Skip to main content
Reventazon Hydroelectric Power Project
The Project will use the waters of Reventazón river to generate approximately 1573 GW/h of electricity per year. The energy produced by the Project will be used by ICE to supply the increased demand for electricity in Costa Rica.

Project Detail

Country

Costa Rica

Project Number

CR-L1056

Approval Date

October 19, 2012

Project Status

Closed

Project Type

Loan Operation

Sector

ENERGY

Subsector

NEW HYDROPOWER PROJECTS

Lending Instrument

BID Invest

Lending Instrument Code

IIC

Modality

PSL (Private Sector Loan)

Facility Type

-

Environmental Classification

-

Total Cost

USD 1,345,000,000.00

Country Counterpart Financing

USD 770,000,000.00

Original Amount Approved

USD 102,000,000.00

Financial Information
Operation Number Lending Type Reporting Currency Reporting Date Signed Date Fund Financial Instrument
2806A/OC-CR Non-Sovereign Guaranteed USD - United States Dollar Ordinary Capital Private Sector Financing
2806B/OC-CR-CF-REVEKYB Non-Sovereign Guaranteed USD - United States Dollar Ordinary Capital Participant Financing
Operation Number 2806A/OC-CR
  • Lending Type: Non-Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: Ordinary Capital
  • Financial Instrument: Private Sector Financing
Operation Number 2806B/OC-CR-CF-REVEKYB
  • Lending Type: Non-Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: Ordinary Capital
  • Financial Instrument: Participant Financing

Can’t find a document? Request information

Other Documents
https://www.iadb.org/document.cfm?id=EZSHARE-172347887-26865
Independent Consultation and Investigation Mechanism
MICI-BID-CR-2016-0110 Reventazon Hydroelectric Project - Management Response for eligibility - Final [40722803].PDF
Nov. 04, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-172347887-26870
Independent Consultation and Investigation Mechanism
MICI-BID-CR-2016-0110 Annex 4 - Evidencia_Informe de avance de indicadores (public) [40722815].PDF
Nov. 09, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1001384165-27442
Technical Note
An Expanded Cost-Benefit Analysis (CBA) of the Reventazon Hydroelectric Project (PHR), in Costa Rica [38039540].PDF
Dec. 31, 1999
English
Implementation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-1231689932-860
Agreement - Financial Closing - SCF
Proyecto Hidroeléctrico Reventazón [37022851].PDF
Aug. 04, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1231689932-856
Agreement - Financial Closing - SCF
Reventazón Hydropower Project [37022625].PDF
Aug. 04, 2014
English
Preparation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-1231689932-859
Environmental Analyses
Estudios ambientales PHR Fase II [36879024].PDF
May. 25, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1231689932-861
Environmental and Social Management Reports
CR-L1049-CR-L1056 - Reventazon Hydropower Project - ESMR [36879354].PDF
May. 25, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1001384165-18
Environmental Analyses
Estudios Fase II Final [36879285].PDF
Aug. 22, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1231689932-857
Environmental Analyses
Marco Estrategico de Restitucion o Mejoras de Condiciones de Vida PH Reventazón [36878994].PDF
May. 25, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1001384165-27444
Environmental Impact Assessments
Proyecto Hidroelectrico Reventazon - Estudios Ambientales Adicionales Fase 1 [36689542].PDF
Mar. 23, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1001384165-27445
Environmental Impact Assessments
Parte A - Resumen Ejecutivo [36689432].PDF
Feb. 24, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1001384165-27446
Environmental Impact Assessments
Parte G - Peces y su habitat [36689446].PDF
Feb. 24, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1001384165-27447
Environmental Impact Assessments
Parte H - Efectos Acumulativos [36689449].PDF
Feb. 24, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1001384165-27450
Environmental Impact Assessments
Parte C - Estudio de sedimentos [36689438].PDF
Feb. 24, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1001384165-27451
Environmental Impact Assessments
Parte I - Emisiones de Gases de Efecto Invernadero [36689431].PDF
Feb. 24, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1001384165-27443
Environmental Impact Assessments
Parte E - Plan de Manejo de la Biodiversidad [36689443].PDF
Feb. 24, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1001384165-27448
Environmental Impact Assessments
Parte F - Propuesta de Proyecto de Compensación de Biodiversidad [36689445].PDF
Feb. 24, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1001384165-27449
Environmental Impact Assessments
Parte D - Plan de Manejo de la Construccion [36689442].PDF
Feb. 24, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1001384165-27441
Environmental Impact Assessments
Parte B - Estudio de Calidad del Agua [36689437].PDF
Feb. 24, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1231689932-855
Environmental Impact Assessments
Environmental_Impact_Assesment-Reventazon Hydroelectric Power Plant [36683639].PDF
Feb. 14, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1231689932-858
Project Abstract
Project Abstract-Reventazon Hydroelectric Power Project [36683842].PDF
Feb. 14, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1864519405-2
Environmental Impact Assessments
Environmental Impact Assesment [36447344].PDF
Oct. 04, 2011
Spanish

Have an Environmental or Social issue related to IDB projects? File a Complaint

Jump back to top