Can’t find a document? Request Information

BR-L1326 : Road Program for Logistic and Integration - Ceara IV

Project Status: Closed

The overall objective is to support sustainable economic development of the State, improving the integration of domestic productive regions or from other states, with regional consumer markets and export logistics nodes (ports and airports). The specific objectives are: (i) improve the mobility of key strategic corridors and their multimodal connectivity (ii) partially remove the discontinuities in the paved network, increasing capacity and efficiency, (iii) support the sustainability of investments by funding a result-driven maintenance pilot, and (iv) improve institutional capacity in managing the freight logistics system.

Project Detail

Project Number
BR-L1326
Project Country
Brazil
Project Sector
TRANSPORT
Project Subsector
MAJOR HIGHWAYS
Project Type
Loan Operation
Project Lending Type
SG
Project Modality
ESP (Specific Investment Operation)
Project Facility Type
Environmental and social impact category
B
Project Status
Closed
Operation Number
2964/OC-BR

Financial Information

Project Number
BR-L1326
Project Status
Closed

IDB Financing

Financing type
FFF
Fund
Ordinary Capital
Reporting currency
USD - United States Dollar
Reporting date
Jul/18/2023

Roles & Responsibilities

Contract signature date
Dec/27/2013

Project Information

Total Cost
USD 504,116,667
Country counterpart financing
USD 104,116,667
Amount
USD 400,000,000

Preparation

Title
Type
Project Number
Date Published
Environmental Impact Assessments
BR-L1326
July 13, 2012
Environmental & Social Management Reports
BR-L1326
July 13, 2012

Approved

Title
Type
Project Number
Date Published
Loan Contract
2964/OC-BR;BR-L1326
December 27, 2013
Loan Contract
2964/OC-BR;BR-L1326
July 24, 2013
Loan Contract
2964/OC-BR;BR-L1326
July 24, 2013

Implementation

Title
Type
Project Number
Date Published
Project Monitoring Report ( Public version)
BR-L1326
February 13, 2020
Project Monitoring Report ( Public version)
BR-L1326
October 15, 2019
Project Monitoring Report ( Public version)
BR-L1326
December 14, 2018
Project Monitoring Report ( Public version)
BR-L1326
August 02, 2018
Project Monitoring Report ( Public version)
BR-L1326
February 15, 2018
Project Monitoring Report ( Public version)
BR-L1326
February 15, 2018
Project Monitoring Report ( Public version)
BR-L1326
December 28, 2016
Procurement Plan
2964/OC-BR;BR-L1326
August 02, 2016
Project Monitoring Report ( Public version)
BR-L1326
June 27, 2016
Project Monitoring Report ( Public version)
BR-L1326
March 21, 2016
Project Monitoring Report ( Public version)
BR-L1326
March 16, 2016
Project Monitoring Report ( Public version)
BR-L1326
March 16, 2016
Annual Project Audited Financial Statement
2964/OC-BR;BR-L1326
December 31, 2015
Procurement Plan
2964/OC-BR;BR-L1326
December 10, 2015
Procurement Plan
2964/OC-BR;BR-L1326
March 12, 2015
Annual Project Audited Financial Statement
2964/OC-BR;BR-L1326
December 31, 2014
Procurement Plan
2964/OC-BR;BR-L1326
December 19, 2014
Procurement Plan
2964/OC-BR;BR-L1326
May 14, 2014
Procurement Plan
2964/OC-BR;BR-L1326
September 19, 2013
Procurement Plan
BR-L1326
July 25, 2012