HA-L1100 : Rehabilitation of the Peligre Transmission Line

Project Status: Closed

Inspect the electrical transmission line and basic engineering details to guarantee a reliable network of electrical energy produced by the Peligre hydroelectric plant which is expected to be fully restored (54MW) in 2016 through a joint funding BID-KFW and OFID of a total of approximately U.S. $ 62.5 million

Project Detail

Project Number
HA-L1100
Project Country
Haiti
Project Sector
ENERGY
Project Subsector
ENERGY SECTOR REHABILITATION AND EFFICIENCY
Project Type
Grant Financing Product
Project Lending Type
SG
Project Modality
ESP (Specific Investment Operation)
Project Facility Type
Environmental and social impact category
B
Project Status
Closed
Operation Number
3413/GR-HA

Financial Information

Project Number
HA-L1100
Project Status
Closed

IDB Financing

Financing type
GRN
Fund
IDB Grant Facility Account
Reporting currency
USD - United States Dollar
Reporting date
Jul/18/2023

Roles & Responsibilities

Contract signature date
Feb/20/2015

Project Information

Total Cost
USD 7,700,000
Country counterpart financing
USD 0
Amount
USD 7,700,000

Approved

Title
Type
Project Number
Date Published
Loan Proposal
HA-G1030,HA-L1100
January 29, 2021
Loan Proposal
HA-G1030,HA-L1100
January 29, 2021
General Agreement
3413/GR-HA;GRT/HR-14830-HA;HA-G1030;HA-L1100
March 06, 2015
General Agreement
3413/GR-HA;HA-L1100
December 17, 2014
General Agreement
3413/GR-HA;HA-L1100
December 17, 2014
Loan Proposal
HA-G1030;HA-L1100
November 21, 2014
Loan Proposal
HA-G1030;HA-L1100
November 21, 2014
Loan Proposal
HA-G1030;HA-L1100
November 03, 2014
Loan Proposal
HA-G1030;HA-L1100
October 17, 2014
Loan Proposal
HA-G1030;HA-L1100
October 17, 2014
Loan Proposal
HA-G1030;HA-L1100
October 17, 2014

Implementation

Title
Type
Project Number
Date Published
Project Monitoring Report ( Public version)
HA-L1100
March 09, 2021
Project Monitoring Report ( Public version)
HA-L1100
August 25, 2020
Project Monitoring Report ( Public version)
HA-L1100
February 12, 2020
Project Monitoring Report ( Public version)
HA-L1100
October 15, 2019
Project Monitoring Report ( Public version)
HA-L1100
December 14, 2018
Project Monitoring Report ( Public version)
HA-L1100
August 07, 2018
Project Monitoring Report ( Public version)
HA-L1100
February 15, 2018
Project Monitoring Report ( Public version)
HA-L1100
February 14, 2018
Procurement Plan
HA-L1100
April 18, 2017
Project Monitoring Report ( Public version)
HA-L1100
December 27, 2016
Project Monitoring Report ( Public version)
HA-L1100
July 05, 2016
Project Monitoring Report ( Public version)
HA-L1100
March 21, 2016
Project Monitoring Report ( Public version)
HA-L1100
March 16, 2016

Completed

Title
Type
Project Number
Date Published
Project Completion Report
HA-L1100
January 29, 2021
Project Completion Report
HA-L1100
January 29, 2021