MICI-BID-CO-2022-0184

Metro of Bogota First Line - First Tranch — Request IV

Country: Colombia

Reception date: February, 15 2022

Current Status: Open

Requesters:

8 residents and merchants of the city of Bogota, led by Mr. Carlos Adrián Flórez García.

Summary of the Request

The Request describes a potential damage to the Requester's property and living conditions derived from the expropriation of his residential property, within the framework of the Project.

The Requester alleges an incorrect appraisal of his property, since the amount offered would be less than an appraisal cited by the Requester. On the other hand, he argues that the loss of profits was not considered and that the expropriation would be depriving him of his livelihood.

The Request claims that no payment derived from the expropriation has been made, as well as inconsistencies in the notification process and noncompliance with the Project's General Resettlement Plan.

This Request is related to the compliant MICI-BID-CO-2021-0179.

Recent actions

On May 6, 2022, MICI determined that the Request was eligible because it met all the eligibility criteria established in the MICI Policy. This determination of eligibility is not an assessment of the merits of the Request or of the issues contained therein.

The Request was transferred to the Consultation Phase as per the decision of the Requesters.

Past actions

On February 22, 2022, the MICI granted the Requesters a maximum period of 10 business days to submit the information required to continue with the Request process (paragraph 20 of the MICI Policy). The term expires on March 8, 2022.

On March 11, 2022, the MICI notified the Requesters and Management of the registration of the Request.

Project Number:

CO-L1234


Environmental Category:

A


Project Name:

Metro of Bogota First Line - First tranch


Sector:

TRANSPORT


Project Type:

Loan Operation


IDB Financing:

USD 70,000,000


Registration
Registered
Eligibility
Eligible
Assessment
Consultation Process
Monitoring
Recommendation for a CR and ToRs
Investigation
CR Report
Monitoring

Registration

Consultation Phase (CP)

Compliance Review Phase (CRP)

Chronology and documents

Steps and milestones Date Remarks Documents
Registry

33112

Request Receipt

2022-02-15

33113

Notice of Registration

2022-03-11

5 business days from the date of receipt of the Request or 15 business days when further information is required from the Requesters.
Elegibility

33235

Management Response

2022-04-11

21 business days from the date of notice of registration. The response will be published as an annex to the Eligibility Memorandum.

33236

Eligibility due date

2022-05-10

21 business days from the date of receipt of Management Response or 45 business days after the Suspension is granted.

33806

Eligibility Memorandum Public Disclosure

2022-05-18

As per the Access to Information Policy (OP-102) the disclosure of this document is done simultaneous to its distribution to the Board of Executive Directors.
Consultation phase
Assessment

33807

Deadline for Assessment

2022-07-06

40 business days from the date of issuance of the eligibility memorandum.