in the Hinterlands. The main components of the Program are: (i) Improvement of EBS¿ Operations; (ii) Sustainable Rural Electrification; and (iii) Critical Infrastructure.

Project Detail

Project Number
SU-L1009
Project Country
Suriname
Project Sector
ENERGY
Project Subsector
ENERGY
Project Type
Loan Operation
Project Lending Type
SG
Project Modality
ESP (Specific Investment Operation)
Project Facility Type
Environmental and social impact category
C
Project Status
Closed
Operation Number
3059/OC-SU

Financial Information

Project Number
SU-L1009
Project Status
Closed

IDB Financing

Financing type
FFF
Fund
Ordinary Capital
Reporting currency
USD - United States Dollar
Reporting date
May/26/2023

Roles & Responsibilities

Contract signature date
Dec/04/2013

Project Information

Total Cost
USD 30,000,000
Country counterpart financing
USD 0
Amount
USD 30,000,000

Preparation

Title
Type
Project Number
Date Published
Project Profile
SU-L1009
September 01, 2013

Approved

Title
Type
Project Number
Date Published
Loan Proposal
SU-L1009
November 06, 2013
Loan Proposal
SU-L1009
November 06, 2013
Loan Proposal
SU-L1009
November 06, 2013
Loan Proposal
SU-L1009
November 06, 2013
Loan Proposal
SU-L1009
November 06, 2013
Loan Proposal
SU-L1009;SU-L1035
November 06, 2013
Loan Proposal
SU-L1009
November 06, 2013
Loan Contract
3059/OC-SU;SU-L1009
November 06, 2013
Loan Contract
3059/OC-SU;SU-L1009
November 06, 2013

Implementation

Title
Type
Project Number
Date Published
Specific Procurement Notices
SU-L1009
December 07, 2021
Annual Project Audited Financial Statement
SU-L1009
December 06, 2021
Project Monitoring Report ( Public version)
SU-L1009
July 20, 2021
Project Monitoring Report ( Public version)
SU-L1009
March 09, 2021
Specific Procurement Notices
SU-L1009
February 01, 2021
Annual Project Audited Financial Statement
SU-L1009
December 10, 2020
Project Monitoring Report ( Public version)
SU-L1009
August 25, 2020
Specific Procurement Notices
SU-L1009
July 20, 2020
Project Monitoring Report ( Public version)
SU-L1009
February 12, 2020
Specific Procurement Notices
SU-L1009
February 07, 2020
Project Monitoring Report ( Public version)
SU-L1009
October 16, 2019
Procurement Plan
SU-L1009
February 11, 2019
Project Monitoring Report ( Public version)
SU-L1009
December 14, 2018
Procurement Plan
SU-L1009
September 10, 2018
Project Monitoring Report ( Public version)
SU-L1009
August 02, 2018
Financial Statements
SU-L1009
June 07, 2018
Project Monitoring Report ( Public version)
SU-L1009
February 15, 2018
Project Monitoring Report ( Public version)
SU-L1009
February 15, 2018
Procurement Plan
SU-L1009
May 09, 2017
Project Monitoring Report ( Public version)
SU-L1009
December 27, 2016
Project Monitoring Report ( Public version)
SU-L1009
June 23, 2016
Project Monitoring Report ( Public version)
SU-L1009
March 28, 2016
Project Monitoring Report ( Public version)
SU-L1009
March 11, 2016
Project Monitoring Report ( Public version)
SU-L1009
March 10, 2016
Project Monitoring Report ( Public version)
SU-L1009
March 08, 2016
Procurement Plan
SU-L1009
August 27, 2013

Completed

Title
Type
Project Number
Date Published
Project Completion Report
SU-L1009
February 18, 2022