Skip to main content

PROCIDADES-Maringá: Municipality of Maringá Urban Mobility Program

To promote the improvement of quality of life of Maringa's inhabitants through the implementation of mobility and urban transportation projects. The specific objectives of the operation are: i) to improve the public transportation system; ii) to improve travel times and reduce travel costs; and iv) to reduce air pollution and noise.

Project Detail

Country

Brazil

Project Number

BR-L1087

Approval Date

February 26, 2009

Project Status

Closed

Project Type

Loan Operation

Sector

URBAN DEVELOPMENT AND HOUSING

Subsector

NEIGHBORHOOD UPGRADING

Lending Instrument

Préstamo de Inversión

Lending Instrument Code

INV

Modality

GCR (Global Credit Operation)

Facility Type

-

Environmental and Social Impact Category (ESIC)

Category B: Likely to cause mostly local and short-term negative environmental and associated social impacts and for which effective mitigation measures are readily available

Total Cost

USD 26,000,000.00

Country Counterpart Financing

USD 13,000,000.00

Original Amount Approved

USD 13,000,000.00

Can’t find a document? Request information

Implementation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-8775
Loan Contract
Carta Aditivo - Empréstimos ao Município de Maringá com taxa de juros baseada na LIBOR.pdf
Jan. 28, 2022
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1430814139-7
Project Monitoring Report ( Public version)
BR-L1087 First period Jan-Jun 2016-Public Report [40800189].PDF
Dec. 28, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1430814139-6
Project Monitoring Report ( Public version)
BR-L1087 Second period Jan-Dec 2015-Public Report [40364578].PDF
Jun. 27, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1430814139-5
Project Monitoring Report ( Public version)
BR-L1087 First period Jan-Jun 2015-Public Report [40192368].PDF
Mar. 21, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1430814139-2
Project Monitoring Report ( Public version)
BR-L1087 Segundo período enero-diciembre 2013-Public Report [40184045].PDF
Mar. 16, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1430814139-3
Project Monitoring Report ( Public version)
BR-L1087 Primer período enero-junio 2014-Public Report [40184632].PDF
Mar. 16, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1430814139-4
Project Monitoring Report ( Public version)
BR-L1087 Segundo período enero-diciembre 2014-Public Report [40185151].PDF
Mar. 18, 2016
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-767
Loan Contract
Amendment No 1- Programa de Mobilidade Urbana do Município de Maringá [39674377].PDF
Jun. 11, 2015
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-39
Procurement Plan
Plano de Aquisições - Atualização nº 3 (BR-L1087 - Fev2015) [39428035].XLS
Nov. 06, 2015
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-38
Procurement Plan
Plano de Aquisições - atualização nº 2 (BR-L1087 - Procidades Maringá) - Fev_2014 [38632401].xls
Feb. 25, 2014
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-33
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BR-L1087-2013-1º-Período [38265229].PDF
Mar. 06, 2014
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-34
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BR-L1087-2013-1º-Período [38265888].PDF
Mar. 06, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-35
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BR-L1087-2013-1º-Periodo [38266543].PDF
Mar. 06, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-36
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BR-L1087-2013-1º-Period [38267216].PDF
Mar. 06, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-30
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BR-L1087-2012-2º-Período [37873684].PDF
Jul. 27, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-31
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BR-L1087-2012-2º-Periodo [37874335].PDF
Jul. 27, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-32
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BR-L1087-2012-2º-Period [37875098].PDF
Jul. 27, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-29
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BR-L1087-2012-2º-Período [37873015].PDF
Jul. 27, 2013
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-25
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BR-L1087-2012-1º-Período [37351915].PDF
Dec. 19, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-26
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BR-L1087-2012-1º-Período [37352562].PDF
Dec. 19, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-27
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BR-L1087-2012-1º-Periodo [37353234].PDF
Jan. 21, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-28
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BR-L1087-2012-1º-Period [37353892].PDF
Jan. 21, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-21
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BR-L1087-2011-2º-Período [36914684].PDF
Nov. 28, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-22
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BR-L1087-2011-2º-Período [36921542].PDF
Nov. 28, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-23
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BR-L1087-2011-2º-Periodo [36924106].PDF
Nov. 28, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-24
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BR-L1087-2011-2º-Period [36926752].PDF
Nov. 28, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-19
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BR-L1087-2011-1º-Periodo [36624959].PDF
Jan. 12, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-20
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BR-L1087-2011-1º-Period [36625522].PDF
Jan. 12, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-17
