Downtown Redevelopment, Modernization Metropolitan Public Transport, Gov Offices
The general objective is to improve the quality of life of the population in the intervention area through the rehabilitation and upgrading of urban and transportation infrastructure.

Project Detail

Country

Paraguay

Project Number

PR-L1044

Approval Date

September 29, 2010

Project Status

Implementation

Project Type

Loan Operation

Sector

TRANSPORT

Subsector

TRANSPORT

Lending Instrument

Investment Loan

Lending Instrument Code

INV

Modality

ESP (Specific Investment Operation)

Facility Type

-

Environmental Classification

Likely to cause mostly local and short-term negative environmental and associated social impacts and for which effective mitigation measures are readily available

Total Cost

USD 125,000,000.00

Country Counterpart Financing

USD 0.00

Original Amount Approved

USD 125,000,000.00

Financial Information
Operation Number Lending Type Reporting Currency Reporting Date Signed Date Fund Financial Instrument
2419/OC-PR Sovereign Guaranteed USD - United States Dollar Ordinary Capital Single Currency Facility
2420/BL-PR Sovereign Guaranteed USD - United States Dollar Ordinary Capital Single Currency Facility and Concessional Financing
2420/BL-PR-1 Sovereign Guaranteed USD - United States Dollar Ordinary Capital Single Currency Facility and Concessional Financing
Operation Number 2419/OC-PR
  • Lending Type: Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: Ordinary Capital
  • Financial Instrument: Single Currency Facility
Operation Number 2420/BL-PR
  • Lending Type: Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: Ordinary Capital
  • Financial Instrument: Single Currency Facility and Concessional Financing
Operation Number 2420/BL-PR-1
  • Lending Type: Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: Ordinary Capital
  • Financial Instrument: Single Currency Facility and Concessional Financing

