Skip to main content

Institutional Strengthening for Environmental Management

The objective of the operation is to improve environmental governance to ensure that the capacity exists at the national and local levels to address the priorities agreed upon in the Interim Cooperation Framework (CCI) and in accordance with the guidelines and policy framework of the National Action Plan for Environment.

Project Detail

Country

Haiti

Project Number

HA-L1006

Approval Date

October 21, 2005

Project Status

Closed

Project Type

Grant Financing Product

Sector

ENVIRONMENT AND NATURAL DISASTERS

Subsector

ENVIRONMENTAL MANAGEMENT AND GOVERNANCE

Lending Instrument

Investment Loan

Lending Instrument Code

INV

Modality

SEF (Sector Facility)

Facility Type

-

Environmental and Social Impact Category (ESIC)

Category C(R): (R) Likely to cause minimal or no negative environmental and associated social impacts

Total Cost

USD 5,045,000.00

Country Counterpart Financing

USD 45,000.00

Original Amount Approved

USD 5,000,000.00

Financial Information
Operation Number Lending Type Reporting Currency Reporting Date Signed Date Fund Financial Instrument
1668/SF-HA Sovereign Guaranteed USD - United States Dollar Fund for Special Operations Concessional Financing
2391/GR-HA Sovereign Guaranteed USD - United States Dollar IDB Grant Facility Account IDB Grant Facility
Operation Number 1668/SF-HA
  • Lending Type: Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: Fund for Special Operations
  • Financial Instrument: Concessional Financing
Operation Number 2391/GR-HA
  • Lending Type: Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: IDB Grant Facility Account
  • Financial Instrument: IDB Grant Facility

Can’t find a document? Request information

Closed Phase
https://www.iadb.org/document.cfm?id=EZSHARE-907890851-1804
Project Completion Report
Institutional Strengthening for Environmental Management [39054110].PDF
Sep. 15, 2014
English
Implementation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-7081
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1006-2013-1º-Período [38265467].PDF
Mar. 06, 2014
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-7346
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1006-2013-1º-Período [38266132].PDF
Mar. 06, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-7625
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1006-2013-1º-Periodo [38266795].PDF
Mar. 06, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-7904
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1006-2013-1º-Period [38267469].PDF
Mar. 06, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-6189
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1006-2012-2º-Período [37873914].PDF
Jul. 27, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-6492
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1006-2012-2º-Periodo [37874568].PDF
Jul. 27, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-6795
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1006-2012-2º-Period [37875383].PDF
Jul. 27, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-5886
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1006-2012-2º-Período [37873246].PDF
Jul. 27, 2013
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-4559
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1006-2012-1º-Período [37352137].PDF
Dec. 19, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-4893
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1006-2012-1º-Período [37352796].PDF
Dec. 19, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-5227
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1006-2012-1º-Periodo [37353456].PDF
Jan. 21, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-5561
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1006-2012-1º-Period [37354114].PDF
Jan. 21, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-3139
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1006-2011-2º-Período [36918588].PDF
Nov. 28, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-3352
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1006-2011-2º-Período [36922584].PDF
Nov. 28, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-3565
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1006-2011-2º-Periodo [36925167].PDF
Nov. 28, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-3778
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1006-2011-2º-Period [36927906].PDF
Nov. 28, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-907890851-1577
Procurement Plan
Plan dePassation Marchés 2012 PRIGE (2) [36741787].PDF
May. 24, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-1395
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-L1006-2010-2º-Period [36313309].PDF
Aug. 10, 2011
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-605
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-L1006-2010-2º-Período [36312146].PDF
Aug. 10, 2011
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-220
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-L1006-2010-2º-Período [36310248].PDF
Aug. 10, 2011
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-1205
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-L1006-2010-2º-Periodo [36312735].PDF
Aug. 10, 2011
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-907890851-942
Procurement Plan
Plan de Passation de Marchés - Renforcement Institutionnel pour la Gestion de l'Environnment [19069921].PDF
Dec. 31, 1999
French
https://www.iadb.org/document.cfm?id=EZSHARE-1537888330-8240
Loan Contract
Contrat de pret pour la Ggestion de l'Eenvironnement [589078].DOC
Dec. 31, 1999
French
https://www.iadb.org/document.cfm?id=EZSHARE-1537888330-8363
Loan Contract
Renforcement Institutionnel pour la Ggestion de l'Eenvironnement [590821].DOC
Dec. 31, 1999
French
https://www.iadb.org/document.cfm?id=EZSHARE-1537888330-8416
Loan Contract
Renforcement Institutionnel pour la Ggestion de l'Eenvironnement [590820].DOC
Dec. 31, 1999
French
https://www.iadb.org/document.cfm?id=EZSHARE-1537888330-8502
Loan Contract
Renforcement Institutionnel pour la Ggestion de l'Eenvironnement [589651].DOC
Dec. 31, 1999
French
https://www.iadb.org/document.cfm?id=EZSHARE-907890851-55
Loan Proposal
Resumen ejecutivo de la propuesta de préstamo de facilidad sectorial para el fortalecimiento institucional para la [645634].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-907890851-56
Loan Proposal
Executive summary of the proposal for a sector facility loan for the institutional strengthening for environmental [645636].PDF
Dec. 31, 1999
English

Have an Environmental or Social issue related to IDB projects? File a Complaint

Jump back to top