AR-L1095 : Additional Financing Norte Grande Electricity Transmission Program
Project Status: Closed
The main objective of the Project is to guarantee the coverage of the increasing power demand and the security of the Argentinean Interconnection System (SADI), with the object of contributing to the continuous development of the productive sectors and elevating the standard of life of the population, by rationally making use of the available generation resources of the country. The specific objectives are: i) to interconnect the electrical systems of the Northeast and Northwest Argentinean regions (NOA ¿ NEA) by using a line of extra high tension (LEAT 500kV and associated Transformation Stations) so it can permit and promote the energy exchange between both regions, improving the prices and increasing the quality and security of the electrical provision, in particular for the macro region of Norte Grande; and ii) to consolidate and expand the regional communication nets (high and med tension lines smaller than 500kV with its respective associated transformation stations), laying the foundations for the productive and social development through giving solution to the problems that attempt against the security and reliability of these systems.
Project Detail
Project Country
Argentina
Project Subsector
NEW POWER DISTRIBUTION & TRANSMISSION PROJECTS
Project Type
Loan Operation
Project Modality
GOM (Global of Multiple Works Operation)
Environmental and social impact category
A
Operation Number
1764/OC-AR-1
Financial Information
IDB Financing
Reporting currency
USD - United States Dollar
Reporting date
Jul/18/2023
Roles & Responsibilities
Contract signature date
Mar/19/2010
Approved
Title
Type
Project Number
Date Published
Loan Contract
AR-L1095; AR-L1017; AR-L1015; AR-L1016; AR-L1026; AR-L1025; AR-L1033; AR-L1031; AR-L1020; AR-L1032; AR-L1013; AR-L1080; AR-L1045; AR-L1092
June 21, 2022
Loan Contract
AR-L1095
July 06, 2020
Loan Contract
AR-L1095
July 06, 2020
Loan Proposal
AR-L1095
January 08, 2010
Loan Proposal
AR-L1095
January 08, 2010
Implementation
Title
Type
Project Number
Date Published
Project Monitoring Report ( Public version)
AR-L1095
February 15, 2018
Project Monitoring Report ( Public version)
AR-L1095
February 14, 2018
Project Monitoring Report ( Public version)
AR-L1095
December 28, 2016
Project Monitoring Report ( Public version)
AR-L1095
March 15, 2016
Project Monitoring Report ( Public version)
AR-L1095
August 20, 2015
Project Monitoring Report ( Public version)
AR-L1095
August 20, 2015
Project Monitoring Report ( Public version)
AR-L1095
August 20, 2015
Project Monitoring Report ( Public version)
AR-L1095
August 20, 2015
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
October 31, 2013
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
October 31, 2013
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
October 31, 2013
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
October 31, 2013
Procurement Plan
AR-L1021,AR-L1095
August 29, 2013
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
May 07, 2013
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
May 07, 2013
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
May 07, 2013
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
May 07, 2013
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
December 11, 2012
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
December 11, 2012
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
December 11, 2012
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
December 11, 2012
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
May 14, 2012
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
May 14, 2012
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
May 14, 2012
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
May 14, 2012
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
November 18, 2011
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
November 18, 2011
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
November 18, 2011
Project Monitoring Report ( Public version)
1764/OC-AR-1;AR-L1095
November 18, 2011
Procurement Plan
AR-L1021,AR-L1095
December 31, 1999
Procurement Plan
AR-L1021,AR-L1095
January 01, 1900
Completed
Title
Type
Project Number
Date Published
Project Completion Report
AR-L1095
December 16, 2019