CR-L1049 : Power Sector Development Program 2012-2016 (Reventazon Hydroelectric Project)
Project Status: Closed
The objective of this operation is contributing to meet the growing electricity demand, maintaining adequate levels of quality, reliability and cost, by financing the RHP.
Project Detail
Project Number
CR-L1049
Project Country
Costa Rica
Project Sector
ENERGY
Project Subsector
NEW HYDROPOWER PROJECTS
Project Type
Loan Operation
Project Lending Type
SG
Project Modality
ESP (Specific Investment Operation)
Project Facility Type
Environmental and social impact category
A
Project Status
Closed
Operation Number
2747/OC-CR
Financial Information
Project Number
CR-L1049
Project Status
Closed
IDB Financing
Financing type
FFF
Fund
Ordinary Capital
Reporting currency
USD - United States Dollar
Reporting date
Jun/09/2023
Roles & Responsibilities
Contract signature date
Oct/31/2012
Project Information
Total Cost
USD 291,700,000
Country counterpart financing
USD 41,700,000
Amount
USD 250,000,000
Preparation
Title
Type
Project Number
Date Published
Environmental Analyses
2747/OC-CR;ATN/OC-13556-CR;CR-L1049;CR-T1086
June 06, 2016
Environmental Analyses
2747/OC-CR;ATN/OC-13556-CR;CR-L1049;CR-T1086
May 26, 2016
Environmental Analyses
2747/OC-CR;CR-L1049
May 26, 2016
Environmental Analyses
2747/OC-CR;CR-L1049
May 26, 2016
Environmental Analyses
2747/OC-CR;CR-L1049
May 26, 2016
Environmental Analyses
2747/OC-CR;CR-L1049
May 26, 2016
Environmental Analyses
2747/OC-CR;CR-L1049
May 26, 2016
Environmental Analyses
2747/OC-CR;CR-L1049
May 26, 2016
Environmental & Social Management Reports
2747/OC-CR;ATN/OC-13556-CR;CR-L1049;CR-T1086
May 26, 2016
Environmental Analyses
2747/OC-CR;ATN/OC-13556-CR;CR-L1049;CR-T1086
May 26, 2016
Environmental Analyses
2747/OC-CR;ATN/OC-13556-CR;CR-L1049;CR-T1086
May 26, 2016
Environmental Analyses
2747/OC-CR;ATN/OC-13556-CR;CR-L1049;CR-T1086
May 26, 2016
Environmental & Social Management Reports
2747/OC-CR;ATN/OC-13556-CR;CR-L1049;CR-T1086
December 23, 2015
Environmental & Social Management Reports
2747/OC-CR;ATN/OC-13556-CR;CR-L1049
November 05, 2015
Environmental & Social Management Reports
2747/OC-CR;ATN/OC-13556-CR;CR-L1049;CR-T1086
November 05, 2015
Environmental & Social Management Reports
2747/OC-CR;ATN/OC-13556-CR;CR-L1049;CR-T1086
November 05, 2015
Environmental Analyses
CR-L1049;CR-L1056
May 24, 2012
Environmental Analyses
CR-L1049;CR-L1056
May 24, 2012
Environmental & Social Management Reports
CR-L1049;CR-L1056
May 24, 2012
Profile I
CR-L1049
March 23, 2012
Environmental Impact Assessments
CR-L1049;CR-L1056
February 18, 2012
Environmental Impact Assessments
CR-L1049;CR-L1056
February 17, 2012
Environmental Impact Assessments
CR-L1049;CR-L1056
February 17, 2012
Environmental Impact Assessments
CR-L1049;CR-L1056
February 17, 2012
Environmental Impact Assessments
CR-L1049;CR-L1056
February 17, 2012
Environmental Impact Assessments
CR-L1049;CR-L1056
February 17, 2012
Environmental Impact Assessments
CR-L1049;CR-L1056
February 17, 2012
Environmental Impact Assessments
CR-L1049;CR-L1056
February 14, 2012
Environmental Impact Assessments
CR-L1049;CR-L1056
February 14, 2012
Environmental Impact Assessments
CR-L1049;CR-L1056
February 14, 2012
Environmental Impact Assessments
