Land tenure security program in rural areas

Increase land tenure security of rural households in pilot targeted areas and improve the quality of land administration services.

Project Detail

Country

Haiti

Project Number

HA-L1056

Approval Date

April 25, 2012

Project Status

Closed

Project Type

Grant Financing Product

Sector

AGRICULTURE AND RURAL DEVELOPMENT

Subsector

LAND ADMINISTRATION AND MANAGEMENT

Lending Instrument

Préstamo de Inversión

Lending Instrument Code

INV

Modality

ESP (Specific Investment Operation)

Facility Type

-

Environmental and Social Impact Category (ESIC)

Category B: Likely to cause mostly local and short-term negative environmental and associated social impacts and for which effective mitigation measures are readily available

Total Cost

USD 27,000,000.00

Country Counterpart Financing

USD 0.00

Original Amount Approved

USD 27,000,000.00

Can’t find a document? Request information

Closed Phase
https://www.iadb.org/document.cfm?id=EZSHARE-391126077-18
Project Completion Report
PCR - Public - HA-L1056.pdf
Mar. 03, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-391126077-14
Project Completion Report
PCR - EEO4 - Note from Beneficiary - HA-L1056.pdf
Mar. 03, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-391126077-11
Project Completion Report
PCR - EEO3 - Final Evaluation.pdf
Mar. 03, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-391126077-10
Project Completion Report
PCR - EEO2 - Impact Evaluation Report - HA-L1056.docx
Mar. 03, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-391126077-5
Project Completion Report
PCR - EER1 - DEM Summary - HA-L1056.PDF
Mar. 03, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-391126077-6
Project Completion Report
PCR - EER2 - Changes to the Results Matrix - HA-L1056.xlsx
Mar. 03, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-391126077-8
Project Completion Report
PCR - EER4 - Checklist - HA-L1056.xlsx
Mar. 03, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-391126077-9
Project Completion Report
PCR - EEO1 - Expost Cost-Effectiveness Analysis - HA-L1056.docx
Mar. 03, 2021
English
Other Documents
https://www.iadb.org/document.cfm?id=EZSHARE-391126077-7
PCR - EER3 - PMR Final Version - HA-L1056.xlsx
Mar. 03, 2021
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-38
Procurement
PPM modifié CIAT - 2720 _ GR-HA - JUIN 2016 [40458907].xlsx
Aug. 12, 2016
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-35
Procurement
CIAT-PSFMR-2720-CF-SFQC-03-15-AMI-RECRUTEMENT D_UNE FIRME-ETUDES DE L_IMPACT DU PSFMR-JANVIER 2015 (3) [39638042].DOCX
Dec. 31, 1999
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-24
Procurement
3_SOLLIC_EXPRESSINTERET [38139573].DOC
Nov. 13, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-1537888330-2528
Elegibility Review Meeting
HAITI_ HA-L1056- Land Tenure Security Program - Project Profile (PP), and HA-T1142 -Preparation of the Land T [35577801].MSG
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1537888330-2527
Elegibility Review Meeting
RE_ HAITI_ HA-L1056- Land Tenure Security Program - Project Profile (PP), and HA-T1142 -Preparation of the La [35577067].MSG
Dec. 31, 1999
Spanish
Implementation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-382
Procurement Plan
2720_GR-HA PPM CIAT 2017 [40839983].XLSX
Feb. 07, 2017
French
https://www.iadb.org/document.cfm?id=EZSHARE-1935787862-7
Project Monitoring Report ( Public version)
HA-L1056 First period Jan-Jun 2016-Public Report [40799047].PDF
Dec. 27, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1935787862-6
Project Monitoring Report ( Public version)
HA-L1056 Second period Jan-Dec 2015-Public Report [40377325].PDF
Jul. 05, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-37
Procurement Plan
Plan Passation de Marches 2720_GR-HA, 2016- FONCIER [40260866].xlsx
Apr. 29, 2016
French
https://www.iadb.org/document.cfm?id=EZSHARE-1935787862-5
Project Monitoring Report ( Public version)
HA-L1056 First period Jan-Jun 2015-Public Report [40194378].PDF
Mar. 21, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1935787862-4
Project Monitoring Report ( Public version)
HA-L1056 Second period Jan-Dec 2014-Public Report [40185512].PDF
Mar. 16, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1935787862-3
Project Monitoring Report ( Public version)
HA-L1056 First period Jan-Jun 2014-Public Report [40181512].PDF
Mar. 15, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1935787862-2
Project Monitoring Report ( Public version)
HA-L1056 Second period Jan-Dec 2013-Public Report [40172087].PDF
Mar. 09, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-3109
Annual Project Audited Financial Statement
Etats Financiers Audites du Programme du Foncier execute par le CIAT et finance par le Don 2720_GR-HA au 30 Sept [40392796].PDF
Dec. 31, 1999
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-34
Procurement Plan
Don 2720_GR-HA - PSFMR - Plan de Passation des Marchés 2015 [39603157].xlsx
