Water and Sanitation for Small Communities Program - Tranche II (PROAS II)
Country: Argentina
Reception date: June, 21 2021
Current Status: Closed
Requesters:
Confidential.
The Request describes potential environmental harm to the community, as well as patrimonial and health issues for the Requesters, due to the future construction and implementation of the sewage collection and treatment system within the framework of the Project.
Specifically, the Requesters indicate that the system would represent significant environmental damage to the different bodies of water (rivers and lakes), riverbanks, and beaches in the area, which they allege would be contaminated with spills. They add that these bodies of water and beaches are used by both residents and tourists for recreational activities, as well as for the provision of drinking water, so any alteration of these could cause significant damage to health.
The Request adds that the Environmental Impact Study generated would be incomplete by not correctly detecting the area impacted by the Project and its environmental implications in protected areas and vulnerable ecosystems, as well as by not offering viable alternatives for its implementation. In the same way, it indicates that it has not received complete information about the Project, nor has it been correctly consulted about it.
Lastly, the Requesters warn of potential damage to their property since several of the contemplated works, such as pumping stations and pipelines, would be planned on private property and not on public domain properties, as currently reported.
October 14th, 2021: Due to the Executing Agency’s decision not to apply for Project eligibility, the Inter-American Development Bank will not finance the sewage collection and treatment system. In this context, MICI does not have matters to address as there is no project financed by the Bank that could cause the damage alleged in the Request. Therefore, the management of Request MICI-BID-AR-2021-0168 has officially concluded.
For more information, please refer to MICI’s public update on the matter: https://www.iadb.org/en/node/31671
On June 22, 2021, MICI notified the Requesters and IDB Management of the registration of the Request.
On August 23, 2021, MICI determined that the Request was eligible because it met all the eligibility criteria established in the MICI Policy. This determination of eligibility is not an assessment of the merits of the Request or of the issues contained therein.
The Request was transferred to the Consultation Phase as per the decision of the Requesters.
B
Water and Sanitation for Small Communities Program - Tranche II (PROAS II)
Water and sanitation
Loan Operation
USD 200,000,000
Registration
Registered
|
Eligibility
Eligible
|
Assessment
|
Consultation Process
|
Monitoring
|
Recommendation for a CR and ToRs
|
Investigation
|
CR Report
|
Monitoring
|
Registration |
Consultation Phase (CP) |
Compliance Review Phase (CRP) |
Steps and milestones | Date | Remarks | Documents |
---|---|---|---|
Registry | |||
Request Receipt |
2021-06-21 |
Requests of a confidential nature are not published. | |
Notice of Registration |
2021-06-22 |
5 business days from the date of receipt of the Request or 15 business days when further information is required from the Requesters. | |
Elegibility | |||
Management Response |
2021-07-22 |
21 business days from the date of notice of registration. The response will be published as an annex to the Eligibility Memorandum. | |
Eligibility due date |
2021-08-23 |
21 business days from the date of receipt of Management Response or 45 business days after the Suspension is granted. | |
Eligibility Memorandum Public Disclosure |
2021-09-09 |
As per the Access to Information Policy (OP-102) the disclosure of this document is done simultaneous to its distribution to the Board of Executive Directors. | |
Consultation phase | |||
Assessment | |||
Deadline for Assessment |
2021-10-22 |
40 business days from the date of issuance of the eligibility memorandum. | |
Consultation Phase Closure | |||
Closing date of MICI process |
2021-10-14 |