Can’t find a document? Request information

Implementation Phase
https://www.iadb.org/document.cfm?id=EZIDB0000578-522669563-44421
Project Monitoring Report ( Public version)
PR-L1044 First period Jan-Jun 2023 - Public Report.PDF
Jan. 29, 2024
English
https://www.iadb.org/document.cfm?id=EZIDB0000452-310855587-891
Annual Project Audited Financial Statement
2419 OC-PR- 2420 OC-PR- 2420 BL-PR-1- EFAs Ejercicio Fiscal 2023.pdf
Apr. 11, 2024
Spanish
https://www.iadb.org/document.cfm?id=EZIDB0000578-522669563-43762
Project Monitoring Report ( Public version)
PR-L1044 Second period Jan-Dec 2022 - Public Report.PDF
Jul. 21, 2023
English
https://www.iadb.org/document.cfm?id=EZIDB0000452-310855587-731
Annual Project Audited Financial Statement
2419-OC-PR 2420-BL-PR 2420-BL-PR-1-EFAS - Ejercicio Fiscal 2022.pdf
Jun. 27, 2023
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-42468
Project Monitoring Report ( Public version)
PR-L1044 First period Jan-Jun 2022 - Public Report.PDF
Feb. 07, 2023
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-41233
Project Monitoring Report ( Public version)
PR-L1044 Second period Jan-Dec 2021 - Public Report.PDF
Aug. 15, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-1375635338-33405
Specific Procurement Notices
PR-L1044_P980305_SP.pdf
May. 24, 2022
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-310855587-695
Annual Project Audited Financial Statement
2419 OC-PR, 2420 BL-PR, 2420 BL-PR-1 y OFID 1386 EFAS Ejercicio fiscal 2021.pdf
Jun. 08, 2022
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-35775
Project Monitoring Report ( Public version)
PR-L1044 First period Jan-Jun 2021 - Public Report.pdf
Feb. 22, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-35192
Project Monitoring Report ( Public version)
PR-L1044 Second period Jan-Dec 2020 - Public Report.pdf
Jul. 20, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-1184211406-3907
Annual Project Audited Financial Statement
2419-OC-PR 2420-BL-PR 2420-BL-PR-1 EFAs Ejercicio fiscal 2020_04302021185844.pdf
Jul. 05, 2021
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-34355
Project Monitoring Report ( Public version)
PR-L1044 First period Jan-Jun 2020 - Public Report.pdf
Mar. 09, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-33775
Project Monitoring Report ( Public version)
PR-L1044 Second period Jan-Dec 2019-Public Report.pdf
Aug. 25, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-1184211406-3838
Annual Project Audited Financial Statement
2419-OC-PR 2420-BL-PR EFAS Ejercicio fiscal 2019.pdf
Dec. 07, 2020
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-310855587-603
Annual Project Audited Financial Statement
2419-OC-PR y 2420-BL-PR EFAS Ejercicio fiscal 2018.pdf
Sep. 14, 2020
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-7814
Loan Contract
Contrato - Proyecto para la Reconversión Centro, Modernización del Transporte Público Metropolitano y Oficinas del Gobierno.pdf
Feb. 16, 2021
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-953
Specific Procurement Notices
PR-L1044 [40846422].PDF
Feb. 13, 2017
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-519715153-7
Project Monitoring Report ( Public version)
PR-L1044 First period Jan-Jun 2016-Public Report [40799856].PDF
Dec. 28, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-61
Loan Proposal
Link Electronico Mandatorio Informe de Gestión Ambiental y Social_(IGAS) [40768625].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-58
Specific Procurement Notices
PR-L1044 [40718189].PDF
Oct. 26, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-59
Specific Procurement Notices
PR-L1044 [40718412].PDF
Oct. 26, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-54
Specific Procurement Notices
PR-L1044 [40372661].PDF
Jul. 01, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-55
Specific Procurement Notices
PR-L1044 [40372663].PDF
Jul. 01, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-519715153-6
Project Monitoring Report ( Public version)
PR-L1044 Second period Jan-Dec 2015-Public Report [40359917].PDF
Jun. 23, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-52
Specific Procurement Notices
PR-L1044 [40341238].PDF
Jun. 13, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-519715153-5
Project Monitoring Report ( Public version)
PR-L1044 First period Jan-Jun 2015-Public Report [40209655].PDF
Mar. 28, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-519715153-4
Project Monitoring Report ( Public version)
PR-L1044 Second period Jan-Dec 2014-Public Report [40176544].PDF
Mar. 11, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-519715153-3
Project Monitoring Report ( Public version)
PR-L1044 First period Jan-Jun 2014-Public Report [40174258].PDF
Mar. 10, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-519715153-2
Project Monitoring Report ( Public version)
PR-L1044 Second period Jan-Dec 2013-Public Report [40169588].PDF
Mar. 08, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-51
Specific Procurement Notices
PR-L1044 [39997302].PDF
Dec. 01, 2015
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-50
Specific Procurement Notices
PR-L1044 [39916718].PDF
Oct. 21, 2015
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-49
Specific Procurement Notices
PR-L1044 [39907339].PDF