Apr. 29, 2015
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-33
Specific Procurement Notices
HA-L1056 [39593181].PDF
Apr. 23, 2015
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-32
Specific Procurement Notices
HA-L1056 [38959802].PDF
Jul. 30, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-31
Specific Procurement Notices
HA-L1056 [38930397].PDF
Jul. 17, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-30
Specific Procurement Notices
HA-L1056 [38772860].PDF
May. 02, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-29
Procurement Plan
Don 2720_GR-HA - PSFMR - Plan de Passations des Marchés 2014 [38765544].pdf
Apr. 29, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-25
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1056-2013-1º-Período [38265487].PDF
Mar. 06, 2014
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-26
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1056-2013-1º-Período [38266152].PDF
Mar. 06, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-27
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1056-2013-1º-Periodo [38266815].PDF
Mar. 06, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-28
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1056-2013-1º-Period [38267489].PDF
Mar. 06, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-36
Annual Project Audited Financial Statement
Etats Financiers Audites du Programme de Securite Fonciere en Milieu Rural PSFMAR avec les ressources du Don 272 [39845264].PDF
Feb. 05, 2016
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-23
Procurement Plan
Don 2720_GR-HA - PSFMR- Plan de Passation de Marché_2013-2017 [38052393].xlsx
Sep. 12, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-19
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1056-2012-2º-Período [37873267].PDF
Jul. 27, 2013
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-20
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1056-2012-2º-Período [37873935].PDF
Jul. 27, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-21
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1056-2012-2º-Periodo [37874592].PDF
Jul. 27, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-22
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1056-2012-2º-Period [37875412].PDF
Jul. 27, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-15
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1056-2012-1º-Período [37352158].PDF
Dec. 19, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-16
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1056-2012-1º-Período [37352818].PDF
Jan. 21, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-17
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1056-2012-1º-Periodo [37353477].PDF
Jan. 21, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-18
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1056-2012-1º-Period [37354137].PDF
Jan. 21, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-13
Loan Proposal
Haiti_ Land Tenure Security Program in Rural Areas [36806006].PDF
Apr. 16, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-14
Loan Proposal
Haití_ Programa de Seguridad de la Tenencia de la Tierra en Zonas Rurales [36806021].PDF
Apr. 16, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-31649
Project Monitoring Report ( Public version)
HA-L1056 First period Jan-Jun 2018-Public Report.pdf
Dec. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-1261068126-27
Procurement Plan
Don 2720-GR-HA Programme Securite fonciere Milieu Rural Janv 18- Juin 18.xlsx
Mar. 08, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-32337
Project Monitoring Report ( Public version)
HA-L1056 Second period Jan-Dec 2018-Public Report.pdf
Oct. 15, 2019
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-436
Project Monitoring Report ( Public version)
HA-L1056 Second period Jan-Dec 2016-Public Report.pdf
Feb. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-3252
Procurement Plan
PPM - PSFMR - CIAT (Actualisé - Juin 2016) 2720_GR-HA [40372355].xlsx
Jun. 27, 2017
French
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-1088
Project Monitoring Report ( Public version)
HA-L1056 First period Jan-Jun 2017-Public Report.pdf
Feb. 15, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-7400
Loan Contract
Contrat - Programme de Sécurité Foncière en Milieu Rural.pdf
Mar. 27, 2020
French
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-2007
Project Monitoring Report ( Public version)
HA-L1056 Second period Jan-Dec 2017-Public Report.pdf
Aug. 02, 2018
English
Preparation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-12
Environmental and Social Management Reports
Environmental and Social Management Report - ESMR [36657398].docx
Mar. 23, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-918336299-11
Project Profile
HAITI_ Land Tenure Security Program_ [35624298].PDF
Dec. 31, 1999
English

Have an Environmental or Social issue related to IDB projects? File a Complaint

Jump back to top