Can’t find a document? Request Information

AR-L1084 : Water and Sanitation Program for Urban and Suburban Centers (PAyS)

Project Status: Closed

To contribute to solve the potable water and sanitation problematic in the main centers and urban agglomerates of the country in order that the users who count on that service improve their quality of life and that the families who do not count on this one can get to have it in the short term.

Project Detail

Project Number
AR-L1084
Project Country
Argentina
Project Sector
WATER AND SANITATION
Project Subsector
WATER AND SANITATION
Project Type
Loan Operation
Project Lending Type
SG
Project Modality
GOM (Global of Multiple Works Operation)
Project Facility Type
Environmental and social impact category
B
Project Status
Closed
Operation Number
2343/OC-AR

Financial Information

Project Number
AR-L1084
Project Status
Closed

IDB Financing

Financing type
SCF
Fund
Ordinary Capital
Reporting currency
USD - United States Dollar
Reporting date
Sep/21/2023

Roles & Responsibilities

Contract signature date
Mar/26/2011

Project Information

Total Cost
USD 250,000,000
Country counterpart financing
USD 50,000,000
Amount
USD 200,000,000

Preparation

Title
Type
Project Number
Date Published
Environmental Analyses
AR-L1084;AR-L1162;AR-X1017
October 31, 2013
Environmental Analyses
AR-L1084;AR-L1162;AR-X1017
March 31, 2012
Environmental Impact Assessments
AR-L1084;AR-L1162;AR-X1017
January 01, 2012
Environmental Impact Assessments
AR-L1084;AR-L1162;AR-X1017
January 01, 2012
Environmental Impact Assessments
2343/OC-AR;AR-L1084
March 23, 2009
Project Profile
AR-L1084
March 03, 2009
Environmental Impact Assessments
AR-L1084
January 21, 2009

Approved

Title
Type
Project Number
Date Published
Loan Contract
AR-L1084; AR-L1064; AR-L1111; AR-L1101; AR-L1079; AR-L1078; AR-L1120; AR-L1071; AR-L1118; AR-L1122; AR-L1131; AR-L1119; AR-L1133; AR-L1014
June 21, 2022
Economic Analysis (during Execution)
AR-L1084
October 18, 2021
Loan Contract
AR-L1079; AR-L1158; AR-L1122; AR-L1162; AR-L1026; AR-L1151; AR-L1068; AR-L1067; AR-L1120; AR-L1159; AR-L1031; AR-L1084
August 24, 2021
Loan Contract
AR-L1101; AR-L1084; AR-L1064; AR-L1079; AR-L1078; AR-L1120; AR-L1071; AR-L1118; AR-L1122; AR-L1131; AR-L1119; AR-L1133; AR-L1068; AR-L1127; AR-L1136; AR-L1141; AR-L1142; AR-L1149; AR-L1067; AR-L1145; AR-L1148
May 20, 2021

Implementation

Title
Type
Project Number
Date Published
Project Monitoring Report ( Public version)
AR-L1084
July 20, 2021
Project Monitoring Report ( Public version)
AR-L1084
March 08, 2021
Project Monitoring Report ( Public version)
AR-L1084
August 24, 2020
Project Monitoring Report ( Public version)
AR-L1084
February 12, 2020
Project Monitoring Report ( Public version)
AR-L1084
October 15, 2019
Project Monitoring Report ( Public version)
AR-L1084
December 14, 2018
Project Monitoring Report ( Public version)
AR-L1084
August 01, 2018
Project Monitoring Report ( Public version)
AR-L1084
February 15, 2018
Project Monitoring Report ( Public version)
AR-L1084
February 14, 2018
Project Monitoring Report ( Public version)
AR-L1084
December 23, 2016
Specific Procurement Notices
AR-L1084
December 21, 2016
Specific Procurement Notices
AR-L1084
December 21, 2016
Project Monitoring Report ( Public version)
AR-L1084
June 23, 2016
Project Monitoring Report ( Public version)
AR-L1084
March 15, 2016
Project Monitoring Report ( Public version)
AR-L1084
March 14, 2016
Project Monitoring Report ( Public version)
AR-L1084
March 11, 2016
Project Monitoring Report ( Public version)
AR-L1084
March 10, 2016
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
October 31, 2013
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
October 31, 2013
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
October 31, 2013
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
October 31, 2013
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
May 07, 2013
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
May 07, 2013
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
May 07, 2013
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
May 07, 2013
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
May 14, 2012
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
May 14, 2012
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
May 14, 2012
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
May 14, 2012
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
November 18, 2011
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
November 18, 2011
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
November 18, 2011
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
November 18, 2011
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
June 22, 2011
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
June 22, 2011
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
June 22, 2011
Project Monitoring Report ( Public version)
2343/OC-AR;AR-L1084
June 22, 2011

Completed

Title
Type
Project Number
Date Published
Project Completion Report
AR-L1084
October 18, 2021