MICI: We work with you to make development better
We are the independent accountability office of the IDB Group. We manage complaints about possible environmental and social harm arising from Group-financed projects.
Tietê Várzeas Program - Request V
Country: Brazil
Reception date: July, 25 2017
Current Status: Closed
Requesters:
A group of residents from the city of Guarulhos, Brazil. The Requesters are represented before MICI by the Public Defender’s Office of the State of São Paulo.
The Request raises potential harms related to the resettlement component that is part of the "Tietê Várzeas Program" Program (BR-L1216). Specifically, it alleges damages to the property and living conditions of the resettled families, as well as impact on the area’s social fabric. In addition, the Request points out a lack of public consultations regarding the housing for those affected by the resettlement.
In addition, they requested MICI to provide loan information concerning the Program and details about the credit given to the Government of São Paulo by the IDB.
On August 14, MICI closed the Request because the Requesters decided to finalize the process in order to resolve their concerns directly with the corresponding instances within the Inter-American Development Bank.
On July 31, 2017, MICI granted the Requesters a period of 10 business days to send the information required to continue the Request process (paragraph 20 of the MICI policy).
A
Tietê Várzea Program
WATER AND SANITATION
Loan Operation
USD 115,700,000
Registration
Not registered
|
Eligibility
|
Assessment
|
Consultation Process
|
Monitoring
|
Recommendation for a CR and ToRs
|
Investigation
|
CR Report
|
Monitoring
|
Registration |
Consultation Phase (CP) |
Compliance Review Phase (CRP) |
Steps and milestones | Date | Remarks | Documents |
---|---|---|---|
Registry | |||
Request Receipt |
2017-07-25 |
Requests of a confidential nature are not published. | |
Notice of Registration |
2017-08-14 |
5 business days from the date of receipt of the Request or 15 business days when further information is required from the Requesters. | |
Closing date of MICI process |
2017-08-14 |