Project Detail
Country
Argentina
Project Number
AR-L1295
Approval Date
November 2, 2018
Project Status
Implementation
Project Type
Loan Operation
Sector
TRANSPORT
Subsector
TRANSPORT
Lending Instrument
Investment Loan
Lending Instrument Code
INV
Modality
GOM (Global of Multiple Works Operation)
Facility Type
-
Environmental and Social Impact Category (ESIC)
Category B: Likely to cause mostly local and short-term negative environmental and associated social impacts and for which effective mitigation measures are readily available
Total Cost
USD 531,900,000.00
Country Counterpart Financing
USD 207,600,000.00
Original Amount Approved
USD 324,300,000.00
| Operation Number | Lending Type | Reporting Currency | Reporting Date | Signed Date | Fund | Financial Instrument | 
|---|---|---|---|---|---|---|
| 4652/OC-AR | Sovereign Guaranteed | USD - United States Dollar | Ordinary Capital | Flexible Financing Facility | 
- Lending Type: Sovereign Guaranteed
- Reporting Currency: USD - United States Dollar
- Reporting Date:
- Signed Date:
- Fund: Ordinary Capital
- Financial Instrument: Flexible Financing Facility
Can’t find a document? Request information
https://www.iadb.org/document.cfm?id=EZIDB0000578-522669563-47098
        Project Monitoring Report ( Public version)
    AR-L1295 Second period Jan-Dec 2024 - Public Report.PDF
      Aug. 01, 2025
      en
https://www.iadb.org/document.cfm?id=EZIDB0000578-522669563-45348
        Project Monitoring Report ( Public version)
    AR-L1295 First period Jan-Jun 2024 - Public Report.PDF
      Feb. 04, 2025
      English
https://www.iadb.org/document.cfm?id=EZIDB0000578-522669563-44687
        Project Monitoring Report ( Public version)
    AR-L1295 Second period Jan-Dec 2023 - Public Report.PDF
      Jun. 28, 2024
      English
https://www.iadb.org/document.cfm?id=EZIDB0000029-421405757-53
        Annual Project Audited Financial Statement
    Estados financieros auditados - ejercicio 2023.pdf
      Jun. 11, 2024
      Spanish
https://www.iadb.org/document.cfm?id=EZIDB0000578-522669563-44019
        Project Monitoring Report ( Public version)
    AR-L1295 First period Jan-Jun 2023 - Public Report.PDF
      Jan. 25, 2024
      English
https://www.iadb.org/document.cfm?id=EZIDB0000578-522669563-43369
        Project Monitoring Report ( Public version)
    AR-L1295 Second period Jan-Dec 2022 - Public Report.PDF
      Jul. 19, 2023
      English
https://www.iadb.org/document.cfm?id=EZIDB0000029-421405757-40
        Annual Project Audited Financial Statement
    Estados Financieros Auditados - Ejercicio 2022.pdf
      May. 31, 2023
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1375635338-34783
        Specific Procurement Notices
    AR-L1295_P1131234_SP.pdf
      Feb. 02, 2023
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-42115
        Project Monitoring Report ( Public version)
    AR-L1295 First period Jan-Jun 2022 - Public Report.PDF
      Feb. 08, 2023
      English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-40866
        Project Monitoring Report ( Public version)
    AR-L1295 Second period Jan-Dec 2021 - Public Report.PDF
      Aug. 11, 2022
      English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-35230
        Project Monitoring Report ( Public version)
    AR-L1295 First period Jan-Jun 2021 - Public Report.pdf
      Feb. 16, 2022
      English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-34628
        Project Monitoring Report ( Public version)
    AR-L1295 Second period Jan-Dec 2020 - Public Report.pdf
      Jul. 20, 2021
      English
https://www.iadb.org/document.cfm?id=EZSHARE-1375635338-30729
        Notice of Contract Award (SG)
    AR-L1295_C699361_AW.pdf
      Mar. 23, 2021
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-33962
        Project Monitoring Report ( Public version)
    AR-L1295 First period Jan-Jun 2020 - Public Report.pdf
      Mar. 08, 2021
      English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-33314
        Project Monitoring Report ( Public version)
    AR-L1295 Second period Jan-Dec 2019-Public Report.pdf
      Aug. 24, 2020
      English
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-22
        Loan Proposal
    EEO_2_El_Sector_Vial_Argentino_y_Necesidades_de_FI_V01.pdf
      Oct. 19, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1470197173-48209
        Loan Contract
