PR-L1022 : Water and Sanitation Program for Rural and Indigenous Communities (PAySRI)
Project Status: Closed
The objective of the program is to help increase access to drinking water and sanitation services in rural and indigenous communities in Paraguay, so that families without these services may get them in the short term, thereby improving their quality of life.
Project Detail
Project Number
PR-L1022
Project Country
Paraguay
Project Sector
WATER AND SANITATION
Project Subsector
WATER SUPPLY URBAN
Project Type
Loan Operation
Project Lending Type
SG
Project Modality
ESP (Specific Investment Operation)
Project Facility Type
Environmental and social impact category
B
Project Status
Closed
Operation Number
2222/OC-PR
Financial Information
Project Number
PR-L1022
Project Status
Closed
IDB Financing
Financing type
SCF
Fund
Ordinary Capital
Reporting currency
USD - United States Dollar
Reporting date
Jul/18/2023
Roles & Responsibilities
Contract signature date
Mar/20/2010
Project Information
Total Cost
USD 20,000,000
Country counterpart financing
USD 8,000,000
Amount
USD 12,000,000
Preparation
Title
Type
Project Number
Date Published
Environmental Analyses
2222/OC-PR;PR-L1022
September 14, 2009
Approved
Title
Type
Project Number
Date Published
Loan Contract
1723/OC-PR;1818/OC-PR;1835/OC-PR;1916/BL-PR;2014/BL-PR;2163/OC-PR;2164/BL-PR;2222/OC-PR;2453/OC-PR;2542/BL-PR;2589/BL-PR;2660/OC-PR;2667/OC-PR;2934/OC-PR;2935/BL-PR;PR-L1010;PR-L1011;PR-L1018;PR-L1019;PR-L1022;PR-L1027;PR-L1049;PR-L1050;PR-L1051;PR-L1060
February 13, 2015
Loan Proposal
PR-L1022
November 04, 2009
Loan Proposal
PR-L1022
November 04, 2009
Implementation
Title
Type
Project Number
Date Published
BEO Procurement
PR-L1022
May 12, 2022
BEO Procurement
PR-L1022
April 22, 2022
Project Monitoring Report ( Public version)
PR-L1022
October 16, 2019
Project Monitoring Report ( Public version)
PR-L1022
December 14, 2018
Project Monitoring Report ( Public version)
PR-L1022
August 03, 2018
Project Monitoring Report ( Public version)
PR-L1022
February 15, 2018
Project Monitoring Report ( Public version)
PR-L1022
February 14, 2018
Project Monitoring Report ( Public version)
PR-L1022
December 28, 2016
Project Monitoring Report ( Public version)
PR-L1022
June 22, 2016
Project Monitoring Report ( Public version)
PR-L1022
March 28, 2016
Project Monitoring Report ( Public version)
PR-L1022
March 11, 2016
Project Monitoring Report ( Public version)
PR-L1022
March 10, 2016
Project Monitoring Report ( Public version)
PR-L1022
March 08, 2016
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
October 31, 2013
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
October 31, 2013
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
October 31, 2013
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
October 31, 2013
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
May 07, 2013
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
May 07, 2013
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
May 07, 2013
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
May 07, 2013
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
December 11, 2012
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
December 11, 2012
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
December 11, 2012
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
December 11, 2012
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
May 14, 2012
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
May 14, 2012
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
May 14, 2012
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
May 14, 2012
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
November 18, 2011
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
November 18, 2011
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
November 18, 2011
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
November 18, 2011
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
June 22, 2011
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
June 22, 2011
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
June 22, 2011
Project Monitoring Report ( Public version)
2222/OC-PR;PR-L1022
June 22, 2011
Specific Procurement Notices
2222/OC-PR;PR-L1022
June 17, 2011
Procurement Plan
PR-L1022
November 18, 2010
Completed
Title
Type
Project Number
Date Published
Project Completion Report
PR-L1022
November 01, 2019