Basic Sanitation Program for the Guanabara Bay Basin



                                     BRAZIL


SECTOR:                 Sanitation

PROJECT NAME:           Basic Sanitation Program for the Guanabara Bay Basin,
                        Phase I
                        (782/OC-BR; 916/SF-BR)

TOTAL COST:             $793 million

FINANCING:
      IDB               $350.0 million
    LOCAL               $148.8 million
    OTHER               $294.2 million    cofinancing from the Overseas Economic
                                          Cooperation Fund (OECF) of Japan

DATE OF APPROVAL:       November 17, 1993

GENERAL DESCRIPTION:    The general objectives of the program are to: (a) clean
                        up the Guanabara Bay and adjacent basin area; (b) improve
                        the quality of life of the 7.3 million residents of the
                        basin; and (c) strengthen local government institutions
                        whose activities can positively affect the bay.

                        Six subprojects will be executed:  (a) sewage collection
                        and treatment, including treatment plants, collectors,
                        trunk lines and connections in the bay's most heavily
                        populated areas; (b) potable water supplies, including
                        pumping stations, distribution tanks and networks;
                        (c) solid waste collection and disposal, including trash
                        collection, rehabilitation of solid-waste transfer sta-
                        tions, recycling and incineration plants, as well as
                        institutional strengthening for municipalities in solid
                        waste collection and disposal and in supervision of
                        private firms; (d) canal and river drainage, including
                        works to prevent flooding; (e) complementary environ-
                        mental programs to control industrial contamination,
                        monitor environmental conditions in the bay and provide
                        environmental education for the area population; and
                        (f) digital mapping and municipal institutional
                        development.

CIVIL WORKS:            The program includes the following contracts for works over
                        a five-year period: (a) construction of sewage treatment
                        plants at Sao Goncalo and Ilha de Paqueta; (b) expansion of
                        the sewage treatment plant at Ilha do Governador;
                        (c) improvements to the Icarai sewage treatment plant; (d)
                        construction of underwater outfalls at Icarai and Paqueta;
                        (e) construction of approximately 727,000 meters of collector
                        networks and 59,000 meters of trunk collectors in the Sao
                        Goncalo, Ilha do Governador, Pavuna and Paqueta systems; (f)
                        sectorization of the water supply system in Baixada Fluminense
                        and Sao Goncalo, with construction of approximately 373,000
                        meters of network with pipes of different diameters, and an
                        increase of 180,000 m3 of water reserve capacity at 10
                        reservoirs; (g) installation of water meters and implementation
                        of an operations development project; (h) construction of a
                        sanitary landfill at Xerem for final disposal of sludge from the
                        existing sewage-treatment plant and others to be built in the
                        metropolitan region of Rio de Janeiro; (i) construction in 29
                        favelas in the Guanabara Bay basin of approximately 62,800 meters
                        of water supply systems and 121,700 meters of sewage collectors;
                        (j) macro-drainage works in the Acari River basin; (k) improved
                        collection of solid waste and con-struction of treatment plants
                        and sanitary landfills in the municipalities of Nilopolis, Duque
                        de Caxias, Sao Joao de Meriti, Mage, Sao Goncalo and Niteroi;
                        and (l) digital mapping and complementary environmental programs,
                        including procurement of equipment and services.

GOODS AND EQUIPMENT:    About 535,000 water meters, equipment for the solid waste
                        component and other goods necessary for program execution
                        will be procured through international public bidding.

CONSULTANTS:            Short-term consultants will be hired using local counter-
                        part funds.

EXECUTING AGENCY:       Companhia Estadual de Agua e Esgotos (CEDAE)

ADDRESS:                Rua Sacadura Cabral, No. 103
                        Rio de Janeiro, R.J., Brasil
                        Telephone:  (55-21) 253-1810/253-1898
                        Fax:        (55-21) 233-5805
                        Contact:    Mr. Tito Ryff
                                    Comissþo Coordenadora para Execu‡þo do
                                    Programa de Despolui‡þo da Baía de
                                    Guanabara (CODEC)