    Segunda Etapa de Ampliación de Capacidad y Mejoras de Seguridad en los Accesos al Paso Cristo Redentor.pdf
      Nov. 27, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-3
        Loan Proposal
    EER_2_PEP y POA.xlsx
      Oct. 19, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1470197173-48210
        Loan Contract
    Phase Two of the Program to Build Capacity and Improve Safety on the Accesses to the Cristo Redentor Border Crossing.pdf
      Nov. 27, 2018
      English
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-6514
        Loan Contract
    Contrato - Segunda Etapa de Ampliación de Capacidad y Mejoras de Seguridad en los Accesos al Paso Cristo Redentor - Segunda Operación CCLIP.pdf
      Aug. 19, 2019
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-41
        Loan Proposal
    Argentina. Propuesta de préstamo individual para la Segunda Etapa de Ampliación de Capacidad y Mejoras de Seguridad en los Accesos al Paso Cristo Redentor”.pdf
      Oct. 19, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-10
        Loan Proposal
    EER_3_Plan de Monitoreo y Evaluación.docx
      Oct. 19, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-42
        Loan Proposal
    Argentina. Proposal for an individual loan for the Phase Two of the Program to Build Capacity and Improve Safety on the Accesses to the Cristo Redentor Border Crossing”.pdf
      Oct. 19, 2018
      English
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-11
        Loan Proposal
    EEO_3_Estudios Tecnicos de las Obras.pdf
      Oct. 19, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-5
        Loan Proposal
    EEO_6_Anexo de Integración_AR-L1295_Final_Limpio.docx
      Oct. 19, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-14
        Loan Proposal
    EEO_11_Anexo de Seguridad Vial.pdf
      Oct. 22, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-7
        Loan Proposal
    EEO_9_Tomo_I_Estudio_de_optimizacion_del_paso_de_frontera[1].pdf
      Oct. 22, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-19
        Loan Proposal
    EEO_1_Evaluacion Economica_AR-L1295.pdf
      Oct. 19, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-8
        Loan Proposal
    EEO_8_Estudio Binacional de Conectividad Argentina-Chile.pdf
      Oct. 22, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-2
        Loan Proposal
    EER_5_Plan de adquisiciones.xlsx
      Oct. 19, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-31997
        Project Monitoring Report ( Public version)
    AR-L1295 Second period Jan-Dec 2018-Public Report.pdf
      Oct. 15, 2019
      English
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-20
        Loan Proposal
    EEO_15_Sistema de Control de Gestion.docx
      Oct. 22, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-32680
        Project Monitoring Report ( Public version)
    AR-L1295 First period Jan-Jun 2019-Public Report.pdf
      Feb. 12, 2020
      English
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-21
        Loan Proposal
    EER_4_IGAS_AR-L1295.docx
      Oct. 19, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-781727023-7
        Public Consultation Report
    Plan de Consulta Publica.pdf
      May. 24, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-781727023-12
        Environmental Impact Assessments
    EIA.pdf
      Aug. 23, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-781727023-13
        Public Consultation Report
    Socializacion Chile final.pdf
      Aug. 23, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-781727023-14
        Environmental and Social Analyses
    EIA complementario.pdf
      Aug. 23, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-781727023-15
        Strategic Environmental Assessments
    EASE.pdf
      Aug. 23, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-781727023-5
        Environmental Impact Assessments
    ESTUDIO DE  IMPACTO AMBIENTAL.pdf
      May. 24, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-781727023-6
        Environmental and Social Analyses
    Analisis_Impactos_Complementarios_Túnel_Caracoles.pdf
      May. 24, 2018
      Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-30346992-4
        Results Matrix
    EER_1_Matriz DEM.xlsx
      May. 08, 2019
      English
Have an Environmental or Social issue related to IDB projects? File a Complaint