Misicuni Renewable Energy Hydroelectric Project
The objective of the Misicuni Multiple Project (MMP) is to supply drinking and irrigation water to the Cochabamba Valley, while generating electricity for the National Interconnected Syste,, using water from the Misicuni River watershed. The specific objective of the Misicuni Renewable Energy Hydroelectric Project (MHP), which is part of the MMP, is to add 80 MW of installed power generation capacity to the NIS and produce 217 GWh of electricity annually. The IDB will provide financing for the MHP, which will help: (i) expand the installed power generation capacity of the NIS to meet the growing need for electricity, especially during peak-demand hours; (ii) improve the energy matrix by increasing the share of renewable energy; and (iii) reduce subsidies to the sector and free up natural gas for export. The project has two components, one for the infrastructure works and the other to cover engineering, supervision, environmental and social mitigation, and other indirect costs.

Project Detail

Country

Bolivia

Project Number

BO-L1043

Approval Date

November 23, 2009

Project Status

Closed

Project Type

Loan Operation

Sector

ENERGY

Subsector

NEW HYDROPOWER PROJECTS

Lending Instrument

Préstamo de Inversión

Lending Instrument Code

INV

Modality

ESP (Specific Investment Operation)

Facility Type

-

Environmental Classification

Likely to cause significant negative impacts, or have profound implications affecting natural resources

Total Cost

USD 114,100,000.00

Country Counterpart Financing

USD 13,100,000.00

Original Amount Approved

USD 101,000,000.00

Financial Information
Operation Number Lending Type Reporting Currency Reporting Date Signed Date Fund Financial Instrument
2238/BL-BO Sovereign Guaranteed USD - United States Dollar Ordinary Capital Single Currency Facility and Concessional Financing
Operation Number 2238/BL-BO
  • Lending Type: Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: Ordinary Capital
  • Financial Instrument: Single Currency Facility and Concessional Financing

