Skip to main content

Additional Financing Norte Grande Electricity Transmission Program

The main objective of the Project is to guarantee the coverage of the increasing power demand and the security of the Argentinean Interconnection System (SADI), with the object of contributing to the continuous development of the productive sectors and elevating the standard of life of the population, by rationally making use of the available generation resources of the country. The specific objectives are: i) to interconnect the electrical systems of the Northeast and Northwest Argentinean regions (NOA ¿ NEA) by using a line of extra high tension (LEAT 500kV and associated Transformation Stations) so it can permit and promote the energy exchange between both regions, improving the prices and increasing the quality and security of the electrical provision, in particular for the macro region of Norte Grande; and ii) to consolidate and expand the regional communication nets (high and med tension lines smaller than 500kV with its respective associated transformation stations), laying the foundations for the productive and social development through giving solution to the problems that attempt against the security and reliability of these systems.

Project Detail

Country

Argentina

Project Number

AR-L1095

Approval Date

November 30, 2009

Project Status

Closed

Project Type

Loan Operation

Sector

ENERGY

Subsector

NEW POWER DISTRIBUTION & TRANSMISSION PROJECTS

Lending Instrument

Préstamo de Inversión

Lending Instrument Code

INV

Modality

GOM (Global of Multiple Works Operation)

Facility Type

-

Environmental and Social Impact Category (ESIC)

Category A: Likely to cause significant negative impacts, or have profound implications affecting natural resources

Total Cost

USD 512,500,000.00

Country Counterpart Financing

USD 212,500,000.00

Original Amount Approved

USD 300,000,000.00

Can’t find a document? Request information

Implementation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-8932
Loan Contract
Modificatorio - Préstamos a Argentina con tasa de interés basada en LIBOR.pdf
Jun. 21, 2022
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-965128629-48825
Loan Contract
Additional Financing for the Norte Grande Electricity Transmission Program [2250566].pdf
Jul. 06, 2020
English
https://www.iadb.org/document.cfm?id=EZSHARE-965128629-48826
Loan Contract
Financiamiento Adicional para el Programa de Transmisión Eléctrica del Norte Grande [1712489].pdf
Jul. 06, 2020
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-8929
Project Monitoring Report ( Public version)
AR-L1095 First period Jan-Jun 2016-Public Report [40801085].PDF
Jan. 10, 2017
English
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-39
Project Monitoring Report ( Public version)
AR-L1095 Second period Jan-Dec 2015-Public Report [40363968].PDF
Aug. 08, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-35
Project Monitoring Report ( Public version)
AR-L1095 First Period Jan-Jun 2014 Public Report [40237799].PDF
Dec. 31, 1999
English
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-36
Project Monitoring Report ( Public version)
AR-L1095 Second Period Jan-Dec 2013 Public Report [40238468].PDF
Apr. 21, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-37
Project Monitoring Report ( Public version)
AR-L1095 Second Period Jan-Dec 2014-Public Report [40238478].PDF
Apr. 21, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-38
Project Monitoring Report ( Public version)
AR-L1095 First Period Jan-Jun 2015-Public Report [40238485].PDF
Apr. 21, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-34
Specific Procurement Notices
AR-L1095 [38874799].PDF
Jun. 20, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-33
Specific Procurement Notices
AR-L1095 [38805395].PDF
May. 19, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-29
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_AR-L1095-2013-1º-Período [38265121].PDF
Mar. 06, 2014
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-30
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_AR-L1095-2013-1º-Período [38265781].PDF
Mar. 06, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-31
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_AR-L1095-2013-1º-Periodo [38266441].PDF
Mar. 06, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-32
Project Monitoring Report ( Public version)
Report for Publication_PMR-_AR-L1095-2013-1º-Period [38267106].PDF
Mar. 06, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-404053128-44
Procurement Plan
Plan de Adquisiciones [37965024].PDF
Aug. 29, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-25
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_AR-L1095-2012-2º-Período [37872907].PDF
Jul. 27, 2013
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-26
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_AR-L1095-2012-2º-Período [37873575].PDF
Jul. 27, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-27
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_AR-L1095-2012-2º-Periodo [37874228].PDF
Jul. 27, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-28
Project Monitoring Report ( Public version)
Report for Publication_PMR-_AR-L1095-2012-2º-Period [37874964].PDF
Jul. 27, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-23
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_AR-L1095-2012-1º-Periodo [37353129].PDF
Jan. 21, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-24
Project Monitoring Report ( Public version)
Report for Publication_PMR-_AR-L1095-2012-1º-Period [37353786].PDF
Jan. 21, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-21
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_AR-L1095-2012-1º-Período [37351811].PDF
Dec. 19, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-22
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_AR-L1095-2012-1º-Período [37352455].PDF
Dec. 19, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-17
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_AR-L1095-2011-2º-Período [37297706].PDF
Nov. 28, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-18
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_AR-L1095-2011-2º-Período [37297896].PDF
Nov. 28, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-19
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_AR-L1095-2011-2º-Periodo [37298089].PDF
Nov. 28, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-20
Project Monitoring Report ( Public version)
Report for Publication_PMR-_AR-L1095-2011-2º-Period [37298280].PDF
Nov. 28, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-13
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_AR-L1095-2011-1º-Período [36623621].PDF
Jan. 12, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-14
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_AR-L1095-2011-1º-Período [36624291].PDF
Jan. 12, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-15
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_AR-L1095-2011-1º-Periodo [36624872].PDF
Jan. 12, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-16
Project Monitoring Report ( Public version)
Report for Publication_PMR-_AR-L1095-2011-1º-Period [36625440].PDF
Jan. 12, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-404053128-20
Procurement Plan
PA 2010 Programa de Transmisión Electrica + Adicional al Programa de Transmisión Electrica [4255646].PDF
Jan. 01, 1900
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-404053128-21
Procurement Plan
PA 2010 Programa de Transmisión Electrica + Adicional al Programa de Transmisión Electrica [35255497].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-11
Loan Proposal
Argentina_ Propuesta de préstamo para el Financiamiento Adicional para el Programa de Transmisión Eléctrica del [35041725].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1119001262-12
Loan Proposal
Argentina_ Proposal for a loan for the Additional Financing for the Norte Grande Electricity Transmission Progr [35041726].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-1348
Project Monitoring Report ( Public version)
AR-L1095 First period Jan-Jun 2017-Public Report.pdf
Feb. 15, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-679
Project Monitoring Report ( Public version)
AR-L1095 Second period Jan-Dec 2016-Public Report.pdf
Feb. 14, 2018
English
Closed Phase
https://www.iadb.org/document.cfm?id=EZSHARE-102586410-10
Project Completion Report
Informe de Terminación de Proyecto para Publicación.pdf
Dec. 16, 2019
Spanish

Have an Environmental or Social issue related to IDB projects? File a Complaint