MICI-BR-2015-0090

Mario Covas Rodoanel Project - Northern Section - Request II

Country: Brazil

Reception date: April, 1 2015

Current Status: Closed

Requesters:

Confidential. 

Summary of the Request

The Request alleged possible damages in the house where the family of the Requester lived, due to the construction of the highway.

The Requester alleged that his property should be considered eligible for the expropriation program.

Recent actions

On April 4th, 2015, the MICI granted a maximum term of 10 business days to the Requester to submit the additional required information for the processing of the Request.

Within that period, the Requester informed the MICI that he had not contacted Management and that he was going to proceed to do so. In case of no response, he had the intention of submitting a Request to the Mechanism.

The Request was not registered for not having received the requested information within the 10 business days. Thus, the processing of the Request at that time was terminated.

Recently, the Requester informed the MICI that the Executing Agency was taking care of his case.

Past actions

Project Number:

BR-L1296


Environmental Category:

A


Project Name:

Mario Covas Rodoanel Project - Northern Section


Sector:

TRANSPORT


Project Type:

Loan Operation


IDB Financing:

USD 1,122,200,458


Registration
Not registered
Eligibility
Assessment
Consultation Process
Monitoring
Recommendation for a CR and ToRs
Investigation
CR Report
Monitoring

Registration

Consultation Phase (CP)

Compliance Review Phase (CRP)

Chronology and documents

Steps and milestones Date Remarks Documents
Registry

24632

Request Receipt

2015-04-01

Requests of a confidential nature are not published.

24634

Notice of Registration

2015-04-20

5 business days from the date of receipt of the Request or 15 business days when further information is required from the Requesters.

24635

Closing date of MICI process

2015-04-20