MICI: We work with you to make development better
We are the independent accountability office of the IDB Group. We manage complaints about possible environmental and social harm arising from Group-financed projects.
Integrated Urban Solid Waste Management
Country: Argentina
Reception date: December, 20 2014
Current Status: Closed
Requesters:
Confidential.
The Request alleged possible breaches of the Bank's procurement policies, potential corruption actions and prohibited practices.
The Request was not registered because it dealt exclusively with issues of corruption and prohibited practices related to the Bank's procurement policies, which are not within the scope of the MICI (paragraphs 19 and 20 of the MICI Policy).
Accordingly, the Request was transferred to the Office of Institutional Integrity and the documentation was classified as confidential as it was not under the scope of the Mechanism.
B
Solid Waste Management Program for Touristic Municipalities
WATER AND SANITATION
Loan Operation
USD 58,219,727
Registration
Not registered
|
Eligibility
|
Assessment
|
Consultation Process
|
Monitoring
|
Recommendation for a CR and ToRs
|
Investigation
|
CR Report
|
Monitoring
|
Registration |
Consultation Phase (CP) |
Compliance Review Phase (CRP) |
Steps and milestones | Date | Remarks | Documents |
---|---|---|---|
Registry | |||
Request Receipt |
2014-12-20 |
Requests of a confidential nature are not published. | |
Notice of Registration |
2014-12-22 |
5 business days from the date of receipt of the Request or 15 business days when further information is required from the Requesters. | |
Closing date of MICI process |
2014-12-22 |