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BR-L1087-2011-1º-Período [36623711].PDF
Jan. 12, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-18
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BR-L1087-2011-1º-Período [36624374].PDF
Jan. 12, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-13
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BR-L1087-2010-2º-Período [36310065].PDF
Aug. 10, 2011
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-14
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BR-L1087-2010-2º-Período [36311954].PDF
Aug. 10, 2011
French
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-15
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BR-L1087-2010-2º-Periodo [36312538].PDF
Aug. 10, 2011
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-16
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BR-L1087-2010-2º-Period [36313113].PDF
Aug. 10, 2011
English
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-12
Procurement Plan
Plano de Aquisições - 2121_OC-BR [35417525].XLS
Dec. 31, 1999
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-173
Loan Contract
Programa de Mobilidade Urbana do Município de Maringá - PROCIDADES [40315689].PDF
Dec. 31, 1899
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-3130
Loan Contract
Contrato Parte X - Programa de Mobilidade Urbana do Município de Maringá - PROCIDADES [1471649].PDF
Dec. 31, 1899
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-14413
Loan Proposal
PROCIDADES - Programa de Movilidad Urbana del Municipio de Maringá [1928916].PDF
Dec. 31, 1899
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-14412
Loan Proposal
PROCIDADES - Urban Mobility Program for the Municipio of Maringá [1928893].PDF
Dec. 31, 1899
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-31261
Project Monitoring Report ( Public version)
BR-L1087 First period Jan-Jun 2018-Public Report.pdf
Dec. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-32069
Project Monitoring Report ( Public version)
BR-L1087 Second period Jan-Dec 2018-Public Report.pdf
Oct. 15, 2019
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-749
Project Monitoring Report ( Public version)
BR-L1087 First period Jan-Jun 2017-Public Report.pdf
Feb. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-1752567784-4
Procurement Plan
Plano de Aquisições - atualização nº 4.xls
Apr. 28, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-95
Project Monitoring Report ( Public version)
BR-L1087 Second period Jan-Dec 2016-Public Report.pdf
Feb. 14, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-5167
Loan Contract
Alteração Contratual No. 2 - Programa de Mobilidade Urbana do Município de Maringá - PROCIDADES.pdf
May. 14, 2018
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-5397
Loan Contract
Alteração Contratual No. 3 - Programa de Mobilidade Urbana do Municipio de Maringá.pdf
Aug. 07, 2018
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-1636
Project Monitoring Report ( Public version)
BR-L1087 Second period Jan-Dec 2017-Public Report.pdf
Aug. 01, 2018
English
Closed Phase
https://www.iadb.org/document.cfm?id=EZSHARE-1744854848-33
Project Completion Report
BR-L1087 - Relatório de Conclusão do Projeto (PCR) - Procidades Maringá.pdf
Apr. 20, 2020
Portuguese
Other Documents
https://www.iadb.org/document.cfm?id=EZSHARE-1430814139-18
Electronic Links
1. Matriz de Efetividade de Desenvolvimento – DEM.PDF
Jul. 08, 2020
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1430814139-16
Electronic Links
3. Alterações à Matriz de Resultados.docx
Jul. 08, 2020
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1430814139-17
Electronic Links
4. PCR Checklist.pdf
Jul. 08, 2020
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1430814139-14
Electronic Links
Anexo I – Quadro de Alterações Contratuais.docx
Jul. 08, 2020
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1430814139-15
Electronic Links
2. Versão final do Relatório de Monitoramento de Progresso (PMR).xlsx
Jul. 08, 2020
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1744854848-29
Electronic Links
EEO_4 Instrumento de Alteração Contratual 3_-_Programa_de_Mobilidade_Urbana_do_Municipio_de_Maringá_pdf.pdf
Mar. 18, 2020
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1744854848-23
Electronic Links
PCR Link 1 Matriz de Efetividade de Desenvolvimento - DEM.PDF
Mar. 18, 2020
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1744854848-30
Electronic Links
EEO_1 Contrato de Empréstimo Programa_de_Mobilidade_Urbana_do_Município_de_Maringá.PDF
Mar. 18, 2020
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1744854848-24
Electronic Links
PCR Link 2 Relatório de Monitoramento de Progresso (PMR) BR-L1087.xlsx
Mar. 18, 2020
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1744854848-25
Electronic Links
PCR Link 3 Alterações na Matriz de Resultados do Programa_Maringá.docx
Mar. 18, 2020
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1744854848-26
Electronic Links
PCR Link 4 Checklist Investment Maringá BR-L1087 final.xlsx
Mar. 18, 2020
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1744854848-27
Electronic Links
EEO_3 Instrumento de Alteração Contratual 2 - Programa_de_Mobilidade_Urbana_do_Município_de_Maringá_-_PROCIDADES_pdf.pdf
Mar. 18, 2020
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1744854848-28
Electronic Links
EEO_2 Instrumento de Alteração Contratual 1 - Programa_de_Mobilidade_Urbana_do_Município_de_Maringá__39674377__PDF.PDF
Mar. 18, 2020
Portuguese
Preparation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-11
Project Outline
Esquema de Proyecto - Maringa_PR-PROGRAMA DE TRANSPORTE Y MOVILIDAD URBANA [895454].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1184880479-37
Project Outline
Esquema de Proyecto - Maringa_PR-PROGRAMA DE TRANSPORTE Y MOVILIDAD URBANA [9097868].PDF
Dec. 31, 1999
Spanish

Have an Environmental or Social issue related to IDB projects? File a Complaint

Jump back to top