Guarantee for the promotion of investments in strategic electricity transmission

The general objective is to contribute to improving electricity service supply through increased electricity transmission capacity; the specific objectives are: (i) to improve the reliability and capacity of the electricity transmission system in Greater Buenos Aires (GBA); and (ii) to enable new interconnection capacity for electricity generation

Project Detail

Country

Argentina

Project Number

AR-U0007

Approval Date

-

Project Status

Preparation

Project Type

Guarantee

Sector

ENERGY

Subsector

NEW POWER DISTRIBUTION & TRANSMISSION PROJECTS

Lending Instrument

Investment Loan

Lending Instrument Code

INV

Modality

PRG (Political Risk Guarantee)

Facility Type

-

Environmental and Social Impact Category (ESIC)

Category A: Likely to cause significant negative impacts, or have profound implications affecting natural resources

Total Cost

USD 0.00

Country Counterpart Financing

-

Original Amount Approved

USD 0.00

Can’t find a document? Request information

Preparation Phase
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-43
Environmental and Social Execution
AR-U0007 PPPI FFD.pdf
Jul. 17, 2026
English
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-42
Environmental and Social Execution
AR-U0007 - EIASc Corredor Sur Anexo 7 - FFD.pdf
Jul. 17, 2026
English
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-41
Environmental and Social Execution
AR-U0007 - EIASc Corredor Sur - FFD.pdf
Jul. 17, 2026
English
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-40
Environmental and Social Execution
AR-U0007 - EIASc Corredor AMBA Anexo 4 - FFD.pdf
Jul. 17, 2026
English
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-39
Environmental and Social Execution
AR-U0007 - EIASc Corredor AMBA - FFD.pdf
Jul. 17, 2026
English
https://www.iadb.org/document.cfm?id=EZIDB001208-784647248-40
Project Profile
AR-U0007 - Paquete PP.pdf
Apr. 28, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-35
Environmental and Social Execution
AR-U0007 - EA MPAS Corredor Sur - Version Preliminar.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-34
Environmental and Social Execution
AR-U0007 - EA MPAS Corredor Oeste - Version Preliminar.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-33
Environmental and Social Execution
AR-U0007 - EA MPAS AMBA I - Version Preliminar.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-29
Environmental and Social Execution
Corredor Sur Linea 500 kv Madryn - Choele - EIA.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-28
Environmental and Social Execution
Corredor Sur EIA Bahia Blanca.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-27
Environmental and Social Execution
Corredor Oeste EIA Informe Charlone - Villegas.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-26
Environmental and Social Execution
Corredor Oeste - LEAT 500 KV CHARLONE - PLOMER.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-25
Environmental and Social Execution
Corredor Oeste - EIA LT 132 KV Charlone - Rufino.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-24
Environmental and Social Execution
Corredor Oeste - EIA Informe Charlone - Gral Pico Sur.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-22
Environmental and Social Execution
Corredor Oeste - EIA FINAL DIAMANTE-CENTRO REHUNA SA.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-23
Environmental and Social Execution
Corredor Oeste - EIA infome Charlone - Realico.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-20
Environmental and Social Execution
Corredor Oeste - EIA ET 500 kV Charlone.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-21
Environmental and Social Execution
Corredor Oeste - EIA ET 500 kV Plomer.docx.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-19
Environmental and Social Execution
Corredor Oeste - EIA Informe Charlone - Laboulaye.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-18
Environmental and Social Execution
AMBA I EIA LAT Plomer - Pantanosa.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-17
Environmental and Social Execution
AMBA I EIA - Plomer - Zappalorto.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-16
Environmental and Social Execution
AMBA I EIA - Plomer - Lujan - Mercedes.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-15
Environmental and Social Execution
AMBA I EIA - Plomer - Ezeiza.pdf
Apr. 06, 2026
Spanish
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-14
Environmental and Social Execution
AMBA I EIA - Plomer - Atucha II.pdf
Apr. 06, 2026
English
https://www.iadb.org/document.cfm?id=EZIDB001208-315596425-13
Environmental and Social Execution
AMBA I EIA - E.T. Plomer.pdf
Apr. 06, 2026
Spanish

Have an Environmental or Social issue related to IDB projects? File a Complaint

Jump back to top