Kingston Metropolitan Area (KMA) Water Supply Improvement Programme

The general objective of the proposed operation is to improve efficiency, quality and sustainability of the potable water services provided in the Kingston Metropolitan Area (KMA) and to increase the access in selected urban centers of Jamaica. The specific objectives of the programme are: (i) optimizing water infrastructure performance; (ii) reducing non-revenue water (NRW) levels; and (iii) strengthening NWC¿s performance in terms of operation and maintenance practices.

Project Detail

Country

Jamaica

Project Number

JA-L1035

Approval Date

November 17, 2011

Project Status

Closed

Project Type

Loan Operation

Sector

WATER AND SANITATION

Subsector

WATER AND SANITATION

Lending Instrument

Préstamo de Inversión

Lending Instrument Code

INV

Modality

ESP (Specific Investment Operation)

Facility Type

-

Environmental and Social Impact Category (ESIC)

Category B: Likely to cause mostly local and short-term negative environmental and associated social impacts and for which effective mitigation measures are readily available

Total Cost

USD 133,000,000.00

Country Counterpart Financing

USD 0.00

Original Amount Approved

USD 133,000,000.00

Financial Information
Operation Number Lending Type Reporting Currency Reporting Date Signed Date Fund Financial Instrument
2633/OC-JA Sovereign Guaranteed USD - United States Dollar Ordinary Capital Single Currency Facility
Operation Number 2633/OC-JA
  • Lending Type: Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: Ordinary Capital
  • Financial Instrument: Single Currency Facility

