DR-L1041 : INAPA Water and Sanitation Investment Program
Project Status: Closed
The program objectives are to (i) to help expand the coverage of efficient, sustainable water and sanitation services in the seven provinces; (ii) to deconcentrate the delivery of water and sanitation services in urban and periurban areas in those seven provinces to four regional INAPA offices, and in rural areas to Asociaciones Comunitarias de Acueductos Rurales [rural community water associations] (ASOCARs), providing administrative, technical, and operational support to these offices as well as human resources training and equipment, so they become efficient in terms of revenues, costs, and operations; and (iii) strengthen commercial, technical/operational, and administrative management at INAPA¿s main offices so it can better deliver services in the other provinces under its responsibility and perform its planning and supervisory functions in the provinces for which service is to be deconcentrated.
Project Detail
Project Country
Dominican Republic
Project Sector
WATER AND SANITATION
Project Subsector
WATER AND SANITATION
Project Type
Loan Operation
Project Modality
ESP (Specific Investment Operation)
Environmental and social impact category
B
Operation Number
2430/OC-DR
Financial Information
IDB Financing
Reporting currency
USD - United States Dollar
Reporting date
Jul/18/2023
Roles & Responsibilities
Contract signature date
Nov/08/2010
Preparation
Title
Type
Project Number
Date Published
Environmental Analyses
2430/OC-DR;DR-L1041
August 10, 2010
Project Profile
DR-L1041
May 20, 2010
Approved
Title
Type
Project Number
Date Published
Loan Contract
DR-L1005; DR-L1008; DR-L1029; DR-L1026; DR-L1039; DR-L1032; DR-L1044; DR-L1041; DR-L1031; DR-L1035; DR-L1048; DR-L1047; DR-L1036
June 21, 2022
Loan Contract
DR-L1041
March 19, 2020
Loan Proposal
DR-L1041;DR-X1005
November 01, 2010
Loan Proposal
DR-L1041;DR-X1005
November 01, 2010
Implementation
Title
Type
Project Number
Date Published
Project Monitoring Report ( Public version)
DR-L1041
February 09, 2023
Annual Project Audited Financial Statement
DR-L1041
January 04, 2023
Project Monitoring Report ( Public version)
DR-L1041
August 12, 2022
Annual Project Audited Financial Statement
DR-L1041
August 04, 2022
Project Monitoring Report ( Public version)
DR-L1041
February 20, 2022
Annual Project Audited Financial Statement
DR-L1041
July 23, 2021
Project Monitoring Report ( Public version)
DR-L1041
July 20, 2021
Project Monitoring Report ( Public version)
DR-L1041
March 09, 2021
Annual Project Audited Financial Statement
DR-L1041
December 08, 2020
Project Monitoring Report ( Public version)
DR-L1041
August 24, 2020
Project Monitoring Report ( Public version)
DR-L1041
February 12, 2020
Project Monitoring Report ( Public version)
DR-L1041
October 15, 2019
Annual Project Audited Financial Statement
DR-L1041
July 01, 2019
Project Monitoring Report ( Public version)
DR-L1041
December 14, 2018
Project Monitoring Report ( Public version)
DR-L1041
August 06, 2018
Annual Project Audited Financial Statement
DR-L1041
June 12, 2018
Project Monitoring Report ( Public version)
DR-L1041
February 15, 2018
Project Monitoring Report ( Public version)
DR-L1041
February 14, 2018
Annual Project Audited Financial Statement
DR-L1041
December 21, 2017
Project Monitoring Report ( Public version)
DR-L1041
June 24, 2016
Project Monitoring Report ( Public version)
DR-L1041
March 15, 2016
Project Monitoring Report ( Public version)
DR-L1041
March 14, 2016
Project Monitoring Report ( Public version)
DR-L1041
March 11, 2016
Project Monitoring Report ( Public version)
DR-L1041
March 10, 2016
Annual Project Audited Financial Statement
2430/OC-DR;DR-L1041;GRT/WS-12442-DR
December 31, 2015
Annual Project Audited Financial Statement
2430/OC-DR;DR-L1041;GRT/WS-12442-DR
December 31, 2014
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
October 31, 2013
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
October 31, 2013
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
October 31, 2013
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
October 31, 2013
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
May 07, 2013
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
May 07, 2013
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
May 07, 2013
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
May 07, 2013
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
December 11, 2012
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
December 11, 2012
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
December 11, 2012
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
December 11, 2012
Procurement Plan
2430/OC-DR;DR-L1041
November 27, 2012
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
May 14, 2012
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
May 14, 2012
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
May 14, 2012
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
May 14, 2012
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
November 18, 2011
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
November 18, 2011
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
November 18, 2011
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
November 18, 2011
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
June 22, 2011
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
June 22, 2011
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
June 22, 2011
Project Monitoring Report ( Public version)
2430/OC-DR;DR-L1041
June 22, 2011
Procurement Plan
DR-L1041
November 18, 2010