MICI-BID-BR-2016-0109

Mario Covas Rodoanel Project - Northern Section - Request IV

Country: Brazil

Reception date: August, 10 2016

Current Status: Closed

Requesters:

Three residents of the Jardim Itatinga, São Paolo

Summary of the Request

The Request alleges harm in the quality of life of the Requesters by the proximity of their homes to the construction of the highway. It also alleges that the residents’ properties should have been considered eligible for expropriation.

Recent actions

On September 1, 2016, MICI concluded the administrative process given that the additional information required was not received by the deadline.

Past actions

On August 15, 2016, MICI granted the Requester a maximum of 10 business days to submit additional information required to process the complaint.

Project Number:

BR-L1296


Environmental Category:

A


Project Name:

Mario Covas Rodoanel Project - Northern Section


Sector:

TRANSPORT


Project Type:

Loan Operation


IDB Financing:

USD 1,122,200,458


Registration
Not registered
Eligibility
Assessment
Consultation Process
Monitoring
Recommendation for a CR and ToRs
Investigation
CR Report
Monitoring

Registration

Consultation Phase (CP)

Compliance Review Phase (CRP)

Chronology and documents

Steps and milestones Date Remarks Documents
Registry

22248

Request Receipt

2016-08-10

Requests of a confidential nature are not published.

22249

Notice of Registration

2016-09-01

5 business days from the date of receipt of the Request or 15 business days when further information is required from the Requesters.

24611

Closing date of MICI process

2016-09-01