Oct. 15, 2015
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-48
Specific Procurement Notices
PR-L1044 [39888584].PDF
Oct. 02, 2015
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-47
Specific Procurement Notices
PR-L1044 [39863573].PDF
Sep. 19, 2015
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-46
Specific Procurement Notices
PR-L1044 [39636660].PDF
May. 19, 2015
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-45
Specific Procurement Notices
PR-L1044 [39622807].PDF
May. 11, 2015
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-44
Specific Procurement Notices
PR-L1044 [39539097].PDF
Mar. 31, 2015
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-43
Specific Procurement Notices
PR-L1044 [39300188].PDF
Dec. 17, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-42
Specific Procurement Notices
PR-L1044 [39266498].PDF
Dec. 03, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-41
Specific Procurement Notices
PR-L1044 [39226645].PDF
Nov. 14, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-40
Specific Procurement Notices
PR-L1044 [39226641].PDF
Nov. 14, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-39
Specific Procurement Notices
PR-L1044 [39091765].PDF
Oct. 01, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-38
Specific Procurement Notices
PR-L1044 [39081501].PDF
Sep. 26, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-34
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_PR-L1044-2013-1º-Período [38265657].PDF
Mar. 06, 2014
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-35
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_PR-L1044-2013-1º-Período [38266321].PDF
Mar. 06, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-36
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_PR-L1044-2013-1º-Periodo [38266985].PDF
Mar. 06, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-37
Project Monitoring Report ( Public version)
Report for Publication_PMR-_PR-L1044-2013-1º-Period [38267658].PDF
Mar. 06, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-31
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_PR-L1044-2012-2º-Período [37874105].PDF
Jul. 27, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-32
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_PR-L1044-2012-2º-Periodo [37874796].PDF
Jul. 27, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-33
Project Monitoring Report ( Public version)
Report for Publication_PMR-_PR-L1044-2012-2º-Period [37875608].PDF
Jul. 27, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-30
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_PR-L1044-2012-2º-Período [37873437].PDF
Jul. 27, 2013
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-26
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_PR-L1044-2012-1º-Período [37352332].PDF
Dec. 19, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-27
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_PR-L1044-2012-1º-Período [37353001].PDF
Jan. 21, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-28
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_PR-L1044-2012-1º-Periodo [37353659].PDF
Jan. 21, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-29
Project Monitoring Report ( Public version)
Report for Publication_PMR-_PR-L1044-2012-1º-Period [37354319].PDF
Jan. 21, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-22
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_PR-L1044-2011-2º-Período [36919925].PDF
Nov. 28, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-23
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_PR-L1044-2011-2º-Período [36923356].PDF
Nov. 28, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-24
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_PR-L1044-2011-2º-Periodo [36925979].PDF
Nov. 28, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-25
Project Monitoring Report ( Public version)
Report for Publication_PMR-_PR-L1044-2011-2º-Period [36928718].PDF
Nov. 28, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-20
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_PR-L1044-2011-1º-Periodo [36625328].PDF
Jan. 12, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-21
Project Monitoring Report ( Public version)
Report for Publication_PMR-_PR-L1044-2011-1º-Period [36625888].PDF
Jan. 12, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-18
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_PR-L1044-2011-1º-Período [36624191].PDF
Jan. 12, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-19
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_PR-L1044-2011-1º-Período [36624774].PDF
Jan. 12, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-56
Consultant/Firm Final Report
Estudio de Impacto Ambiental (Metrobús) [40450555].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-14
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_PR-L1044-2010-2º-Período [36311759].PDF
Aug. 10, 2011
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-15
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_PR-L1044-2010-2º-Período [36312337].PDF
Aug. 10, 2011
French
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-16
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_PR-L1044-2010-2º-Periodo [36312919].PDF
Aug. 10, 2011
