MICI: We work with you to make development better
We are the independent accountability office of the IDB Group. We manage complaints about possible environmental and social harm arising from Group-financed projects.
Tietê Várzea Program - Request IV
Country: Brazil
Reception date: June, 15 2017
Current Status: Closed
Requesters:
A group of residents of Jardim Izildinha, Guarulhos, Brazil.
The Request raises potential harms related to the resettlement component that is part of the "Várzeas del Tiete" Program (BR-L1216).
This Request is a reactivation by some of the Requesters who filed the Application MICI-BID-BR-2016-0106.
On July 7, 2017, the MICI notified the Requesters that their Request was not registered as one of the exclusions set out in the MICI Policy applied, specifically paragraph 19 (c), which states that neither the Consultation Phase nor the Compliance Review Phase will be applied to Requests that contain particular issues or matters that have been reviewed by MICI, unless justified by new evidence or circumstances not available at the time of the initial Request.
On June 21, 2017, MICI granted the Requesters a 10 business day period to send the information required to continue with the processing of the Request (paragraph 20 of the MICI Policy).
A
Tietê Várzea Program
WATER AND SANITATION
Loan Operation
USD 115,700,000
Registration
Not registered
|
Eligibility
|
Assessment
|
Consultation Process
|
Monitoring
|
Recommendation for a CR and ToRs
|
Investigation
|
CR Report
|
Monitoring
|
Registration |
Consultation Phase (CP) |
Compliance Review Phase (CRP) |
Steps and milestones | Date | Remarks | Documents |
---|---|---|---|
Registry | |||
Request Receipt |
2017-06-15 |
Requests of a confidential nature are not published. | |
Notice of Registration |
2017-07-07 |
5 business days from the date of receipt of the Request or 15 business days when further information is required from the Requesters. | |
Closing date of MICI process |
2017-07-07 |