Can’t find a document? Request information

Implementation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-1290855614-7
Project Monitoring Report ( Public version)
BO-L1043 First period Jan-Jun 2016-Public Report [40801051].PDF
Dec. 28, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1290855614-6
Project Monitoring Report ( Public version)
BO-L1043 Second period Jan-Dec 2015-Public Report [40363014].PDF
Jun. 24, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1290855614-5
Project Monitoring Report ( Public version)
BO-L1043 First period Jan-Jun 2015-Public Report [40211515].PDF
Mar. 29, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1290855614-4
Project Monitoring Report ( Public version)
BO-L1043 Second period Jan-Dec 2014-Public Report [40209137].PDF
Mar. 28, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1290855614-3
Project Monitoring Report ( Public version)
BO-L1043 First period Jan-Jun 2014-Public Report [40193442].PDF
Mar. 21, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1290855614-2
Project Monitoring Report ( Public version)
BO-L1043 Second period Jan-Dec 2013-Public Report [40170773].PDF
Mar. 10, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-41
Specific Procurement Notices
BO-L1043 [39624997].PDF
May. 12, 2015
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-36
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BO-L1043-2013-1º-Período [38265185].PDF
Mar. 06, 2014
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-37
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BO-L1043-2013-1º-Período [38265847].PDF
Mar. 06, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-38
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BO-L1043-2013-1º-Periodo [38266505].PDF
Mar. 06, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-39
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BO-L1043-2013-1º-Period [38267174].PDF
Mar. 06, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-33
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BO-L1043-2012-2º-Período [37873639].PDF
Jul. 27, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-34
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BO-L1043-2012-2º-Periodo [37874292].PDF
Jul. 27, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-35
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BO-L1043-2012-2º-Period [37875045].PDF
Jul. 27, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-32
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BO-L1043-2012-2º-Período [37872973].PDF
Jul. 27, 2013
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-28
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BO-L1043-2012-1º-Período [37351873].PDF
Dec. 19, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-29
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BO-L1043-2012-1º-Período [37352519].PDF
Dec. 19, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-30
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BO-L1043-2012-1º-Periodo [37353191].PDF
Jan. 21, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-31
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BO-L1043-2012-1º-Period [37353848].PDF
Jan. 21, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-24
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BO-L1043-2011-2º-Período [37297736].PDF
Nov. 28, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-25
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BO-L1043-2011-2º-Período [37297927].PDF
Nov. 28, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-26
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BO-L1043-2011-2º-Periodo [37298119].PDF
Nov. 28, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-27
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BO-L1043-2011-2º-Period [37298310].PDF
Nov. 28, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-23
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BO-L1043-2010-2º-Period [36313068].PDF
Aug. 10, 2011
English
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-20
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BO-L1043-2010-2º-Período [36310021].PDF
Aug. 10, 2011
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-21
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BO-L1043-2010-2º-Período [36311909].PDF
Aug. 10, 2011
French
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-22
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BO-L1043-2010-2º-Periodo [36312493].PDF
Aug. 10, 2011
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-19
Approved TC document
BO-T1144 - Tunari National Park Management Plan [36201250].DOC
Mar. 14, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-18
Specific Procurement Notices
DISEÑO, SUMINISTRO Y CONSTRUCCIÓN DE LAS OBRAS DE LA CENTRAL HIDROELÉCTRICA MISICUNI [35668380].PDF
Dec. 31, 1999
English
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-16
Specific Procurement Notices
OBRAS DE LA CENTRAL HIDROELÉCTRICA MISICUNI Power [35532255].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-17
Specific Procurement Notices
SERVICIOS DE CONSULTORIA Power [35532280].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-15
General Procurement Notices
ANUNCIO GENERAL DE ADQUISICIONES H (power) [35401602].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-13
Procurement Plan
Plan Adquisiciones (17-08-10) [8136716].XLS
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-14
Procurement Plan
Plan Adquisiciones (17-08-10) [35316053].XLSX
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-133
Loan Contract
Proyecto Hidroeléctrico de Energía Renovable Misicuni [40056180].PDF
Dec. 31, 1899
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-46848
Loan Proposal
Propuesta de Préstamo Proyecto Hidroeléctrico de Energía Renovable Misicuni [35055136].PDF
Dec. 31, 1899
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-46849
Loan Proposal
Loan Proposal Misicuni Renewable Energy Hydroelectric Project BO-L1043 [35055137].PDF
Dec. 31, 1899
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-164
Project Monitoring Report ( Public version)
BO-L1043 Second period Jan-Dec 2016-Public Report.pdf
Feb. 15, 2018
English
https://www.iadb.org/document.cfm?id=EZSHARE-522669563-819
Project Monitoring Report ( Public version)
BO-L1043 First period Jan-Jun 2017-Public Report.pdf
Feb. 15, 2018
English
Other Documents
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-42
Procurement
BO-L1043 [39981862].PDF
Nov. 23, 2015
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-40
Procurement
BO-L1043 [38936955].PDF
Jul. 22, 2014
Spanish
Preparation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-419344705-3
Environmental and Social Management Reports
IGAS con Plan de Reasentamiento Proyecto Hidroeléctrico Misicuni [2225285].PDF
Oct. 22, 2009
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-46847
Project Profile
MISICUNI - Proyecto Hidroeléctrico de Energía Renovable Misicuni [2145274].PDF
Dec. 31, 1899
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-419344705-2
Environmental Impact Assessments
Proyecto Misicuni Fase I [2045723].PDF
Dec. 31, 1999
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-378647906-11
Environmental Impact Assessments
Central Hidroeléctrica Misicuni y Línea de Transmisión [2041081].PDF
Dec. 31, 1999
Spanish
Closed Phase
https://www.iadb.org/document.cfm?id=EZSHARE-1109403963-13
Project Completion Report
PCR BO-L1043.pdf
May. 14, 2019
Spanish