Can’t find a document? Request information

Implementation Phase
https://www.iadb.org/document.cfm?id=EZIDB0000361-507391937-228
Annual Project Audited Financial Statement
NWC Signed Financial Statements 2021.pdf
Oct. 16, 2024
English
https://www.iadb.org/document.cfm?id=EZSHARE-507391937-226
Annual Project Audited Financial Statement
Signed FS..PDF
Oct. 16, 2024
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-41417
Project Monitoring Report ( Public version)
JA-L1035 Second period Jan-Dec 2021 - Public Report.PDF
Aug. 15, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-8961
Loan Contract
Loans to the National Water Commission Subject to a LIBOR based interest rate.PDF
Jun. 21, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-507391937-199
Annual Project Audited Financial Statement
KMAWSIP Final FS Dec 2021.pdf
Dec. 14, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-35645
Project Monitoring Report ( Public version)
JA-L1035 First period Jan-Jun 2021 - Public Report.pdf
Feb. 20, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-507391937-145
Annual Project Audited Financial Statement
2633-OC-JA Audited Financial Statements for the Programme for the Period Ended March 31, 2021.pdf
Sep. 22, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-34962
Project Monitoring Report ( Public version)
JA-L1035 Second period Jan-Dec 2020 - Public Report.pdf
Jul. 20, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-34522
Project Monitoring Report ( Public version)
JA-L1035 First period Jan-Jun 2020 - Public Report.pdf
Mar. 09, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-1286680947-279
Procurement Plan
2633-OC-JA Kingston Metropolitan Area (KMA) Water Supply Improvement Programme 2020 Procurement Plan.xlsx
Dec. 21, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-33666
Project Monitoring Report ( Public version)
JA-L1035 Second period Jan-Dec 2019-Public Report.pdf
Aug. 25, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-507391937-109
Annual Project Audited Financial Statement
KMAWSIP FS 2020 - COMPILED.PDF
Oct. 23, 2024
English
https://www.iadb.org/document.cfm?id=EZSHARE-249695302-7
Project Monitoring Report ( Public version)
JA-L1035 First period Jan-Jun 2016-Public Report [40799184].PDF
Dec. 27, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-51
Specific Procurement Notices
JA-L1035 [40754993].PDF
Nov. 22, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-50
Specific Procurement Notices
JA-L1035 [40727961].PDF
Oct. 31, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-249695302-6
Project Monitoring Report ( Public version)
JA-L1035 Second period Jan-Dec 2015-Public Report [40377704].PDF
Jul. 05, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-47
Procurement Plan
Loan 2633_OC-JA_ Kingston Metropolitan Area Water Supply and Sanitation Improvement Programme Procurement Plan [40364329].PDF
Jun. 24, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-46
Procurement Plan
Loan 2633_OC-JA_ Kingston Metropolitan Area Water Supply and Sanitation Improvement Programme Procurement Plan [40359796].PDF
Jun. 22, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-249695302-5
Project Monitoring Report ( Public version)
JA-L1035 First period Jan-Jun 2015-Public Report [40199597].PDF
Mar. 23, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-249695302-4
Project Monitoring Report ( Public version)
JA-L1035 Second period Jan-Dec 2014-Public Report [40185564].PDF
Mar. 16, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-249695302-3
Project Monitoring Report ( Public version)
JA-L1035 First period Jan-Jun 2014-Public Report [40182632].PDF
Mar. 15, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-249695302-2
Project Monitoring Report ( Public version)
JA-L1035 Second period Jan-Dec 2013-Public Report [40174735].PDF
Mar. 10, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-45
Specific Procurement Notices
JA-L1035 [40098547].PDF
Feb. 01, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-44
Specific Procurement Notices
JA-L1035 [40057722].PDF
Jan. 08, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-39
Specific Procurement Notices
JA-L1035 [39888057].PDF
Oct. 02, 2015
English
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-870
Loan Contract
Amendatory Contract No_ 1 - Kingston Metropolitan Area (KMA) Water Supply Improvement Programme [39866203].PDF
Sep. 22, 2015
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-35
Procurement Plan
Kingston Metropolitan Area Water Supply and Sanitation Improvement Programme Procurement Plan March 2014 to end [39249702].PDF
Nov. 27, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-43
Annual Project Audited Financial Statement
Kingston Metropolitan Area Water Supply Improvement Programme Audited Financial Statements March 31, 2014 [40031508].PDF
Dec. 17, 2015
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-28
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_JA-L1035-2013-1º-Período [38265544].PDF
Mar. 06, 2014
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-29
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_JA-L1035-2013-1º-Período [38266209].PDF
Mar. 06, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-30
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_JA-L1035-2013-1º-Periodo [38266873].PDF
Mar. 06, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-31
Project Monitoring Report ( Public version)
Report for Publication_PMR-_JA-L1035-2013-1º-Period [38267547].PDF
Mar. 06, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-27
Procurement Plan
2633_OC-JA - Procurement Plan [38141856].xls
Oct. 03, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-24
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_JA-L1035-2012-2º-Periodo [37874649].PDF
Jul. 27, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-25
Project Monitoring Report ( Public version)
Report for Publication_PMR-_JA-L1035-2012-2º-Period [37875480].PDF
Jul. 27, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-22
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_JA-L1035-2012-2º-Período [37873322].PDF
Jul. 27, 2013
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-23
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_JA-L1035-2012-2º-Período [37873989].PDF
Jul. 27, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-42
Annual Project Audited Financial Statement
Kingston Metropolitan Area Water Supply Improvement Programme Audited Financial Statements and Supplementary Inf [40030919].PDF
Dec. 17, 2015
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-26
Procurement Plan
2633_OC-JA - Procurement Plan [38027086].xls
Aug. 29, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-18
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_JA-L1035-2012-1º-Período [37352217].PDF
Dec. 19, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-19
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_JA-L1035-2012-1º-Período [37352879].PDF
Jan. 21, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-20
