RG-L1112 : Sustainable Energy Facility (SEF) for the Eastern Caribbean EXPANDED - (SEF EXPANDED)
Project Status: Implementation
the objective of the SEF-Expanded is to reduce the financial, technical and institutional barriers which Geothermal Energy (GE) development encounters in the Five Eastern Caribbean Countries (5ECC),(g)and to provide institutional strengthening and capacity building to the governments of the 5ECC and to the CDB for GEdevelopment.
Project Detail
Project Number
RG-L1112
Approval date
December 12, 2018
Project Country
Regional
Project Sector
ENERGY
Project Subsector
ENERGY INSTITUTIONAL STRENGTHENING AND CAPACITY BUILDING
Project Type
Loan Operation
Project Lending Type
SG
Project Modality
GCR (Global Credit Operation)
Project Facility Type
Environmental and social impact category
B13
Project Status
Implementation
Operation Number
4712/GN-RG
Financial Information
Project Number
RG-L1112
Project Status
Implementation
IDB Financing
Financing type
PTF
Fund
Green Climate Fund
Reporting currency
USD - United States Dollar
Reporting date
Jul/19/2023
Roles & Responsibilities
Contract signature date
Dec/11/2019
Project Information
Total Cost
USD 60,000,000
Country counterpart financing
USD 0
Amount
USD 60,000,000
Preparation
Title
Type
Project Number
Date Published
Environmental Impact Assessments
RG-L1112
February 16, 2022
Environmental Impact Assessments
RG-L1071, RG-L1112, RG-G1004, RG-G1009, RG-G1013
February 04, 2021
Environmental Analyses
RG-L1112
December 08, 2020
Environmental Analyses
RG-L1112
December 08, 2020
Project Profile
RG-L1112
September 26, 2017
Approved
Title
Type
Project Number
Date Published
Loan Contract
RG-L1112
January 28, 2020
Technical Cooperation Agreement
RG-L1112;RG-T3170;RG-G1013
March 07, 2019
Technical Cooperation Agreement
RG-L1112;RG-T3170;RG-G1013
March 07, 2019
Loan Contract
RG-L1112
January 15, 2019
Loan Contract
RG-L1112
January 15, 2019
Loan Proposal
RG-L1112
December 10, 2018
Loan Proposal
RG-L1112
December 10, 2018
Loan Proposal
RG-L1112
December 10, 2018
Implementation
Title
Type
Project Number
Date Published
Project Monitoring Report ( Public version)
RG-L1112
February 08, 2023
Environmental and Social Execution
RG-L1112
November 02, 2022
Annual Project Audited Financial Statement
RG-L1112
October 27, 2022
Project Monitoring Report ( Public version)
RG-L1112
August 15, 2022
Project Monitoring Report ( Public version)
RG-L1112
February 28, 2022
Annual Project Audited Financial Statement
RG-L1112
December 07, 2021
Annual Project Audited Financial Statement
RG-L1112
December 03, 2021
Project Monitoring Report ( Public version)
RG-L1112
July 20, 2021
Project Monitoring Report ( Public version)
RG-L1112
March 09, 2021
Environmental and Social Execution
RG-L1112
February 26, 2021
Environmental and Social Execution
RG-L1112
February 10, 2021
Environmental and Social Execution
RG-L1112
February 10, 2021
Environmental and Social Execution
RG-L1112
February 09, 2021
Environmental and Social Execution
RG-L1112
December 14, 2020
Environmental and Social Execution
RG-L1112
December 14, 2020
Environmental and Social Execution
RG-L1112
August 27, 2020
Environmental and Social Execution
RG-L1112
August 27, 2020
Environmental and Social Execution
RG-L1112
August 27, 2020
Environmental and Social Execution
RG-L1112
August 27, 2020
Environmental and Social Execution
RG-L1112
August 27, 2020
Environmental and Social Execution
RG-L1112
August 27, 2020
Project Monitoring Report ( Public version)
RG-L1112
August 25, 2020
Project Monitoring Report ( Public version)
RG-L1112
February 12, 2020
Project Monitoring Report ( Public version)
RG-L1112
October 16, 2019