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-17
Project Monitoring Report ( Public version)
Report for Publication_PMR-_PR-L1044-2010-2º-Period [36313496].PDF
Aug. 10, 2011
English
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-12
Loan Proposal
PIC_ PARAGUAY_ Reconversión Centro, Modernización del Transporte Público Metropolitano y Oficinas de Gobierno (P [35382302].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-13
Loan Proposal
PIC_ PARAGUAY_ Downtown Redevelopment, Modernization of Metropolitan Public Transport and Government Offices (PR [35382314].PDF
Dec. 31, 1999
English
https://www.iadb.org/document.cfm?id=EZSHARE-1709244737-2
Loan Proposal
Link Electronico Mandatorio_ Informe de Gestión Ambiental y Social (IGAS) _ POD [35294363].doc
Dec. 06, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-5275
Loan Contract
Contrato Modificatorio No.3 - Reconversión Centro, Modernización del Transporte Público Metropolitano y Oficinas del Gobierno.pdf
May. 31, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-31832
Project Monitoring Report ( Public version)
PR-L1044 First period Jan-Jun 2018-Public Report.pdf
Dec. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-494156146-8
Loan Proposal
EEO_7_Plan Maestro Puerto.pdf
Sep. 19, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-32510
Project Monitoring Report ( Public version)
PR-L1044 Second period Jan-Dec 2018-Public Report.pdf
Oct. 16, 2019
English
https://www.iadb.org/document.cfm?id=EZSHARE-494156146-9
Loan Proposal
Paraguay. Proposed amendment of loans 2420-BL-PR and 1880-BL-PR for the Downtown Redevelopment Modernization of Metropolitan Public Transport and Government.pdf
Sep. 18, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-33131
Project Monitoring Report ( Public version)
PR-L1044 First period Jan-Jun 2019-Public Report.pdf
Feb. 12, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-1983553961-4436
Loan Contract
Modificación de los programas Escuela Viva II y Reconversión del Centro Modernización del Transporte Público Metropolitano y Oficinas de Gobierno.pdf
Sep. 13, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1983553961-4437
Loan Contract
Modification of Programs Escuela Viva II & Downtown Redevelopment Modernization of Metropolitan Public Transport and Government Offices.pdf
Sep. 13, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-5267
Loan Contract
Contrato - Capital Ordinario - Reconversión Centro, Modernización del Transporte Público Metropolitano y Oficinas del Gobierno.PDF
May. 31, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-376
Project Monitoring Report ( Public version)
PR-L1044 Second period Jan-Dec 2016-Public Report.pdf
Feb. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-5269
Loan Contract
Contrato - Blend - Reconversión Centro, Modernización del Transporte Público Metropolitano y Oficinas del Gobierno.PDF
May. 31, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1132444900-20588
Specific Procurement Notices
PR-L1044 1327.pdf
Nov. 09, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-494156146-10
Loan Proposal
Paraguay. Propuesta de modificacion a los prestamos 2420-BL-PR y 1880-BL-PR del Programa Reconversion del Centro Modernizacion del Transporte Publico
Sep. 18, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-5271
Loan Contract
Contrato Modificatorio Nº 1 - Reconversión Centro, Modernización del Transporte Público Metropolitano y Oficinas del Gobierno.pdf
May. 31, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-1029
Project Monitoring Report ( Public version)
PR-L1044 First period Jan-Jun 2017-Public Report.pdf
Feb. 15, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-1132444900-23796
Specific Procurement Notices
PR-L1044 1273.pdf
Oct. 07, 2019
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-494156146-11
Loan Proposal
IGAS_FINAL_31-10-20101.pdf
May. 21, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-5273
Loan Contract
Contrato Modificatorio Nº 2 - Reconversión Centro, Modernización del Transporte Público Metropolitano y Oficinas.pdf
May. 31, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-2344
Project Monitoring Report ( Public version)
PR-L1044 Second period Jan-Dec 2017-Public Report.pdf
Aug. 06, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-494156146-7
Loan Proposal
EEO_6_Plan de Ejecución Plurianual (PEP)_PR-L1044.xlsx
Jul. 12, 2019
Spanish
Other Documents
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-60
Progress Report
Plan Director Reasentamiento- Programa RU-BRT [40752373].PDF
Dec. 06, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-43895
Independent Consultation and Investigation Mechanism
MICI-BID-PR-2016-0101 Memorandum de Elegibilidad en español - para web [40433817].PDF
Aug. 26, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-43984
Independent Consultation and Investigation Mechanism
MICI-BID-PR-2016-0101 Memorandum de Elegibilidad en inglés - para web [40433796].PDF
Aug. 26, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-44071
Independent Consultation and Investigation Mechanism
MICI-BID-PR-2016-0101_Managemente_Response_Redacted [40387460].PDF
Jul. 12, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-44077
Independent Consultation and Investigation Mechanism
