MICI-BO-2011-013
Bolivia - Bolivia - Santa Barbara-Rurrenabaque Northern Corridor Highway Improvement Program
Country: Bolivia
Reception date: February, 28 2011
Current Status: Closed
Requesters:
Bolvian Forum on Environment and Development - FOBOMADE
Summary of the Request
The “Foro Boliviano sobre el Medio Ambiente y Desarrollo” submitted a Request concerning the negative environmental and social impacts that the construction and access of a bridge connecting Rurrenabaque and San Buenaventura in Bolivia could cause to Rurrenabaque and its inhabitants. In addition, the Request alleged the inadequate management of information and of the public consultation process, during which the community’s concerns had not been addressed and the different designs of the bridge project had not been based on social, environmental and urban planning analyses by the Executing Agency, the “Administradora Boliviana de Carreteras” (ABC).
MICI actions
After gathering comments from the Requesters and the Administration, the Panel submitted to the Board of Executive Directors for their consideration, its Recommendation to conduct a Compliance Review and its Terms of Reference. After considering the document, on December 22nd 2014, the Board of Executive Directors decided not to approve the proposed investigation since the bridge, motive of the Request, was not being financed by the Bank. Consequently, processing of Request BO- MICI001-2011was concluded and the case closed by the ICIM.
Less - 2013
In January 2013, the Government of Bolivia informed the Bank’s Representative of its decision to reassign the funds from Loan 1833/SF-BO, previously allocated for the construction of the Rurrenabaque-San Buenaventura Bridge. On March 25, 2013, Bank Management officially notified the Requesters that, in view of the Government’s decision, the Bank would no longer be funding the construction of the bridge or the studies on possible alternative sites for the bridge. Consequently, the Project Ombudsperson terminated the Consultation Phase owing to the lack of adequate conditions for dialogue. The Consultation Phase Report was issued on April 22, 2013.The Requesters then asked that their Request be considered for a Compliance Review, and on October 29, 2013, the Panel Chairperson declared the Request eligible for this Phase.
Less - 2012
The Request was declared eligible for the Consultation Phase, as it was concluded during the assessment stage that the concerns expressed were related to an insufficient analysis of alternatives for the design and location of the bridge, and of the indirect impacts in the Environmental Impact Study, as well as to the lack of consideration in the Environmental Management Plan of actions to mitigate or compensate for those impacts, in addition to an inadequate consultation process. Although there was no opposition to the construction of the bridge from any group consulted, there was opposition to its proposed location and access routes. Additionally, when the MICI entered the process, the relationship and trust among the Parties was already notably eroded. This led the Parties to condition their amenability to the dialogue. In June 2012, the Parties signed an agreement within the framework of the dialogue process, stipulating that the “ABC” would study a second alternative location for the bridge and its access routes. The Requesters agreed to establish a technical committee, including representatives from both towns, responsible for analyzing the second alternative and following up with the new studies. In November 2012, the Parties approved the final text of the contract between the “ABC” and the consulting firm “PROES” to carry out the studies of the second alternative location. The Bank expressed its approval of the terms of the agreement.
B
Santa Bárbara-Rurrenabaque Northern Corridor Highway Improvement
TRANSPORT
Loan Operation
USD 120,000,000.00
Steps and milestones | Date | Remarks | Documents |
---|---|---|---|
INTAKE | |||
Filing of Request | |||
Request received by Executive Secretariat
|
February 28, 2011 |
|
|
Registration | |||
Notice of registration of Request and transfer to the Consultation Phase
|
March 15, 2011 |
|
|
CONSULTATION PHASE | |||
Eligibility for the Consultation Phase | |||
Eligibility due date
|
April 7, 2011 | (15 business days from date of transfer to the Consultation Phase) |
|
Eligibility revised due date
|
April 13, 2011 | Extension from 7-Abr-11 to 13-Abr-11 |
|
Issuance of Eligibility Memorandum
|
April 13, 2011 | The Eligibility Memorandum is published after it is distributed to the Board of Executive Directors. |
|
Eligibility memorandum distributed to the Board of Executive Directors
|
April 26, 2011 |
|
|
Assessment | |||
Assessment due date
|
August 13, 2011 | (120 calendar days from the date of issuance of the eligibility memorandum) |
|
Issuance of Assessment Report
|
August 22, 2011 | The Assessment Report is published after it is distributed to the Board of Executive Directors. |
|
Assessment Report distributed to the Board of Executive Directors
|
September 12, 2011 |
|
|
Consultation Exercise | |||
Beginning of the consultation exercise
|
August 24, 2011 |
|
|
Issuance of Consultation Phase Report
|
April 22, 2013 | The Consultation Phase Report is published after it is distributed to the Board of Executive Directors. |
|
Consultation Phase Report distributed to the Board of Executive Directors
|
May 8, 2013 |
|
|
Closing of the Consultation Phase | |||
File transferred to the Executive Secretariat |
April 25, 2013 |
|
|
COMPLIANCE REVIEW PHASE | |||
Compliance Review Intake | |||
Notification received by Executive Secretariat indicating/ratifying Requester(s) desire to have a Compliance review by the Panel
|
July 2, 2013 | The document is available only in Spanish. |
|
Transfer Notice | |||
Notice of transfer
|
July 2, 2013 |
|
|
Eligibility for the Compliance Review Phase | |||
Eligibility due date
|
July 25, 2013 | (15 business days from date of transfer to the Compliance Review Phase) |
|
Eligibility revised due date
|
November 4, 2013 | First extension: August 15, 2013. Second extension: November 4, 2013. |
|
Issuance of Eligibility Memorandum
|
October 29, 2013 | The Eligibility Memorandum is published after it is distributed to the Board of Executive Directors. |
|
Eligibility Memorandum distributed to the Board of Executive Directors
|
November 6, 2013 |
|
|
Terms of Reference (TORs) | |||
Issuance of draft recommendation and TORs
|
February 20, 2014 |
|
|
Due date for Management and Requester’s comments to draft recommendation
|
March 27, 2014 | (20 business days for submission of comments) Original date for submission of comments: 20 March 2014 |
|
Submission of the final document to the Board of Executive Directors for consideration
|
October 21, 2014 |
|
|
Determination of the Board of Executive Directors to conduct a Compliance Review
|
December 22, 2014 |
|
|