Project Detail
Country
Haiti
Project Number
HA-G1022
Approval Date
November 8, 2010
Project Status
Closed
Project Type
Investment Grants
Sector
ENERGY
Subsector
NEW HYDROPOWER PROJECTS
Lending Instrument
-
Lending Instrument Code
-
Modality
-
Facility Type
-
Environmental and Social Impact Category (ESIC)
Category B: Likely to cause mostly local and short-term negative environmental and associated social impacts and for which effective mitigation measures are readily available
Total Cost
USD 12,500,000.00
Country Counterpart Financing
USD 0.00
Original Amount Approved
USD 12,500,000.00
| Operation Number | Lending Type | Reporting Currency | Reporting Date | Signed Date | Fund | Financial Instrument |
|---|---|---|---|---|---|---|
| GRT/HR-12410-HA | Sovereign Guaranteed | USD - United States Dollar | Haiti Reconstruction Fund | Grant |
- Lending Type: Sovereign Guaranteed
- Reporting Currency: USD - United States Dollar
- Reporting Date:
- Signed Date:
- Fund: Haiti Reconstruction Fund
- Financial Instrument: Grant
Can’t find a document? Request information
https://www.iadb.org/document.cfm?id=EZSHARE-1070187509-109
Project Completion Report
HA-G1022 (Project Completion Report).pdf
Mar. 14, 2022
English
https://www.iadb.org/document.cfm?id=EZSHARE-1070187509-108
Project Completion Report
HA-G1022 (Rapport d'Achevement de Projet).pdf
Mar. 14, 2022
French
https://www.iadb.org/document.cfm?id=EZSHARE-1947324039-386
Annual Project Audited Financial Statement
GRT HR-12410-HA-2 Audit final de la periode allant du 1er janvier 2020 au 31 mars 2021.pdf
Sep. 09, 2021
French
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-34935
Project Monitoring Report ( Public version)
HA-G1022 Second period Jan-Dec 2020 - Public Report.pdf
Jul. 20, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-1947324039-382
Annual Project Audited Financial Statement
EFA2021 EFUCP-MTPTC 12410- Septembre 2020_ (3) (1).pdf
Aug. 15, 2021
French
https://www.iadb.org/document.cfm?id=EZSHARE-1947324039-380
Annual Project Audited Financial Statement
EFA2021Final EFUCP-MTPTC 12410- 1er octobre 2020 au 31 mars 2021.pdf
Jul. 25, 2021
French
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-34509
Project Monitoring Report ( Public version)
HA-G1022 First period Jan-Jun 2020 - Public Report.pdf
Mar. 09, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-33594
Project Monitoring Report ( Public version)
HA-G1022 Second period Jan-Dec 2019-Public Report.pdf
Aug. 24, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-1375635338-25687
Specific Procurement Notices
HA-G1022_P534751_SP.pdf
Jun. 24, 2020
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-8972
Project Monitoring Report ( Public version)
HA-G1022 First period Jan-Jun 2016-Public Report (1) [40799362].PDF
Jan. 10, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-30
Project Monitoring Report ( Public version)
HA-G1022 Second period Jan-Dec 2015-Public Report [40381737].PDF
Aug. 08, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-29
Project Monitoring Report ( Public version)
HA-G1022 First period Jan-Jun 2015-Public Report (1) [40194553].PDF
Apr. 04, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-28
Project Monitoring Report ( Public version)
HA-G1022 Second period Jan-Dec 2014-Public Report [39824018].PDF
Sep. 04, 2015
English
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-27
Project Monitoring Report ( Public version)
HA-G1022 First period Jan-Jun 2014-Public Report [39823202].PDF
Sep. 04, 2015
English
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-26
Project Monitoring Report ( Public version)
HA-G1022_Second_period_Jan-Dec_2013-Public_Report [39813868].PDF
Sep. 03, 2015
English
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-25
Loan Proposal
LP_ Proposal for Non-Reimbursable Financing [39676118].PDF
Jun. 11, 2015
English
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-24
Loan Proposal
LP_ Propuesta de Financiamiento No Reembolsable [39676117].PDF
Jun. 11, 2015
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-20
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-G1022-2013-1º-Período [38265462].PDF
Mar. 06, 2014
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-21
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-G1022-2013-1º-Período [38266127].PDF
Mar. 06, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-22
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-G1022-2013-1º-Periodo [38266790].PDF
