HA-L1089 : Support for Transport Sector in Haiti IV

Project Status: Implementation

The general objective of the project is to increase the competitiveness and connectivity in Haiti by reducing transportation costs and providing safer services. Specific objectives include the rehabilitation of the Toussaint Louverture International Airport (TLIA) and the rehabilitation of a road segment on Route Nationale 1 (RN-1) between Plaisance and Camp Coq. The project will promote the country's regional and international integration potential and will support institutional strengthening for the transport sector in Haiti.

Project Detail

Project Number
HA-L1089
Approval date
June 12, 2014
Project Country
Haiti
Project Sector
TRANSPORT
Project Subsector
AIRPORT INFRASTRUCTURE
Project Type
Grant Financing Product
Project Lending Type
SG
Project Modality
ESP (Specific Investment Operation)
Project Facility Type
Environmental and social impact category
B
Project Status
Implementation
Operation Number
3190/GR-HA

Financial Information

Project Number
HA-L1089
Project Status
Implementation

IDB Financing

Financing type
GRN
Fund
IDB Grant Facility Account
Reporting currency
USD - United States Dollar
Reporting date
Jul/18/2023

Roles & Responsibilities

Contract signature date
Aug/04/2014

Project Information

Total Cost
USD 50,000,000
Country counterpart financing
USD 0
Amount
USD 50,000,000

Preparation

Title
Type
Project Number
Date Published
Project Profile
HA-L1089
November 12, 2013

Approved

Title
Type
Project Number
Date Published
General Agreement
3190/GR-HA;HA-L1089
June 08, 2015
General Agreement
3190/GR-HA;HA-L1089
October 01, 2014
General Agreement
3190/GR-HA;HA-L1089
June 12, 2014
General Agreement
3190/GR-HA;HA-L1089
June 12, 2014
Loan Proposal
HA-L1089
May 27, 2014
Loan Proposal
HA-L1089
May 27, 2014
Loan Proposal
HA-L1089
April 28, 2014
Loan Proposal
HA-L1089
March 24, 2014
Loan Proposal
HA-L1089
March 24, 2014
Loan Proposal
HA-L1089
March 24, 2014
Loan Proposal
HA-L1089
March 20, 2014

Implementation

Title
Type
Project Number
Date Published
Project Monitoring Report ( Public version)
HA-L1089
February 08, 2023
Project Monitoring Report ( Public version)
HA-L1089
August 12, 2022
Project Monitoring Report ( Public version)
HA-L1089
February 20, 2022
Project Monitoring Report ( Public version)
HA-L1089
July 20, 2021
Procurement Plan
HA-L1089
April 27, 2021
Project Monitoring Report ( Public version)
HA-L1089
March 09, 2021
Annual Project Audited Financial Statement
HA-L1089
November 25, 2020
Project Monitoring Report ( Public version)
HA-L1089
August 25, 2020
Project Monitoring Report ( Public version)
HA-L1089
February 12, 2020
Project Monitoring Report ( Public version)
HA-L1089
October 15, 2019
Procurement Plan
HA-L1089
May 27, 2019
Project Monitoring Report ( Public version)
HA-L1089
December 14, 2018
Project Monitoring Report ( Public version)
HA-L1089
August 02, 2018
Project Monitoring Report ( Public version)
HA-L1089
February 15, 2018
Project Monitoring Report ( Public version)
HA-L1089
February 14, 2018
Procurement Plan
HA-L1089
April 18, 2017
Project Monitoring Report ( Public version)
HA-L1089
July 05, 2016
Project Monitoring Report ( Public version)
HA-L1089
March 21, 2016
Project Monitoring Report ( Public version)
HA-L1089
March 16, 2016
Project Monitoring Report ( Public version)
HA-L1089
March 15, 2016