We are the independent accountability office of the IDB Group. We manage complaints about possible environmental and social harm arising from Group-financed projects.
Urban Municipal Infraestructure Program
Country: Argentina
Reception date: February, 9 2021
Current Status: Closed
Requesters:
Confidential
The Request describes potential economic and property harms of the Requesters for the works in the downtown area of the city contemplated in the Program.
Specifically, the Requesters allege that the paving, drainage, and tree planting works that have been carried out have been carried out without prior information and consultation with the impacted population, which, in addition to having been paralyzed for several months, has prevented the merchants from can open their businesses on a regular basis. As a consequence of the above, they warn of damage to their economy and dismissal of workers.
Likewise, the Request also contains an allegation regarding irregularities in the bidding for the works, which is outside the scope of the Mechanism, for which reason this matter was referred to the Bank's Procurement Office.
On May 5, 2021, the MICI Director determined that the Request was not eligible as it did not meet the eligibility criteria established in the MICI-IDB Policy, as the Requesters informed the MICI of their decision to withdraw from the entire process with the Mechanism, thus withdrawing their Request, and informed that they would continue with the management of their claim through other corresponding channels. After notifying the Parties of this decision, the process was concluded.
On March 4, 2021, MICI notified the Requesters and Bank Management of the registration of the Request.
On February 16, 2021, the MICI granted the Requesters a maximum period of 10 business days to submit the information required to continue with the Request process (paragraph 20 of the MICI Policy). The term expires on March 2, 2021.
B
URBAN MUNICIPAL INFRAESTRUCTURE PROGRAM
URBAN DEVELOPMENT AND HOUSING
Loan Operation
USD 180,000,000
Registration
Registered
|
Eligibility
Not eligible
|
Assessment
|
Consultation Process
|
Monitoring
|
Recommendation for a CR and ToRs
|
Investigation
|
CR Report
|
Monitoring
|
Registration |
Consultation Phase (CP) |
Compliance Review Phase (CRP) |
Steps and milestones | Date | Remarks | Documents |
---|---|---|---|
Registry | |||
Request Receipt |
2021-02-09 |
Requests of a confidential nature are not published. | |
Notice of Registration |
2021-03-04 |
5 business days from the date of receipt of the Request or 15 business days when further information is required from the Requesters. | |
Elegibility | |||
Management Response |
2021-04-06 |
21 business days from the date of notice of registration. The response will be published as an annex to the Eligibility Memorandum. | |
Eligibility due date |
2021-05-05 |
21 business days from the date of receipt of Management Response or 45 business days after the Suspension is granted. | |
Eligibility Memorandum Public Disclosure |
2021-05-19 |
As per the Access to Information Policy (OP-102) the disclosure of this document is done simultaneous to its distribution to the Board of Executive Directors. | |
Closing date of MICI process |
2021-05-19 |