Acoyapa - CR border Road Integration Program

The general objective is to improve Nicaragua's competitiveness through reduced transport costs and increased production and trade. The specific objective is the integration of the project's influence zone to the Nicaraguan economy and consolidation if highway integration with Costa Rica and the other countries in the Mesoamerican region.

Project Detail

Country

Nicaragua

Project Number

NI-L1006

Approval Date

November 1, 2006

Project Status

Closed

Project Type

Loan Operation

Sector

TRANSPORT

Subsector

TRANSPORT

Lending Instrument

Préstamo de Inversión

Lending Instrument Code

INV

Modality

ESP (Specific Investment Operation)

Facility Type

-

Environmental Classification

(R) Likely to cause significant negative impacts, or have profound implications affecting natural resources

Total Cost

USD 60,700,000.00

Country Counterpart Financing

USD 11,200,000.00

Original Amount Approved

USD 49,500,000.00

Financial Information
Operation Number Lending Type Reporting Currency Reporting Date Signed Date Fund Financial Instrument
1796/SF-NI Sovereign Guaranteed USD - United States Dollar Ordinary Capital Concessional Financing
Operation Number 1796/SF-NI
  • Lending Type: Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: Ordinary Capital
  • Financial Instrument: Concessional Financing

Can’t find a document? Request information

Closed Phase
https://www.iadb.org/document.cfm?id=EZSHARE-819883592-1663
Project Completion Report
PIC_ NICARAGUA_ Programa de Integración Vial Acoyapa - San Carlos - Frontera con Costa Rica del Plan Puebla Pana [38933854].PDF
Feb. 06, 2015
Spanish
Implementation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-5937
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_NI-L1006-2012-2º-Período [37873346].PDF
Jul. 27, 2013
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-6240
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_NI-L1006-2012-2º-Período [37874013].PDF
Jul. 27, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-6543
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_NI-L1006-2012-2º-Periodo [37874675].PDF
Jul. 27, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-6874
Project Monitoring Report ( Public version)
Report for Publication_PMR-_NI-L1006-2012-2º-Period [37875504].PDF
Jul. 27, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-4617
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_NI-L1006-2012-1º-Período [37352236].PDF
Dec. 19, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-4951
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_NI-L1006-2012-1º-Período [37352897].PDF
Jan. 21, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-5285
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_NI-L1006-2012-1º-Periodo [37353556].PDF
Jan. 21, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-5619
Project Monitoring Report ( Public version)
Report for Publication_PMR-_NI-L1006-2012-1º-Period [37354220].PDF
Jan. 21, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-3811
Project Monitoring Report ( Public version)
Report for Publication_PMR-_NI-L1006-2011-2º-Period [36928322].PDF
Nov. 28, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-3172
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_NI-L1006-2011-2º-Período [36919016].PDF
Nov. 28, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-3385
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_NI-L1006-2011-2º-Período [36922992].PDF
Nov. 28, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-3598
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_NI-L1006-2011-2º-Periodo [36925587].PDF
Nov. 28, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-1843
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_NI-L1006-2011-1º-Período [36624099].PDF
Jan. 12, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-2197
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_NI-L1006-2011-1º-Período [36624678].PDF
Jan. 12, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-2658
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_NI-L1006-2011-1º-Periodo [36625235].PDF
Jan. 12, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-2941
Project Monitoring Report ( Public version)
Report for Publication_PMR-_NI-L1006-2011-1º-Period [36625797].PDF
Jan. 12, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-1072
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_NI-L1006-2010-2º-Periodo [36312825].PDF
Aug. 10, 2011
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-1471
Project Monitoring Report ( Public version)
Report for Publication_PMR-_NI-L1006-2010-2º-Period [36313401].PDF
Aug. 10, 2011
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-282
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_NI-L1006-2010-2º-Período [36310337].PDF
Aug. 10, 2011
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-677
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_NI-L1006-2010-2º-Período [36312241].PDF
Aug. 10, 2011
French
https://www.iadb.org/document.cfm?id=EZSHARE-819883592-332
Procurement Plan
Actualización del Plan de Adquisiciones_ [1964214].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-819883592-7671
Procurement Plan
Actualización del Plan de Adquisiciones_ [25070919].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-819883592-329
Procurement Plan
Plan de Adquisiciones PO 1796_SF-NI (Aprobado Marzo 2008) [1664973].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-819883592-478
Procurement Plan
Plan de Adquisiciones PO 1796_SF-NI (Aprobado Marzo 2008) [25063836].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-819883592-697
Procurement Plan
Plan de Adquisiciones PO 1796_SF-NI (Aprobado Marzo 2008) [35194586].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1515410380-6227
Loan Contract
Programa Vial de Integración Acoyapa - San Carlos - Frontera Costa Rica del Plan Puebla Panamá [802940].DOC
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1515410380-6229
Loan Contract
Programa Vial de Integración Acoyapa - San Carlos - Frontera Costa Rica del Plan Puebla Panamá [800890].DOC
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1515410380-6231
Loan Contract
Programa Vial de Integración Acoyapa - San Carlos - Frontera Costa Rica del Plan Puebla Panamá [799693].DOC
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-819883592-315
Loan Proposal
Programa Vial de Integración Acoyapa - San Carlos - Frontera Costa Rica del Plan Puebla Panamá [849846].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-819883592-316
Loan Proposal
Acoyapa - San Carlos - Costa Rica Borders Highway Integration Program Under the Puebla - Panama Plan [849848].PDF
Dec. 31, 1999
English
Preparation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-819883592-285
Environmental Impact Assessments
Carretera Acoyapa - San Carlos - Frontera con Costa Rica [757420].DOC
Jun. 22, 2006
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-819883592-274
Project Outline
PPP - Programa Vial de Integración Acoyapa - San Carlos - Frontera Costa Rica [717711].PDF
Dec. 31, 1999
Spanish
Other Documents
https://www.iadb.org/document.cfm?id=EZSHARE-819883592-290
Project Concept Document
PCD - Programa Vial de Integración Acoyapa - San Carlos - Frontera Costa Rica [775156].PDF
Dec. 31, 1999
Spanish