AR-L1121 : Reconquista River Basin Environmental Sanitation Program
Project Status: Implementation
The objective of the program is to restore the environmental quality of the Reconquista River Basin (CRR) by implementing a comprehensive management plan that prioritizes leveraging actions in that regard. To motivate the population and include it in the program, priority will be given to investments aimed at those living in health risk areas. These investments will help to: (i) increase water, sewerage, and wastewater treatment coverage; (ii) enhance integrated solid waste management, primarily by closing open air dumps; (iii) improve connectivity and access to outlying neighborhoods located in hard-to-reach areas; and (iv) strengthen the operational management capacity of the Reconquista River Basin Committee (COMIREC) by developing management tools, which primarily include the Reconquista River Basin Comprehensive Management Plan (PGICRR).
Project Detail
Approval date
July 23, 2014
Project Country
Argentina
Project Sector
WATER AND SANITATION
Project Subsector
SANITATION RURAL AND PERI-URBAN
Project Type
Loan Operation
Project Modality
GOM (Global of Multiple Works Operation)
Environmental and social impact category
A
Project Status
Implementation
Operation Number
3256/OC-AR
Financial Information
Project Status
Implementation
IDB Financing
Reporting currency
USD - United States Dollar
Reporting date
May/26/2023
Roles & Responsibilities
Contract signature date
Dec/10/2014
Preparation
Title
Type
Project Number
Date Published
Environmental and Social Management Plan
AR-L1121
August 05, 2022
Environmental Impact Assessments
AR-L1121
March 19, 2018
Environmental Impact Assessments
AR-L1121
May 07, 2013
Project Profile
AR-L1121
August 12, 2011
Resettlement Plans
AR-L1121
May 27, 2011
Approved
Title
Type
Project Number
Date Published
Loan Contract
3256/OC-AR;AR-L1121
December 03, 2015
Loan Contract
3256/OC-AR;AR-L1121
December 10, 2014
Loan Contract
3256/OC-AR;AR-L1121
December 10, 2014
Loan Contract
3256/OC-AR;AR-L1121
July 23, 2014
Loan Contract
3256/OC-AR;AR-L1121
July 23, 2014
Loan Proposal
AR-L1121
July 02, 2014
Loan Proposal
AR-L1121
July 02, 2014
Loan Proposal
AR-L1121
May 15, 2014
Loan Proposal
AR-L1121
May 14, 2014
Loan Proposal
AR-L1121
May 14, 2014
Loan Proposal
AR-L1121
May 14, 2014
Loan Proposal
AR-L1121
May 14, 2014
Loan Proposal
AR-L1121
May 14, 2014
Loan Proposal
AR-L1121
May 14, 2014
Loan Proposal
AR-L1121
May 14, 2014
Loan Proposal
AR-L1121
May 14, 2014
Loan Proposal
AR-L1121
May 14, 2014
Loan Proposal
AR-L1121
May 14, 2014
Loan Proposal
AR-L1121
May 14, 2014
Loan Proposal
AR-L1121
December 30, 2013
Loan Proposal
AR-L1121
October 07, 2013
Loan Proposal
AR-L1121
October 07, 2013
Loan Proposal
AR-L1121
October 07, 2013
Loan Proposal
AR-L1121
October 04, 2013
Implementation
Title
Type
Project Number
Date Published
Environmental and Social Execution
AR-L1121
May 24, 2023
Notice of Contract Award (SG)
AR-L1121
February 13, 2023
Notice of Contract Award (SG)
AR-L1121
February 10, 2023
Project Monitoring Report ( Public version)
AR-L1121
February 08, 2023
Annual Project Audited Financial Statement
AR-L1121
August 23, 2022
Project Monitoring Report ( Public version)
AR-L1121
August 11, 2022
Environmental and Social Execution
AR-L1121
June 23, 2022
Environmental and Social Execution
AR-L1121
June 23, 2022
Environmental and Social Execution
AR-L1121
June 09, 2022
Specific Procurement Notices
AR-L1121
May 02, 2022
Notice of Contract Award (SG)
AR-L1121
April 21, 2022
Specific Procurement Notices
AR-L1121
April 19, 2022
Project Monitoring Report ( Public version)
AR-L1121
February 16, 2022
Notice of Contract Award (SG)
AR-L1121
August 03, 2021
Annual Project Audited Financial Statement
AR-L1121
July 30, 2021
Project Monitoring Report ( Public version)
AR-L1121
July 20, 2021
Environmental and Social Execution
AR-L1121
June 10, 2021
Environmental and Social Execution
AR-L1121
June 10, 2021
Environmental and Social Execution
AR-L1121
June 10, 2021
Project Monitoring Report ( Public version)
AR-L1121
March 08, 2021
Environmental and Social Execution
AR-L1121
December 11, 2020
Environmental and Social Execution
AR-L1121
December 11, 2020
Environmental and Social Execution
AR-L1121
December 11, 2020
Annual Project Audited Financial Statement
AR-L1121
November 13, 2020
Project Monitoring Report ( Public version)
AR-L1121
August 24, 2020
Project Monitoring Report ( Public version)
AR-L1121
February 12, 2020
Project Monitoring Report ( Public version)
AR-L1121
October 15, 2019
Annual Project Audited Financial Statement
AR-L1121
September 05, 2019
Environmental and Social Execution
AR-L1121
July 10, 2019
Environmental and Social Execution
AR-L1121
July 09, 2019
Environmental and Social Execution
AR-L1121
July 09, 2019
Environmental and Social Execution
AR-L1121
July 09, 2019
Environmental and Social Execution
AR-L1121
July 09, 2019
Environmental and Social Execution
AR-L1121
July 09, 2019
Environmental and Social Execution
AR-L1121
July 09, 2019
Environmental and Social Execution
AR-L1121
July 09, 2019
Environmental and Social Execution
AR-L1121
June 20, 2019
Environmental and Social Execution
AR-L1121
June 20, 2019
Environmental and Social Execution
AR-L1121
June 20, 2019
Project Monitoring Report ( Public version)
AR-L1121
December 14, 2018
Project Monitoring Report ( Public version)
AR-L1121
August 01, 2018
Annual Project Audited Financial Statement
AR-L1121
June 30, 2018
Project Monitoring Report ( Public version)
AR-L1121
February 16, 2018
Project Monitoring Report ( Public version)
AR-L1121
February 14, 2018
Project Monitoring Report ( Public version)
AR-L1121
December 23, 2016
Project Monitoring Report ( Public version)
AR-L1121
June 23, 2016
Project Monitoring Report ( Public version)
AR-L1121
March 15, 2016
Project Monitoring Report ( Public version)
AR-L1121
March 14, 2016