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_JA-L1035-2012-1º-Periodo [37353537].PDF
Jan. 21, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-21
Project Monitoring Report ( Public version)
Report for Publication_PMR-_JA-L1035-2012-1º-Period [37354200].PDF
Jan. 21, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-17
Project Monitoring Report ( Public version)
Report for Publication_PMR-_JA-L1035-2011-2º-Period [37298416].PDF
Nov. 28, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-14
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_JA-L1035-2011-2º-Período [37297836].PDF
Nov. 28, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-15
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_JA-L1035-2011-2º-Período [37298027].PDF
Nov. 28, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-16
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_JA-L1035-2011-2º-Periodo [37298219].PDF
Nov. 28, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1622901323-2
Procurement Plan
KMA Water Supply Procurement Plan [36638690].DOCX
Jan. 23, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-12
Loan Proposal
Kingston Metropolitan Area (KMA) Water Supply Improvement Programme [36523964].PDF
Nov. 15, 2011
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-13
Loan Proposal
Programa de Mejora del Abastecimiento de Agua a la Zona Metropolitana de Kingston [36523998].PDF
Nov. 15, 2011
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-7519
Loan Contract
Contract - Kingston Metropolitan Area (KMA) Water Supply Improvement Programme.pdf
Apr. 07, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-33021
Project Monitoring Report ( Public version)
JA-L1035 First period Jan-Jun 2019-Public Report.pdf
Feb. 12, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-7520
Loan Contract
Guarantee Contract - Kingston Metropolitan Area (KMA) Water Supply Improvement Programme.pdf
Apr. 07, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-507391937-38
Annual Project Audited Financial Statement
2633OC-JA Kingston Metropolitan Area (KMA) Water Supply Improvement Programme Audited Financial Statements March 31 2018.pdf
Aug. 29, 2019
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-394
Project Monitoring Report ( Public version)
JA-L1035 Second period Jan-Dec 2016-Public Report.pdf
Feb. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-507391937-79
Annual Project Audited Financial Statement
2633OC-JA Kingston Metropolitan Area (KMA) Water Supply Improvement Programme - Audited Financial Statements for the Programme - March 31, 2019.pdf
Nov. 01, 2019
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-1049
Project Monitoring Report ( Public version)
JA-L1035 First period Jan-Jun 2017-Public Report.pdf
Feb. 15, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-619253148-45
Procurement Plan
2633-OC-JA Kingston Metropolitan Area (KMA) Water Supply Improvement Programme 2018 Procurement Plan.xlsx
May. 01, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-1286680947-2
Procurement Plan
Procurement Plan_KMA Water Supply Improvement Programme_April18_2018.pdf
May. 08, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-2064
Project Monitoring Report ( Public version)
JA-L1035 Second period Jan-Dec 2017-Public Report.pdf
Aug. 02, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-619253148-62
Annual Project Audited Financial Statement
KMA signed FS March 31 2017.pdf
May. 02, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-31703
Project Monitoring Report ( Public version)
JA-L1035 First period Jan-Jun 2018-Public Report.pdf
Dec. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-32392
Project Monitoring Report ( Public version)
JA-L1035 Second period Jan-Dec 2018-Public Report.pdf
Oct. 15, 2019
English
Closed Phase
https://www.iadb.org/document.cfm?id=EZIDB0000361-1261540006-22
Project Completion Report
JAMAICA. JA-L1035 NWC-KMA Water Supply Improvement Programme PCR-PUBLIC-20230329.pdf
Mar. 30, 2023
English
Other Documents
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-49
Financial Statements
Loan 2633_OC-JA_ Kingston Metropolitan Area Water Supply Improvement Programme Audited Financial Statements fo [40699861].PDF
Oct. 07, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-48
Financial Statements
Loan 2633_OC-JA_ Kingston Metropolitan Area Water Supply Improvement Programme Audited Financial Statements as [40645969].PDF
Sep. 05, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-40
Financial Statements
Kingston Metorpolitan Area Water Supply Improvement Programme Financial Statements March 31, 2015 [39993461].PDF
Nov. 30, 2015
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-41
Financial Statements
Kingston Metropolitan Area Water Supply Improvement Programme Financial Statements Progrmme March 31, 2015 [39993504].PDF
Nov. 30, 2015
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-38
Procurement
JA-L1035 [39840609].PDF
Sep. 08, 2015
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-36
Financial Statements
Kingston Metropolitan Area Water Supply Improvement Programme Financial Statements March 31, 2013 [39394246].PDF
Feb. 11, 2015
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-34
Procurement
JA-L1035 [38841375].PDF
Jun. 05, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-33
Procurement
JA-L1035 [38792633].PDF
May. 13, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-32
Procurement
JA-L1035 [38792632].PDF
May. 13, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-37
Financial Statements
National Water Commission (Entity) Financial Statements March 31 2013 [39791535].PDF
Aug. 13, 2015
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-2319
Best practices papers
Evaluation des Sytèmes de Pompage D'Eau - Guide pour la feuille de calcul [36729142].PDF
Mar. 14, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-2320
Best practices papers
Evaluation des Sytèmes de Pompage D'Eau - Manuel d'évaluation de l'efficacité énergétique [36729149].PDF
Mar. 14, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-2315
Best practices papers
Avaliação para sistemas de bombeamento de água - Guia folha de calculo [36729107].PDF
Mar. 14, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-2316
Best practices papers
Avaliação para sistemas de bombeamento de água - Manual de eficiência energética [36729116].PDF
Mar. 14, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-2317
Best practices papers
Avaliação para sistemas de bombeamento de água - Manual de manutençao [36729123].PDF
Mar. 14, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-2318
Best practices papers
Evaluation des Sytèmes de Pompage D'Eau - Manuel de maintenance [36729127].PDF
Mar. 14, 2012
French
Preparation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-705009174-2
Environmental Analyses
Kingston Metropolitan Area (KMA) Water SupplyImprovement Project_ NWC-IDB-ESA-20110630 [36272703].PDF
Jul. 07, 2011
English
https://www.iadb.org/document.cfm?id=EZSHARE-2120240627-11
Project Profile
Kingston Metropolitan Area (KMA) Water Supply Improvement Project [35766643].PDF