CR-L1049;CR-L1056
October 04, 2011
Project Profile
CR-L1049
May 23, 2011
Project Profile
CR-L1049
December 21, 2010
Approved
Title
Type
Project Number
Date Published
Loan Contract
CR-L1070; CR-L1009; CR-L1049
April 05, 2023
Loan Contract
CR-L1049
March 12, 2020
Loan Contract
CR-L1049
May 08, 2018
Loan Contract
2747/OC-CR;CR-L1049
February 17, 2014
An Expanded Cost-Benefit Analysis (CBA) of the Reventazon Hydroelectric Project (PHR), in Costa Rica
Technical Note
CR-L1049;CR-L1056
September 05, 2013
Loan Proposal
CR-L1049
July 05, 2012
Loan Proposal
CR-L1049
July 05, 2012
Loan Contract
2747/OC-CR;CR-L1049;CR-X1005
June 25, 2012
Loan Contract
2747/OC-CR;CR-L1049;CR-X1005
June 25, 2012
Implementation
Title
Type
Project Number
Date Published
Project Monitoring Report ( Public version)
CR-L1049
March 09, 2021
Annual Project Audited Financial Statement
CR-L1049
February 02, 2021
Project Monitoring Report ( Public version)
CR-L1049
August 24, 2020
Annual Project Audited Financial Statement
CR-L1049
June 25, 2020
Notice of Contract Award (SG)
CR-L1049
February 28, 2020
Project Monitoring Report ( Public version)
CR-L1049
February 12, 2020
Project Monitoring Report ( Public version)
CR-L1049
October 15, 2019
Annual Project Audited Financial Statement
CR-L1049
June 03, 2019
Project Monitoring Report ( Public version)
CR-L1049
December 14, 2018
Project Monitoring Report ( Public version)
CR-L1049
August 02, 2018
Financial Statements
CR-L1049
June 12, 2018
Annual Project Audited Financial Statement
CR-L1049
April 19, 2018
Project Monitoring Report ( Public version)
CR-L1049
February 14, 2018
Project Monitoring Report ( Public version)
CR-L1049
February 14, 2018
Project Monitoring Report ( Public version)
CR-L1049
December 23, 2016
Project Monitoring Report ( Public version)
CR-L1049
June 24, 2016
Project Monitoring Report ( Public version)
CR-L1049
March 15, 2016
Project Monitoring Report ( Public version)
CR-L1049
March 14, 2016
Project Monitoring Report ( Public version)
CR-L1049
March 11, 2016
Project Monitoring Report ( Public version)
CR-L1049
March 10, 2016
Financial Statements
1908/OC-CR;2747/OC-CR;CR-L1009;CR-L1049
June 06, 2014
Project Monitoring Report ( Public version)
2747/OC-CR;CR-L1049
October 31, 2013
Project Monitoring Report ( Public version)
2747/OC-CR;CR-L1049
October 31, 2013
Project Monitoring Report ( Public version)
2747/OC-CR;CR-L1049
October 31, 2013
Project Monitoring Report ( Public version)
2747/OC-CR;CR-L1049
October 31, 2013
Project Monitoring Report ( Public version)
2747/OC-CR;CR-L1049
May 07, 2013
Project Monitoring Report ( Public version)
2747/OC-CR;CR-L1049
May 07, 2013
Project Monitoring Report ( Public version)
2747/OC-CR;CR-L1049
May 07, 2013
Project Monitoring Report ( Public version)
2747/OC-CR;CR-L1049
May 07, 2013
Project Monitoring Report ( Public version)
2747/OC-CR;CR-L1049
December 11, 2012
Project Monitoring Report ( Public version)
2747/OC-CR;CR-L1049
December 11, 2012
Project Monitoring Report ( Public version)
2747/OC-CR;CR-L1049
December 11, 2012
Project Monitoring Report ( Public version)
2747/OC-CR;CR-L1049
December 11, 2012
Procurement Plan
CR-L1049
May 16, 2012
Completed
Title
Type
Project Number
Date Published
Project Completion Report
CR-L1049
September 20, 2021