Can’t find a document? Request Information

BR-L1303 : CEEE Generation and Transmission Project

Project Status: Closed

The operation's objective is to expand, rehabilitate and modernize the generation and transmission infrastructure of the CEEE-GT, in order to improve the reliability of the service which includes the metropolitan region of Porto Alegre in the Rio Grande do Su, to serve the incresing electricity demand and to update tecnologically the infraestructure. The Invesment Program will help to guarantee the construction of the required electricity infrastructure to support the increase in demand with an expected peak during the World Cup 2014.

Project Detail

Project Number
BR-L1303
Project Country
Brazil
Project Sector
ENERGY
Project Subsector
NEW POWER DISTRIBUTION & TRANSMISSION PROJECTS
Project Type
Loan Operation
Environmental and social impact category
B
Project Status
Closed
Operation Number
2813/OC-BR

Financial Information

Project Number
BR-L1303
Project Status
Closed

IDB Financing

Financing type
FFF
Fund
Ordinary Capital
Reporting currency
USD - United States Dollar
Reporting date
Jan/18/2021

Roles & Responsibilities

Contract signature date
Dec/28/2012

Project Information

Total Cost
USD 147,759,953
Country counterpart financing
USD 59,103,957
Amount
USD 88,655,996

Preparation

Title
Type
Project Number
Date Published
Environmental Impact Assessments
2813/OC-BR;BR-L1303
July 29, 2015
Project Abstract
BR-L1303
June 21, 2011
Environmental & Social Strategies
BR-L1303
March 24, 2011

Implementation

Title
Type
Project Number
Date Published
Annual Project Audited Financial Statement
BR-L1303
December 10, 2020
Project Monitoring Report ( Public version)
BR-L1303
February 12, 2020
Project Monitoring Report ( Public version)
BR-L1303
October 15, 2019
Procurement Plan
BR-L1303
February 01, 2019
Project Monitoring Report ( Public version)
BR-L1303
December 14, 2018
Project Monitoring Report ( Public version)
BR-L1303
August 02, 2018
Procurement Plan
BR-L1303
March 23, 2018
Project Monitoring Report ( Public version)
BR-L1303
February 14, 2018
Project Monitoring Report ( Public version)
BR-L1303
February 14, 2018
Procurement Plan
BR-L1303
December 21, 2017
Specific Procurement Notices
BR-L1303
February 03, 2017
Specific Procurement Notices
BR-L1303
January 25, 2017
Specific Procurement Notices
BR-L1303
January 23, 2017
Specific Procurement Notices
BR-L1303
January 13, 2017
Project Monitoring Report ( Public version)
BR-L1303
December 28, 2016
Specific Procurement Notices
BR-L1303
December 19, 2016
Procurement Plan
2813/OC-BR;BR-L1303
September 16, 2016
Consultant Firm
BR-L1303
September 08, 2016
Project Monitoring Report ( Public version)
BR-L1303
June 27, 2016
Project Monitoring Report ( Public version)
BR-L1303
March 21, 2016
Project Monitoring Report ( Public version)
BR-L1303
March 16, 2016
Project Monitoring Report ( Public version)
BR-L1303
March 16, 2016
Project Monitoring Report ( Public version)
BR-L1303
March 16, 2016
Annual Project Audited Financial Statement
2813/OC-BR;BR-L1303
December 31, 2015
Annual Project Audited Financial Statement
2813/OC-BR;BR-L1303
December 31, 2015
Procurement Plan
2813/OC-BR;BR-L1303
August 06, 2015
Annual Project Audited Financial Statement
2813/OC-BR;BR-L1303
December 31, 2014
Procurement Plan
2813/OC-BR;BR-L1303
November 20, 2013
Project Monitoring Report ( Public version)
2813/OC-BR;BR-L1303
October 31, 2013
Project Monitoring Report ( Public version)
2813/OC-BR;BR-L1303
October 31, 2013
Project Monitoring Report ( Public version)
2813/OC-BR;BR-L1303
October 31, 2013
Project Monitoring Report ( Public version)
2813/OC-BR;BR-L1303
October 31, 2013
Project Monitoring Report ( Public version)
2813/OC-BR;BR-L1303
May 07, 2013
Project Monitoring Report ( Public version)
2813/OC-BR;BR-L1303
May 07, 2013
Project Monitoring Report ( Public version)
2813/OC-BR;BR-L1303
May 07, 2013
Project Monitoring Report ( Public version)
2813/OC-BR;BR-L1303
May 07, 2013

Completed

Title
Type
Project Number
Date Published
Project Completion Report
BR-L1303
September 16, 2020