HO-L1102 : Cañaveral-Río Lindo Hydropower Complex Rehabilitation and Uprating Project

Project Status: Implementation

The objective of the project is to recuperate and to conserve the power generation capacity from renewable energies, contributing to energy security, through the improvement of the efficiency and the extension of the lifespan of the power generation and transmission infrastructure. The specific objectives are: i) to rehabilitate the power infrastructure of the Canaveral and Rio Lindo power stations, ii) to rehabilitate the transmission infrastructure that connects the power stations to the grid; and iii) to improve the ENEE's operational and commercial efficiency generation management.

Project Detail

Project Number
HO-L1102
Approval date
March 12, 2015
Project Country
Honduras
Project Sector
ENERGY
Project Subsector
ENERGY EFFICIENCY AND RENEWABLE ENERGY IN END USE
Project Type
Loan Operation
Environmental and social impact category
B
Project Status
Implementation
Operation Number
3435/BL-HO

Financial Information

Project Number
HO-L1102
Project Status
Implementation

IDB Financing

Financing type
SCC
Fund
Ordinary Capital
Reporting currency
USD - United States Dollar
Reporting date
Sep/24/2021

Roles & Responsibilities

Contract signature date
Mar/26/2015

Project Information

Total Cost
USD 167,180,000
Country counterpart financing
USD 8,816,000
Amount
USD 23,000,000

Approved

Title
Type
Project Number
Date Published
Loan Proposal
HO-L1102
March 04, 2015
Loan Proposal
HO-L1102
March 04, 2015
Loan Proposal
HO-L1102
March 04, 2015
Loan Proposal
HO-L1102
March 04, 2015
Loan Proposal
HO-L1102
March 04, 2015
Loan Proposal
HO-L1102
January 05, 2015
Loan Proposal
HO-L1102
November 28, 2014

Implementation

Title
Type
Project Number
Date Published
Project Monitoring Report ( Public version)
HO-L1102
July 21, 2021
Notice of Contract Award (SG)
HO-L1102
June 03, 2021
Project Monitoring Report ( Public version)
HO-L1102
March 09, 2021
Annual Project Audited Financial Statement
HO-L1102
December 11, 2020
Notice of Contract Award (SG)
HO-L1102
November 02, 2020
Specific Procurement Notices
HO-L1102
October 27, 2020
Specific Procurement Notices
HO-L1102
October 13, 2020
Project Monitoring Report ( Public version)
HO-L1102
August 25, 2020
Project Monitoring Report ( Public version)
HO-L1102
February 13, 2020
Specific Procurement Notices
HO-L1102
February 12, 2020
Annual Project Audited Financial Statement
HO-L1102
January 10, 2020
Annual Project Audited Financial Statement
HO-L1102
November 18, 2019
Project Monitoring Report ( Public version)
HO-L1102
October 15, 2019
Project Monitoring Report ( Public version)
HO-L1102
December 14, 2018
Project Monitoring Report ( Public version)
HO-L1102
August 02, 2018
Annual Project Audited Financial Statement
HO-L1102
July 12, 2018
Project Monitoring Report ( Public version)
HO-L1102
February 15, 2018
Project Monitoring Report ( Public version)
HO-L1102
February 15, 2018
Annual Project Audited Financial Statement
HO-L1102
February 03, 2018
Specific Procurement Notices
HO-L1102
January 23, 2017
Project Monitoring Report ( Public version)
HO-L1102
December 27, 2016
Project Monitoring Report ( Public version)
HO-L1102
July 05, 2016
Project Monitoring Report ( Public version)
HO-L1102
March 21, 2016