Mar. 06, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-23
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-G1022-2013-1º-Period [38267464].PDF
Mar. 06, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-16
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-G1022-2012-2º-Período [37873242].PDF
Jul. 27, 2013
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-17
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-G1022-2012-2º-Período [37873909].PDF
Jul. 27, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-18
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-G1022-2012-2º-Periodo [37874563].PDF
Jul. 27, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-19
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-G1022-2012-2º-Period [37875378].PDF
Jul. 27, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-15
Project Monitoring Report ( Public version)
Report for Publication_PMR-_HA-G1022-2012-1º-Period [37354109].PDF
Jan. 21, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-12
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_HA-G1022-2012-1º-Período [37352131].PDF
Dec. 19, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-13
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_HA-G1022-2012-1º-Período [37352790].PDF
Dec. 19, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-14
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_HA-G1022-2012-1º-Periodo [37353450].PDF
Jan. 21, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-90
Loan Proposal
Programa de Apoyo al Desarrollo Productivo_ Propuesta_ [37342034].PDF
Dec. 14, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1532196850-11
Loan Proposal
Program to Support Productive Development_ Proposal [37279660].PDF
Dec. 14, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-5445
Loan Contract
Amendment 2 - Programme de Soutien aux Chaines de Production.pdf
Aug. 27, 2018
French
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-708
Project Monitoring Report ( Public version)
HA-G1022 Second period Jan-Dec 2016-Public Report.pdf
Feb. 15, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-1132444900-21450
Specific Procurement Notices
HA-G1022 1203.pdf
Jan. 03, 2019
French
https://www.iadb.org/document.cfm?id=EZSHARE-1470197173-48143
Loan Contract
Apoyo Financiero para Reforzar Líneas de Transmisión y Rehabilitar Infraestructura Vial - Tercera Enmienda a la Resolución.pdf
Oct. 24, 2018
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-1379
Project Monitoring Report ( Public version)
HA-G1022 First period Jan-Jun 2017-Public Report.pdf
Feb. 15, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-1470197173-48144
Loan Contract
Financial Support for the Reinforcement of Transmission Lines and Road Infrastructure Rehabilitation - Third Amendment to Resolution.pdf
Oct. 22, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-2402
Project Monitoring Report ( Public version)
HA-G1022 Second period Jan-Dec 2017-Public Report.pdf
Aug. 07, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-31622
Project Monitoring Report ( Public version)
HA-G1022 First period Jan-Jun 2018-Public Report.pdf
Dec. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-32316
Project Monitoring Report ( Public version)
HA-G1022 Second period Jan-Dec 2018-Public Report.pdf
Oct. 15, 2019
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-33240
Project Monitoring Report ( Public version)
HA-G1022 First period Jan-Jun 2019-Public Report.pdf
Feb. 13, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-239514878-39
Project Profile
Perfil de Proyecto - Apoyo a Cadenas de Agronegocios [37618959].PDF
Apr. 23, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1070187509-22
Project Profile
PP aprobado HA-G1022-Reformulation para publicación.pdf
Jun. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-1831254404-10
Environmental and Social Execution
Péligre_TL_EIES _141121.pdf
Jul. 24, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-1831254404-11
Environmental and Social Execution
AIC-Plan de Gestion Environnemental Social (PGES) Post-Matthew-Lots2-3-FINAL.PDF
Jul. 24, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-1831254404-12
Resettlement Plans
Plan de Reinstallation 07 2018.docx
Aug. 29, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-6223
General Agreement
Avenant No. 3 - Soutien Financier pour le Renforcement des Lignes de Transmission et la Ré.pdf
Apr. 18, 2019
French
Have an Environmental or Social issue related to IDB projects? File a Complaint