PE-L1151 : Improvement Huanuco Road, Conococha Huanuco Sector - Huallanca PE - 3N Route Project
Project Status: Implementation
The project's objective is to finance 1 section of the Longitudinal Highway in the Highlands, in a total of 150 km. The sections is Huanuco-Huallanca
Project Detail
Project Number
PE-L1151
Approval date
December 14, 2016
Project Country
Peru
Project Sector
TRANSPORT
Project Subsector
MAJOR HIGHWAYS
Project Type
Loan Operation
Project Lending Type
SG
Project Modality
ESP (Specific Investment Operation)
Project Facility Type
Environmental and social impact category
A
Project Status
Implementation
Operation Number
3881/OC-PE
Financial Information
Project Number
PE-L1151
Project Status
Implementation
IDB Financing
Financing type
FFF
Fund
Ordinary Capital
Reporting currency
USD - United States Dollar
Reporting date
Jun/09/2023
Roles & Responsibilities
Contract signature date
Sep/14/2017
Project Information
Total Cost
USD 469,639,000
Country counterpart financing
USD 389,639,000
Amount
USD 80,000,000
Preparation
Title
Type
Project Number
Date Published
Environmental Impact Assessments
PE-L1151
December 09, 2016
Environmental Impact Assessments
PE-L1151
December 09, 2016
Environmental Impact Assessments
PE-L1151
December 09, 2016
Environmental Impact Assessments
PE-L1151
December 09, 2016
Environmental Impact Assessments
PE-L1151
December 09, 2016
Environmental Impact Assessments
PE-L1151
December 09, 2016
Project Profile
PE-L1151
November 23, 2016
Project Profile
PE-L1151
November 22, 2016
Project Profile
PE-L1151
November 22, 2016
Project Profile
PE-L1151
November 22, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Environmental Impact Assessments
PE-L1151
November 02, 2016
Project Profile
PE-L1151
May 06, 2016
Environmental Impact Assessments
PE-L1151
February 11, 2016
Environmental Impact Assessments
PE-L1151
December 22, 2015
Environmental Impact Assessments
PE-L1151
December 22, 2015
Environmental Impact Assessments
PE-L1151
December 22, 2015
Environmental Impact Assessments
PE-L1151
December 22, 2015
Environmental Impact Assessments
PE-L1151
December 22, 2015
Environmental Impact Assessments
PE-L1151
December 18, 2015
Approved
Title
Type
Project Number
Date Published
Loan Contract
PE-L1151
May 09, 2018
Loan Proposal
PE-L1151
May 04, 2018
Loan Contract
3881/OC-PE;PE-L1151
December 14, 2016
Loan Contract
3881/OC-PE;PE-L1151
December 14, 2016
Loan Proposal
PE-L1151
December 13, 2016
Loan Proposal
PE-L1151
December 13, 2016
Loan Proposal
PE-L1151
September 19, 2016
Loan Proposal
PE-L1151
August 25, 2016
Loan Proposal
PE-L1151
August 25, 2016
Loan Proposal
PE-L1151
August 25, 2016
Loan Proposal
PE-L1151
August 25, 2016
Implementation
Title
Type
Project Number
Date Published
Specific Procurement Notices
PE-L1151
April 25, 2023
Project Monitoring Report ( Public version)
PE-L1151
February 09, 2023
Specific Procurement Notices
PE-L1151
February 01, 2023
Project Monitoring Report ( Public version)
PE-L1151
August 15, 2022
Annual Project Audited Financial Statement
PE-L1151
June 08, 2022
Specific Procurement Notices
PE-L1151
April 26, 2022
Specific Procurement Notices
PE-L1151
March 21, 2022
Project Monitoring Report ( Public version)
PE-L1151
February 22, 2022
Specific Procurement Notices
PE-L1151
February 08, 2022
Specific Procurement Notices
PE-L1151
February 08, 2022
Specific Procurement Notices
PE-L1151
February 08, 2022
Specific Procurement Notices
PE-L1151
December 20, 2021
Project Monitoring Report ( Public version)
PE-L1151
July 20, 2021
Annual Project Audited Financial Statement
PE-L1151
May 14, 2021
Project Monitoring Report ( Public version)
PE-L1151
March 09, 2021
Annual Project Audited Financial Statement
PE-L1151
October 01, 2020
Project Monitoring Report ( Public version)
PE-L1151
August 25, 2020
Project Monitoring Report ( Public version)
PE-L1151
February 13, 2020
Project Monitoring Report ( Public version)
PE-L1151
October 16, 2019
Project Monitoring Report ( Public version)
PE-L1151
December 14, 2018
Project Monitoring Report ( Public version)
PE-L1151
August 02, 2018
Project Monitoring Report ( Public version)
PE-L1151
February 15, 2018
Project Monitoring Report ( Public version)
PE-L1151
February 14, 2018