NI-L1040 : National Sustainable Electrification and Renewable Energy Program (PNESER)
Project Status: Closed
The objective of the National Sustainable Electrification and Renewable Energy Program (PNESER) is to support the efforts of the Nicaraguan government to reduce poverty by promoting access by a significant portion of the population to efficient, sustainable electricity service, while supporting creation of the conditions to move forward on a change of the energy mix that contributes to better conditions for mitigation and adaptation to climate change. PNESER will support seven components: (i) rural electrification by network extension; (ii) normalization of service in settlements; (iii) expansion in isolated areas with renewable energy; (iv) preinvestment and studies for generation projects with renewable energy; (v) energy efficiency programs; (vi) strengthening the transmission system in rural areas; and (vii) sustainability of ENEL isolated systems.
Project Detail
Project Country
Nicaragua
Project Subsector
NEW POWER DISTRIBUTION & TRANSMISSION PROJECTS
Project Type
Loan Operation
Project Modality
ESP (Specific Investment Operation)
Environmental and social impact category
B
Operation Number
2342/BL-NI
Financial Information
IDB Financing
Reporting currency
USD - United States Dollar
Reporting date
Jul/18/2023
Roles & Responsibilities
Contract signature date
Aug/12/2010
Preparation
Title
Type
Project Number
Date Published
Project Profile
NI-L1040
October 14, 2009
Approved
Title
Type
Project Number
Date Published
Loan Contract
NI-L1040
June 15, 2020
Loan Contract
NI-L1040;NI-L1063;NI-L1050
June 15, 2020
Loan Contract
NI-L1040
June 15, 2020
Loan Contract
NI-L1040
June 15, 2020
Loan Contract
NI-L1040
June 15, 2020
Loan Contract
NI-L1040
June 15, 2020
Loan Contract
NI-L1040
April 10, 2020
Loan Contract
2342/BL-NI;NI-L1040
August 07, 2014
Loan Contract
2342/BL-NI;NI-L1040
March 24, 2014
Loan Proposal
NI-L1040
July 07, 2010
Loan Proposal
NI-L1040
July 07, 2010
Implementation
Title
Type
Project Number
Date Published
Project Monitoring Report ( Public version)
NI-L1040
February 13, 2020
Project Monitoring Report ( Public version)
NI-L1040
October 16, 2019
Project Monitoring Report ( Public version)
NI-L1040
December 14, 2018
Project Monitoring Report ( Public version)
NI-L1040
August 03, 2018
Project Monitoring Report ( Public version)
NI-L1040
February 15, 2018
Project Monitoring Report ( Public version)
NI-L1040
February 14, 2018
Financial Statements
NI-L1040
January 17, 2018
Project Monitoring Report ( Public version)
NI-L1040
December 27, 2016
Project Monitoring Report ( Public version)
NI-L1040
July 05, 2016
Project Monitoring Report ( Public version)
NI-L1040
March 23, 2016
Project Monitoring Report ( Public version)
NI-L1040
March 16, 2016
Project Monitoring Report ( Public version)
NI-L1040
March 15, 2016
Project Monitoring Report ( Public version)
NI-L1040
March 10, 2016
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
October 31, 2013
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
October 31, 2013
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
October 31, 2013
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
May 07, 2013
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
May 07, 2013
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
May 07, 2013
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
May 07, 2013
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
December 11, 2012
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
December 11, 2012
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
December 11, 2012
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
December 11, 2012
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
May 14, 2012
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
May 14, 2012
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
May 14, 2012
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
May 14, 2012
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
November 18, 2011
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
November 18, 2011
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
November 18, 2011
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
November 18, 2011
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
June 22, 2011
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
June 22, 2011
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
June 22, 2011
Project Monitoring Report ( Public version)
2342/BL-NI;NI-L1040
June 22, 2011
Specific Procurement Notices
2342/BL-NI;NI-L1040
June 17, 2011
General Procurement Notices
2342/BL-NI;NI-L1040
November 05, 2010
Completed
Title
Type
Project Number
Date Published
Project Completion Report
NI-L1040
January 27, 2021