MICI-BID-PR-2016-0101_Respuesta_de_la_Administración_Redacted [40387462].PDF
Jul. 12, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-44060
Independent Consultation and Investigation Mechanism
MICI-BID-PR-2016-0101_NOTIFICACIÓN_DE_REGISTRO_DE_SOLICITUD-PORTUGUESE_web [40333960].PDF
Jun. 09, 2016
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-44027
Independent Consultation and Investigation Mechanism
MICI-BID-PR-2016-0101 Solicitud Original-PORTUGUESE_web [40333952].PDF
Jun. 09, 2016
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-44057
Independent Consultation and Investigation Mechanism
MICI-BID-PR-2016-0101_NOTIFICACIÓN_DE_REGISTRO_DE_SOLICITUD_ENGLISH_WEB [40325892].PDF
Jun. 09, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-44063
Independent Consultation and Investigation Mechanism
MICI-BID-PR-2016-0101_NOTIFICACIÓN_DE_REGISTRO_DE_SOLICITUD_FRE_WEB [40327563].PDF
Jun. 09, 2016
French
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-44080
Independent Consultation and Investigation Mechanism
MICI-BID-PR-2016-0101_Solicitud_Original_ENGLISH_WEB [40325951].PDF
Dec. 31, 1999
English
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-44019
Independent Consultation and Investigation Mechanism
MICI-BID-PR-2016-0101 Solicitud Original_FRE_WEB [40327589].PDF
Jul. 25, 2016
French
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-44073
Independent Consultation and Investigation Mechanism
MICI-BID-PR-2016-0101_NOTIFICACIÓN_DE_REGISTRO_DE_SOLICITUD [40317036].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-78
NON-APPLICABLE
Decreto 3457 Plan Maestro Puerto.pdf
Aug. 07, 2017
English
Preparation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-53
Environmental Impact Assessments
EIAp Tramos II y III - Julio 2015 [40342552].PDF
Jun. 16, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-44361
Environmental Impact Assessments
PIC_ Estudio Socio Ambiental BRT Corredor Eusebio Ayala-Mcal Estigarribia [40342747].PDF
Jun. 22, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-44362
Resettlement Plans
PIC_ Marco de Plan de Reasentamiento - Programa Asunción BRT y RU [35363897].PDF
Dec. 31, 1899
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-57
Environmental and Social Management Reports
PIC_ Informe de Gestión Ambiental y Social (IGAS) [40480869].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2073519417-11
Project Profile
PIC_ PARAGUAY_ Reconversión Centro, Modernización del Transporte Público Metropolitano y Oficinas de Gobierno (P [35109799].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-74
Environmental Impact Assessments
IDBDOCS-40342747-PIC__Estudio_Socio_Ambiental_BRT_Corredor_Eusebio_Ayala-Mcal_Estigarribia Parte8.pdf
Jul. 19, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-75
Environmental Impact Assessments
EIAp-Plan Maestro del Puerto de la ciudad de Asunción .pdf
Aug. 03, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-76
Environmental Impact Assessments
acta del puerto asuncion villeta (002).pdf
Aug. 07, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-1709244737-13
Environmental and Social Execution
Plan especifico de reasentamento sub-tramo 3.1.pdf
May. 19, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-1017
Resettlement Plans
Plan Especifico de Reasentamiento Sub Tramo 2-4.pdf
Sep. 06, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-67
Environmental Impact Assessments
IDBDOCS-40342747-PIC__Estudio_Socio_Ambiental_BRT_Corredor_Eusebio_Ayala-Mcal_Estigarribia Parte1.pdf
Jul. 19, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-79
Environmental Impact Assessments
SEAM 1503_2016 Plan Maestro del Puerto (2) (1) (1).pdf
Aug. 07, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-68
Environmental Impact Assessments
IDBDOCS-40342747-PIC__Estudio_Socio_Ambiental_BRT_Corredor_Eusebio_Ayala-Mcal_Estigarribia Parte2.pdf
Jul. 19, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-864
Environmental Impact Assessments
EIAp Tramo 1.1.pdf
Feb. 15, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-69
Environmental Impact Assessments
IDBDOCS-40342747-PIC__Estudio_Socio_Ambiental_BRT_Corredor_Eusebio_Ayala-Mcal_Estigarribia Parte3.pdf
Jul. 19, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-865
Resettlement Plans
Plan Director de Reasentamiento.pdf
Feb. 20, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-70
Environmental Impact Assessments
IDBDOCS-40342747-PIC__Estudio_Socio_Ambiental_BRT_Corredor_Eusebio_Ayala-Mcal_Estigarribia Parte4.pdf
Jul. 19, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-898
Resettlement Plans
Plan Especifico de reasentamiento Sub Tramo 3.2.pdf
Feb. 23, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-71
Environmental Impact Assessments
IDBDOCS-40342747-PIC__Estudio_Socio_Ambiental_BRT_Corredor_Eusebio_Ayala-Mcal_Estigarribia Parte5.pdf
Jul. 19, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-72
Environmental Impact Assessments
IDBDOCS-40342747-PIC__Estudio_Socio_Ambiental_BRT_Corredor_Eusebio_Ayala-Mcal_Estigarribia Parte6.pdf
Jul. 19, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-448177878-73
Environmental Impact Assessments
IDBDOCS-40342747-PIC__Estudio_Socio_Ambiental_BRT_Corredor_Eusebio_Ayala-Mcal_Estigarribia Parte7.pdf
Jul. 19, 2017
English