Can’t find a document?
Request Information
PR-L1173 : Expansion of the High Voltage Transmission System and Energy Efficiency Actions
Project Status: Implementation
The specific objectives of the first operation under the CCLIP are (i) to support the improvement of the reliability and efficiency of the high-voltage transmission system; and (ii) to improve the energy efficiency in ANDE's commercial buildings and public lighting.
Project Detail
Número do Projeto
PR-L1173
Approval date
May 06, 2020
Project Country
Paraguay
Project Sector
ENERGY
Project Subsector
NEW POWER DISTRIBUTION & TRANSMISSION PROJECTS
Tipo de Projeto
Loan Operation
Project Lending Type
SG
Project Modality
ESP (Specific Investment Operation)
Project Facility Type
Environmental and social impact category
B
Project Status
Implementation
Operation Number
5023/OC-PR
Financial Information
Número do Projeto
PR-L1173
Project Status
Implementation
Financiamento BID
Financing type
FFF
Fund
Ordinary Capital
Reporting currency
USD - United States Dollar
Reporting date
May/29/2023
Roles & Responsibilities
Contract signature date
Aug/18/2021
Project Information
Total Cost
USD 155,000,000
Country counterpart financing
USD 0
Amount
USD 70,000,000
Preparation
Título
Type
Número do Projeto
Date Published
Public Consultation Report
PR-L1173
March 09, 2020
Environmental Impact Assessments
PR-L1173
January 31, 2020
Strategic Environmental Assessments
PR-L1173
January 30, 2020
Environmental and Social Management Plan
PR-L1173
January 30, 2020
Resettlement Plans
PR-L1173
January 30, 2020
Environmental Impact Assessments
PR-L1173
January 30, 2020
Environmental Impact Assessments
PR-L1173
January 30, 2020
Environmental Analyses
PR-L1173
November 27, 2019
Environmental Analyses
PR-L1173
November 27, 2019
Environmental Impact Assessments
PR-L1173
November 27, 2019
Environmental Analyses
PR-L1173
November 27, 2019
Project Profile
PR-L1173
November 26, 2019
Approved
Título
Type
Número do Projeto
Date Published
Loan Contract
PR-L1173
May 18, 2020
Loan Contract
PR-L1173
May 18, 2020
Loan Proposal
PR-L1173
April 24, 2020
Loan Proposal
PR-L1173
April 24, 2020
Implementation
Título
Type
Número do Projeto
Date Published
Project Monitoring Report ( Public version)
PR-L1173
February 08, 2023
Project Monitoring Report ( Public version)
PR-L1173
August 15, 2022
Project Monitoring Report ( Public version)
PR-L1173
February 28, 2022
Project Monitoring Report ( Public version)
PR-L1173
July 20, 2021
Project Monitoring Report ( Public version)
PR-L1173
March 09, 2021