Péligre Hydroelectric Plant Rehabilitation Program

The objective of the program is to help restore and preserve Haiti's capacity to generate electrical power with renewable energy sources by rehabilitating the PHP, and to ensure the supply of electricity to Haiti's capital by rehabilitating the transmission line to Port-au-Prince. The rehabilitation of the PHP is designed to: (i) restore and maintain its generating capacity; (ii) improve the efficiency of the plant's generating units; and (iii) improve the conditions under which energy is transmitted from the PHP to Port-au-Prince. The program is designed so as to maximize resources and gain access to additional cofinancing resources. The rehabilitation works will take five years, to ensure that the PHP can continue to supply electricity in Haiti during execution.

Project Detail

Country

Haiti

Project Number

HA-L1032

Approval Date

December 2, 2008

Project Status

Closed

Project Type

Grant Financing Product

Sector

ENERGY

Subsector

NEW HYDROPOWER PROJECTS

Lending Instrument

Préstamo de Inversión

Lending Instrument Code

INV

Modality

ESP (Specific Investment Operation)

Facility Type

-

Environmental and Social Impact Category (ESIC)

Category B: Likely to cause mostly local and short-term negative environmental and associated social impacts and for which effective mitigation measures are readily available

Total Cost

USD 12,500,000.00

Country Counterpart Financing

USD 0.00

Original Amount Approved

USD 12,500,000.00

Financial Information
Operation Number Lending Type Reporting Currency Reporting Date Signed Date Fund Financial Instrument
2073/GR-HA Sovereign Guaranteed USD - United States Dollar IDB Grant Facility Account IDB Grant Facility
Operation Number 2073/GR-HA
  • Lending Type: Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: IDB Grant Facility Account
  • Financial Instrument: IDB Grant Facility

