We are the independent accountability office of the IDB Group. We manage complaints about possible environmental and social harm arising from Group-financed projects.
Strategic Program for Transportation Infrastructure and Logistics in Paraná
Country: Brazil
Reception date: September, 4 2018
Current Status: Closed
Requesters:
96 residentes de Bairro Riozinho, Engenheiro Gutiérrez, Irati en Paraná, Brasil.
The Request describes impacts on the quality of life of the Requesters linked to the construction of the viaduct (interseção em dois níveis) of the São Mateus do Sul bridge that is part of the Program. Specifically, the Requesters allege that the construction of the route reduced access to the communities where the Requesters live. Also, they highlight an increase in traffic, which would have affected their daily activities. Finally, they report a lack of consultation processes with the affected communities and a lack of information available on the Program.
On September 11, MICI terminated the administrative process of the Request for the Requesters to establish initial contact with the Project Team and seek to respond to their concerns with them as a first instance. The Requesters were informed about the possibility of resubmitting their Request if they consider that their concerns have not been addressed within a reasonable period of time.
A
Strategic Program for Transportation Infrastructure and Logistics in Paraná
TRANSPORT
Loan Operation
USD 235,000,000
Registration
Not registered
|
Eligibility
|
Assessment
|
Consultation Process
|
Monitoring
|
Recommendation for a CR and ToRs
|
Investigation
|
CR Report
|
Monitoring
|
Registration |
Consultation Phase (CP) |
Compliance Review Phase (CRP) |
Steps and milestones | Date | Remarks | Documents |
---|---|---|---|
Registry | |||
Request Receipt |
2018-09-04 |
||
Notice of Registration |
2018-09-11 |
5 business days from the date of receipt of the Request or 15 business days when further information is required from the Requesters. | |
Closing date of MICI process |
2018-09-11 |