Skip to main content

Integrated Water and Sanitation Programme for the Placencia Peninsula

The loan will complement the CReW financing in Placencia for the construction of a wastewater treatment facility and associated networks. In addition, the loan will address the issues pertaining to reforms in the institutional and regulatory arrangements required for the management of the wastewater sector.

Project Detail

Country

Belize

Project Number

BL-L1015

Approval Date

December 10, 2010

Project Status

Closed

Project Type

Loan Operation

Sector

WATER AND SANITATION

Subsector

WATER AND SANITATION

Lending Instrument

Préstamo de Inversión

Lending Instrument Code

INV

Modality

ESP (Specific Investment Operation)

Facility Type

-

Environmental Classification

Likely to cause mostly local and short-term negative environmental and associated social impacts and for which effective mitigation measures are readily available

Total Cost

USD 10,000,000.00

Country Counterpart Financing

USD 5,000,000.00

Original Amount Approved

USD 5,000,000.00

Financial Information
Operation Number Lending Type Reporting Currency Reporting Date Signed Date Fund Financial Instrument
2486/OC-BL Sovereign Guaranteed USD - United States Dollar Ordinary Capital Single Currency Facility
Operation Number 2486/OC-BL
  • Lending Type: Sovereign Guaranteed
  • Reporting Currency: USD - United States Dollar
  • Reporting Date:
  • Signed Date:
  • Fund: Ordinary Capital
  • Financial Instrument: Single Currency Facility

Can’t find a document? Request information

Implementation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-8443
Loan Contract
Amendment Letter - Changes to the Interest Rate Calculation Basis and Other Provisions.pdf
Aug. 24, 2021
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-8433
Project Monitoring Report ( Public version)
BL-L1015 First period Jan-Jun 2015-Public Report [40181825].PDF
Mar. 15, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-8395
Project Monitoring Report ( Public version)
BL-L1015 Second period Jan-Dec 2014-Public Report [40178631].PDF
Mar. 14, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-8333
Project Monitoring Report ( Public version)
BL-L1015 First period Jan-Jun 2014-Public Report [40176121].PDF
Mar. 11, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-8205
Project Monitoring Report ( Public version)
BL-L1015 Second period Jan-Dec 2013-Public Report [40173141].PDF
Mar. 10, 2016
English
https://www.iadb.org/document.cfm?id=EZSHARE-1967013545-90
Procurement Plan
IWSPPP Loan_ Submission of Procurement Plan for the period January - December 2014 - Supporting Document [38252285].PDF
Jan. 17, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-7513
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BL-L1015-2013-1º-Periodo [38266490].PDF
Mar. 06, 2014
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-7792
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BL-L1015-2013-1º-Period [38267156].PDF
Mar. 06, 2014
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-6969
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BL-L1015-2013-1º-Período [38265169].PDF
Mar. 06, 2014
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-7234
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BL-L1015-2013-1º-Período [38265831].PDF
Mar. 06, 2014
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-5764
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BL-L1015-2012-2º-Período [37872957].PDF
Jul. 27, 2013
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-6370
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BL-L1015-2012-2º-Periodo [37874276].PDF
Jul. 27, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-6419
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BL-L1015-2012-2º-Período [37873623].PDF
Jul. 27, 2013
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-6681
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BL-L1015-2012-2º-Period [37875025].PDF
Jul. 27, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-5098
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BL-L1015-2012-1º-Periodo [37353173].PDF
Jan. 21, 2013
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-5432
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BL-L1015-2012-1º-Period [37353831].PDF
Jan. 21, 2013
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-4430
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BL-L1015-2012-1º-Período [37351857].PDF
Dec. 19, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-4764
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BL-L1015-2012-1º-Período [37352502].PDF
Dec. 19, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1967013545-62
Procurement Plan
Integrated Water _ Sanitation Program for the Placencia Peninsula, Procurement Plan 2012 (2) [36884210].PDF
May. 28, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-4820
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BL-L1015-2011-2º-Periodo [36923915].PDF
Nov. 28, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-3058
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BL-L1015-2011-2º-Período [36914290].PDF
Nov. 28, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-3271
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BL-L1015-2011-2º-Período [36921350].PDF
Nov. 28, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-3697
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BL-L1015-2011-2º-Period [36926555].PDF
Nov. 28, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-839592141-159
Procurement Plan
GENERAL PROCUREMENT NOTICE LOAN 2486 OC-BL February 16 2012 [36687311].PDF
Feb. 16, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-839592141-241
General Procurement Notices
Integrated Water and Sanitation Programme for the Placencia Peninsula - General Procurement Notice [37038642].PDF
Aug. 10, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-1639
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BL-L1015-2011-1º-Período [36623658].PDF
Jan. 12, 2012
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-1993
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BL-L1015-2011-1º-Período [36624320].PDF
Jan. 12, 2012
French
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-2347
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BL-L1015-2011-1º-Periodo [36624903].PDF
Jan. 12, 2012
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-2705
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BL-L1015-2011-1º-Period [36625469].PDF
Jan. 12, 2012
English
https://www.iadb.org/document.cfm?id=EZSHARE-839592141-104
Procurement Plan
Project Procurement Plan - Integrated Water and Sanitation Program for Placencia Peninsula [36485271].PDF
Oct. 25, 2011
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-1235
Project Monitoring Report ( Public version)
Report for Publication_PMR-_BL-L1015-2010-2º-Period [36313050].PDF
Aug. 10, 2011
English
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-49
Project Monitoring Report ( Public version)
Relatório para publicação_PMR-_BL-L1015-2010-2º-Período [36310004].PDF
Aug. 10, 2011
Portuguese
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-840
Project Monitoring Report ( Public version)
Informe para Publicación_PMR-_BL-L1015-2010-2º-Periodo [36312475].PDF
Aug. 10, 2011
Spanish
https://www.iadb.org/document.cfm?id=EZSHARE-1856068004-445
Project Monitoring Report ( Public version)
Rapport pour Publication_PMR-_BL-L1015-2010-2º-Período [36311892].PDF
Aug. 10, 2011
French
https://www.iadb.org/document.cfm?id=EZSHARE-2056220512-128
Loan Contract
Integrated Water and Sanitation Programme for the Placencia [40018125].PDF
Dec. 31, 1899
English
https://www.iadb.org/document.cfm?id=EZSHARE-839592141-74
Loan Proposal
Integrated Water and Sanitation for the Placencia Peninsula [35517507].PDF
Dec. 31, 1999
English
https://www.iadb.org/document.cfm?id=EZSHARE-839592141-75
Loan Proposal
Programa Integrado de Agua y Saneamiento para la Peninsula de Placencia [35517533].PDF
Dec. 31, 1999
Spanish
Preparation Phase
https://www.iadb.org/document.cfm?id=EZSHARE-839592141-33
Project Profile
Integrated Water and Sanitation Programme in Placencia [35280288].PDF
Dec. 31, 1999
English

Have an Environmental or Social issue related to IDB projects? File a Complaint

Jump back to top