Can’t find a document? Request information

Other Documents
https://www.iadb.org/document.cfm?id=EZSHARE-328530853-5
Electronic Links
HA-L1032 and 1038__PCR Checklist Investment.xlsx
Mar. 10, 2023
English
https://www.iadb.org/document.cfm?id=EZSHARE-328530853-4
Electronic Links
HA_L1038_DEM Summary.pdf
Mar. 10, 2023
English
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-18
Procurement
Technical Analysis of Peligre Evaluation Report [35589085].docx
Dec. 31, 1999
French
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-17
Consultant Firm
Conditions Generals du Contrat_ de FICHTNER GmBH _ CO _ KB [35453199].PDF
Dec. 31, 1999
French
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-12
Proposal for Operation Development
Informe de Gestión Ambiental y Plan de Manejo Ambiental_ [1670144].DOC
Dec. 31, 1999
Spanish
Implementation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-34896
Project Monitoring Report ( Public version)
HA-L1032 Second period Jan-Dec 2020 - Public Report.pdf
Jul. 20, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-980848319-109
Annual Project Audited Financial Statement
EFAS 2019 Rapport d_audit revise 2684-Experts C.pdf
Jun. 12, 2024
French
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-34519
Project Monitoring Report ( Public version)
HA-L1032 First period Jan-Jun 2020 - Public Report.pdf
Mar. 09, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-33604
Project Monitoring Report ( Public version)
HA-L1032 Second period Jan-Dec 2019-Public Report.pdf
Aug. 25, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-84992730-7
Project Monitoring Report ( Public version)
HA-L1032 First period Jan-Jun 2016-Public Report [40799007].PDF
Dec. 27, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-84992730-6
Project Monitoring Report ( Public version)
HA-L1032 Second period Jan-Dec 2015-Public Report [40377311].PDF
Jul. 05, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-84992730-5
Project Monitoring Report ( Public version)
HA-L1032 First period Jan-Jun 2015-Public Report [40194369].PDF
Mar. 21, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-84992730-4
Project Monitoring Report ( Public version)
HA-L1032 Second period Jan-Dec 2014-Public Report [40185509].PDF
Mar. 16, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-84992730-3
Project Monitoring Report ( Public version)
HA-L1032 First period Jan-Jun 2014-Public Report [40181494].PDF
Mar. 15, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-84992730-2
Project Monitoring Report ( Public version)
HA-L1032 Second period Jan-Dec 2013-Public Report [40172088].PDF
Mar. 09, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-28274724-33
Annual Project Audited Financial Statement
Etats Financiers Audites du Projet de Remise en Etat de la Central Hydraulique de Peligre II avec les ressources [39850712].PDF
Feb. 05, 2016
French
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-44
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1032-2013-1º-Period [38267476].PDF
Mar. 06, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-41
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1032-2013-1º-Período [38265473].PDF
Mar. 06, 2014
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-42
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1032-2013-1º-Período [38266139].PDF
Mar. 06, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-43
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1032-2013-1º-Periodo [38266801].PDF
Mar. 06, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-37
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1032-2012-2º-Período [37873253].PDF
Jul. 27, 2013
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-38
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1032-2012-2º-Período [37873921].PDF
Jul. 27, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-39
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1032-2012-2º-Periodo [37874575].PDF
Jul. 27, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-40
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1032-2012-2º-Period [37875392].PDF
Jul. 27, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-36
Procurement Plan
Programme de rehabilitation de la centrale hydroelectrique de Peligre _ Plan de passation de marches 2013 _ [37633331].xlsx
Mar. 13, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-32
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1032-2012-1º-Período [37352145].PDF
Dec. 19, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-35
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1032-2012-1º-Period [37354123].PDF
Jan. 21, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-34
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1032-2012-1º-Periodo [37353464].PDF
Jan. 21, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-33
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1032-2012-1º-Período [37352804].PDF
Jan. 21, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-30
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1032-2011-2º-Periodo [36925190].PDF
Nov. 28, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-31
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1032-2011-2º-Period [36927928].PDF
Nov. 28, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-28
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1032-2011-2º-Período [36918607].PDF
Nov. 28, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-29
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1032-2011-2º-Período [36922605].PDF
Nov. 28, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-24
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1032-2011-1º-Período [36624024].PDF
Jan. 12, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-25
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1032-2011-1º-Período [36624604].PDF
Jan. 12, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-26
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1032-2011-1º-Periodo [36625159].PDF
Jan. 12, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-27
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1032-2011-1º-Period [36625722].PDF
Jan. 12, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-23
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1032-2010-2º-Period [36313317].PDF
Aug. 10, 2011
English
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-20
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1032-2010-2º-Período [36310255].PDF
Aug. 10, 2011
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-21
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1032-2010-2º-Período [36312153].PDF
Aug. 10, 2011
French
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-22
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1032-2010-2º-Periodo [36312742].PDF
Aug. 10, 2011
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-19
Specific Procurement Notices
REALISATION DE L’INGENIERIE DE LA LIGNE DE TRANSMISSION PELIGRE – PORT-AU-PRINCE [36143213].PDF
Dec. 31, 1999
English
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-16
Procurement Plan
Plan de Passations de Marches - Projet de Remise en Etat de la Centrale Hydroélectrique de Péligre - [35022410].XLSX
Dec. 31, 1999
French
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-14
Loan Proposal
Rehabilitación de la Central Hidroelécrica Peligre [1822824].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-15
Loan Proposal
Proposal for a grant for Peligre Hydroelectric Rehabilitation Program [1822848].PDF
Dec. 31, 1999
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-1054
Project Monitoring Report ( Public version)
HA-L1032 First period Jan-Jun 2017-Public Report.pdf
Feb. 15, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-2326
Project Monitoring Report ( Public version)
HA-L1032 Second period Jan-Dec 2017-Public Report.pdf
Aug. 03, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-31637
Project Monitoring Report ( Public version)
HA-L1032 First period Jan-Jun 2018-Public Report.pdf
Dec. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-32329
Project Monitoring Report ( Public version)
HA-L1032 Second period Jan-Dec 2018-Public Report.pdf
Oct. 15, 2019
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-32963
Project Monitoring Report ( Public version)
HA-L1032 First period Jan-Jun 2019-Public Report.pdf
Feb. 12, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-400
Project Monitoring Report ( Public version)
HA-L1032 Second period Jan-Dec 2016-Public Report.pdf
Feb. 14, 2018
English
Preparation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-11
Profile I
Perfil HA-L1032 [1622873].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1646601995-13
Environmental and Social Management Reports
Peligre Sedimentation Study Summary [1804863].PDF
Dec. 31, 1999
English